Infra Lead at Surbana Jurong
  • Saudi Arabia - Riyadh
  • My current job since July 2022

Currently, in Riyadh with Surbana Jurong International Multi Disciplinary Consultant as an infra lead engineering manager for NEOM Trojena Lake Project (started Jul. 2022).
My work scopes as an Engineering Manger Infra Leader is to ensure all design deliverables of roads, wet & dry utilities, Mobility, Mobility Infrastructure structure, tunnels, solid waste and utility buildings for the NEOM Trojena infra project have been submitted on the agreed schedule following specification and fulfilling the requirements and standard NEOM procedures. Coordinating among design lead disciplines and firming up the NEOM-PMC requirements. Attending interface meeting with other stakeholders and PMC-NEOM in order to get the necessary interfacing information’s. Attending internal meetings as well as progress meetings with NEOM-PMC. Conducting presentations to PMC/NEOM whenever required for design concept optioneering and other issues that raised. Ensures RFI correspondence with PMCM-NEOM are raised for any information required also putting safety in design as per NEOM procedure as a priority. I ensured interdisciplinary checked carried out for the proposed design prior to submission of deliverables. I also ensures optioneering and value engineering carried out during conceptual stage of design. I also following up wit design leads on issues and resolving them as well as meeting date lines and submission of drawings register accordingly. I’m also being a part of the team to daft the scopes of work and identifying deliverables and drafting base line program.

Project Manager at Gamuda Engineering
  • Malaysia - Kuala Lumpur
  • July 2017 to June 2022

Project: KVMRT-SSP Metro Line, Underground station building work, Kg.Baru station Building. (2 TBMs mine through) work associated with tunnel team. (Design and Build)

Employer: Gamuda Engineering
Position: Project Manager
Period: July 2017- June 2022
Cost: 6.8b AU$.
The Station Building in brief:
The footprint of the proposed station fells on the busy road of Kg Baru Road, Kuala Lumpur and overlapping few buildings and bungalows which were demolished accordingly. An early plan for road diversion and m&e utilities relocation has been planned by me and approved by local authorities in order to create the workspace for the station and allows the subcontractor to mobilize and start the work. Upon diverting the m&e utilities out of the station box boundaries, Diaphragm wall activities shall be started in order to create the station box followed by station box excavation and RC work. M&e fit out and Architect finishes shall be started wherever few zones of RC work completed and ready to receive such finishes and fit out. However, two TBM’s planned to mine through the station while the station undergoing construction and I provided and complied tunnel and team with all facilities and we have coordination meetings. The station excavation work shall be resumed once the TBMs has broken out of the station walls and the station work shall continue till the completion and station team shall interface with tunnel work as well as track work to complete the work stage by stage as scheduled. First access would be track access followed by power on.

My scopes and responsibilities as a project manager are as below:

1. Diaphragm wall installation, Soil investigations, Excavation and RC work of the station building, it’s a semi top-down and bottom-up construction with the use of steel structing.

2. M&E work (temporary and permanent) which include installation of 33kv switch gears and transformers, Chillers installations, AHU installation, Fire system, Audio system, Auto-gates installations, 10 lifts & 16 escalators, fire &water tanks installation, cable laying, sewerage &drainages, testing and commissioning and handing over to related authorities.

3. Enforcing safety, health and environment rules at site in line with the MRT SHE procedure and policy. It’s a very high and stringent requirement and we won The Sord, British safety award on 2018 for the best safety health and environment performance.

4. Responsible for architecture &finishes work and compliance to specifications and client satisfaction. Ensures all materials and methodologies are in line with requirement.
5. Ensuring site activities are ahead of scheduled and properly addressed.

6. Liaising with stakeholders, local authorities and other department to ascertain compliance and/or obtains consent.

7. Monitoring spending and ensures it’s within budget. presenting budget to top management and highlighting issues and forecast.

8. Attending meeting with client, consultant, suppliers and subcons.

Project Manager at Gamuda Engineering
  • Malaysia
  • April 2013 to July 2017

Project: KVMRT-SBK Metro Line, Underground station building work, Pasar Seni station building. (4 TBMs retrieved) Tunnel associated work (Design and Build)

Employer: Gamuda Engineering
Position: Project Manager
Period: April 2013- July 2017
Cost:4.8b AU$.

