Senior Project Engineer
Jeddah Central Development Company
Total years of experience :10 years, 7 Months
Working as a SMP Piping Engineer IV with Saudi Aramco Project Management Team in Haradh & Hawiyah Compression PL Project Division and my duties are:
• Assuring the compliance of contractors to Aramco standards
• iPlant Administrator
• eReview system Administrator
• Issuing Concurrence letters
• Interacting and arranging meetings with Proponents & contractors.
• Interacting and arranging meetings with EK&RD
• Participating in 90% Model E-review
• Participating in Risk Management meetings
• Participating in 30%, 60%, 90% Model Review Meetings
• Attending weekly progress meetings with contractor
• Escorting contractors in site visits survey or meetings as an PMT
• Oversee contractor site activities using baseline Schedule
• Review contractor monthly invoices.
Working with JACOBS ZATE as a Piping Engineer in MPP Oil project and my tasks are:
• Reviewing Plot Plan
• Reviewing Piping General Arrangement
• Reviewing 3D Model.
• Reviewing Isometric drawings
• Reviewing Pipeline Plan and Profile
• Issuing Safety Instruction Sheets SIS
• Issuing List of Deliverables LOD
• Issuing & responding to Technical Query TQ
• Reviewing Hydrostatic Diagram
• Preparing Material Take off MTO
•Familiar with following standards:
o SAES-L-100, 105, 125, 108, 109, 110 & 410
o SAES-A-202, SAEP-334
o ASME B36.10, B16.34
training in South Korea with GS E&C Corp. as Piping Engineer for a year in UO1 RABIGH II porject
I'm also attended an on-line course with IIT BOMBAY in Piping Engineer since september 2013
Worked as summer trainer for two months at "Najran Gas Power Plant" that belong to SCECO COMPANY
- Bachlore in Mechanical Engineer from KFUPM . (Aug 2011) - Graduation Project: Designing and assembling of a device to calculate the thermal conductivity of bricks in Saudi Arabia.