The Station Building in brief:
The footprint of the proposed station falls on the busy road of Pasar Seni, Kuala Lumpur and overlapping few two hotel buildings, each one is 12 storey with 3 levels basement which needs to be demolished. An early plan for road diversion and m&e utilities relocation has been planned and approved by local authorities in order to create the workspace for the station box and allows the subcontractor to mobilize and start the work. Upon diverting the m&e utilities out of the station box boundaries, Diaphragm wall activities shall be started in order to create the station box followed by station box excavation and RC work. M&e fit out and Architect finishes shall be started wherever few zones of RC work completed and ready to receive such finishes and fit out. However, four TBM planned to be retrieved from the station thus the base sunken slab must be completed prior to TBMs breaks in and I have coordinated the wor with tunnel teams and attended meeting with them as well as provided them necessary supporting facilities to demob and dismantle the TBM’s.


Role and responsibilities as a project manager as follow:

1. Responsible for temporary works such as utilities diversion, ground anchors and struts installation, demolition of existing multi-storey buildings and jet grouting work.
2. Deep foundation work (diaphragm walls), RC work and associated excavation work for the station box. My underground station is a semi bottom up & top-down construction method.
3. Water proofing work which is a vital item for the underground work.

4. Temporary M&E work which involve temporary power supply, lighting and ventilation.

5. Responsible for the architect work and building services installation (ABWF).

6. Responsible for the permanent M&E work and progress of work and planning and delivery of M&E items to site. These items include installation of 33kv switch gears and transformers, Chillers installations, AHU installation, Fire system, Audio system, Auto-gates installations, 9 lifts & 14 escalators, fire &water tanks installation, cable laying and sewerage &drainages and their associated tanks, pits and pumps

7. Responsible of planning for the overall activities and monitor the progress as per master program.

8. Assist and coordinate the work with the TBM teams in order to facilitate the TBM break thru and retrieval work.

9. Ensure compliance to S.H.E rules and regulation at site.

10. Liaise with the sub-contractors, Consultant, client, suppliers and third parties in order to ensure smooth progress.

Construction Manager at Gamuda Engineering
  • Malaysia
  • October 2007 to April 2013

Project: Electrified Double Track Project between Ipoh to Padang Besar, N2 Package between Alor Star to Arau 38km (Design and Build)
Employer: Gamuda Engineering
Position: Construction Manager
Period: Oct. 2007- April 2013
Cost:9b AU$

My scopes of work as a construction manager are as below:

1. Roads & Bridges construction: in my package I have constructed 7 nos. Of fly-overs, the foundations are various and depend on soil profile; some are bored piles, spun pile foundations and micro piles. I used two types of beams, post-tensioned T-beams and pre-stressed beams. The work including roads also.

2. Bridges across rivers: in my package I have constructed 11 bridges with bored pile foundation and pre-stressed beams. Temporary steel bridges are used to facilitate the construction.

3. Station Buildings works which includes the followings:

3.1 Temporary station building
3.2 Permanent & Temporary M&E work
3.3 Permanent station works which includes RC & Architecture works
3.4 System works which includes temporary and permanent system works.

4. Mega Earthwork & Excavation and Ground treatment of main lines with associated enabling works. Embankment fill was carried out by using suitable material with layer by layer compaction, each layer to achieve a certain degree of compaction and so on until I reached surcharge level.
Embankment monitoring have been carried out with a designated monitoring skim and certain tolerances.

5. Permanent Under pass (3 nos.), Box culvert and pipe culvert installation (34 nos.).

Assistant Project Manager at Green Resources
  • Malaysia - Ipoh
  • April 2007 to October 2007

Project: Rehabilitation and Strengthening of Track and Associated Work Between
Sungai Siput and Ipoh Station. (Contractor Role)
Employer: Real Green attitude resources Sdn Bhd
Position: A. Project Manager
Period: April 2007-Oct. 2007
Cost:11m AU$

My roles as an acting project manager are as below:

I’m conducting the widening of the existing track (LHS&RHS) with a suitable earth filling and compaction with 1:2 slope of embankment. Relocation of m7e utilities and installation of pipe culverts. I have to make sure that the work is carried out smoothly in terms of consistent earth supplying to site (logistic) and have adequate machineries.
In my scope also I have to coordinate and liaise with Client (KTMB).
I did a precise planning for until completion and I did look ahead schedules
I complied to SHE rules and adhered to local authorities’ requirements.

Projects Construction Manager at KSKK Consotuim
  • Malaysia
  • August 2001 to April 2007

Project: Proposed Road Work Between Rawang to Ipoh, Earthwork, Ground Treatment Work, Structures and Formation preparation, Package 4&5 (TAPAH ROAD YARD CH 238000 TO IPOH CH177900). Malaysia (PMC Role)

Employer: KSKK Consortium Sdn Bhd
Position: Sr Project Engineer- Construction Manager
Period: Aug.2001-April. 2007


PMC Role: “Project completed”

During design and planning stage I was working with the architect and engineers to assist in outlining the requirements and scopes of the projects in line with the client objectives and a value engineering carried out through the process. I also enforce the quality and safety during construction phases and ensure the budget allocated are followed strictly without over run. I also ensures that all the approved construction drawings, shop drawings and quality forms are in place before the works kicked off as well as materials approvals. I also playing a role in identifying the risk associated and create risk management and mitigations. I initiate regular daily routine site inspection and compliance as well as regular reporting to client and meeting with local authorities and meeting their requirements and seeking approvals. Attending meeting with client, contractors, suppliers, and stakeholders. Keeping records of work done and initiate commissioning and handover. The work scopes are as below:

1. Earthwork: this work in general starting with initial survey for ROW and followed with site clearance. The ground treatment for the road shall be conducted prior to the embankment fill. The following are the type of ground treatment techniques and overall quantities used

• Pre and post-treatment Cone penetration test (CPT).
• Surface Vibratory Compaction (SVC), work done so far is 572000 m.sq.
• Vibro-Replacement stone column (VR), work done so far is 250, 000 meter run.
• Prefabricated Vertical Drain (PVD), work done so far is 35, 000 meter run.
• Dynamic Compaction (DC). Work carried out is 24000m.sq
• Earthwork, we carried out some earth work like site clearance, removal and replacement, sand& earth filling for embankment.

1.1 Embankment work: Upon ground treatment completion, the embankment fill shall be started with the use of suitable materials which shall be laid and compacted layer by layer toll the formation finishing level.
1.2 Under pass (2 nos.), Box culvert and pipe culvert (32) : shall be either cast in situ or a precast and such work shall be started upon completion of ground treatment.
1.3 Instrument installation and monitoring.

2. Bridges: I have constructed all bridges in 14 nos. and hand it over to the road authority. T-beam design and prestressed. Foundation was bored piles, spun piles and micro piles used.

Structure Design Engineer at Perunding Bersatu C&S consulting firm
  • Malaysia - Ipoh
  • April 1996 to August 2001

Employer : Perunding Bersatu Ipoh- C&S Consulting Firm
Position: Design Engineer
Period: Jun 1996-Aug.2001

Role and responsibilities:
• Responsible for preparing the preliminary design and issuance of tender drawings
• Responsible for obtaining final design and issuance of construction drawings.
• Responsible of getting approvals from local authorities to the designed items such as LAP (National water department), JKR (national road department), Majlis (manciple council), Bomba (fire department).
• Attending progress and coordination meetings with client.
• Attending site inspection.
• Responding to multiple technical site issues and inquiries.
• Undertaken housing and commercial project design, steel structure design, road & drainage design, main waterpipes and pump house station.
• Responsible of issuance tender drawings and preliminary design
• Issuance of final design
• Supervising draftsmen
• I completed the design for housing project for Lembah Bringing Z 2-11, I contributed to the design of main building and mechanical building, composite structure, for the KLIA Airport project, Also I contributed to the design of PUNB which is 4 storey main building and 10 storey tower. I did the design of Bandar Kinerara housing and commercial projects including main water work and pump house station.
• I designed main infra water main which they are a twin pipes, 900mm, CLMS including steel bridge crossing and pump house station. Miru, Perak, Malaysia

Site Engineer at AlMansoor Contracting
  • Iraq - Basra
  • June 1994 to June 1996

Project: Proposed track line replacement and upgrading between Basra and Umm Qasar, 56 km of track work (Iraq)
Employer: Al-Mansoor Contractor (Railway work-Iraq)
Position: Site Engineer
Period: Mac.1994-April 1996
My scopes are as below:
• Coordination of soil investigation.
• To ensure the track corridor and CL are compatible with design
• Construction of railway bridge work (4 nos)
• Logistic yard is provided and accessible.
• Sleepers laying and rail pulling proceeded following agreed method and procedure.
• Welding and de-stress cycles carried out along installed rail.
• Ballast adjusted and shaped by ballast regulator
• Rail adjusted to designed level with the use of temping machine.

Education

Master's degree, Civil Engineering
  • at University science of Malaysia
  • March 2013

Specialties & Skills

INSTALLATION
CONSTRUCTION
NETWORK OPERATING SYSTEM (NOS)
BRIDGES
LOOKAHEAD
PLANNING
CABLE LAYING
SOFTWARE DEFINED NETWORKING (SDN)
WATER PIPES

Languages

English
Expert