BMS Project Engineer
Elofoq For Trading & contracting
مجموع سنوات الخبرة :13 years, 5 أشهر
BMS Start up & Commissioning of the Electrical & HVAC systems as per scope of supply and
contractual specification.
- Ensure quality feedback to the engineering and development departments.
- Conduction of site acceptance tests and handover of the scope of supply to customers requirements.
- Generally responsible for implementations and monitoring of all electrical & mechanical works related to
the startup & commissioning of the HVAC System.
- Estimates, prepares and assigns the resources such as manpower, materials, consumables, equipment,
tools, etc., required for all related works prior to execution.
- Plans and analyses all possible construction methodologies and recommends the best options to the
Asst. Project Manager for approval prior to execution at site.
- Interprets construction drawings and studies the contract documents and applicable standards or
specifications prior to execution of any jobs.
- Manages directly and provide engineering and technical supports to all the power and control (BMS &
DDC) of the HVAC work groups at site.
- Plans the execution of all the power & control works related to the HVAC system and coordinates the
works with mechanical and civil groups.
- Coordinates with Client / Consultant’s representatives for any site instructions and inspection of works.
- Assign targets for accomplishments and ensure targets are met on daily basis for all power and control
(BMS & DDC) of the HVAC work groups at site.
- Submits site daily reports, inspection requests, estimates and all applicable monitoring reports on
regular basis or as required.
- Supports the Project Manager in accomplishing all the goals and targets for the power and control (BMS
& DDC) of the HVAC work groups at site.
- Ensures that all the works done are in accordance with the approved construction drawings, contract
documents, project specifications, and all applicable standards whether local, national or international
standards.
- Ensures that all site works are done according to all applicable quality standards.
`
- Directly responsible for the safety of all working groups’ personnel of the project by ensuring that the
project execution will be done according to all applicable health, safety, sanitary and environmental
standards.
- Performs other related duties as may be required by the Project Manager.
Project Value: LE 320 million
Main Contractor: Limak Inşaat
still going on))
Project Value: LE 85 million
Main Contractor: FAS construction.
Responsible for site construction for Mechanical, Electrical & BMS systems.
Submit progress reports to the MEP Project Manager.
`
Design review & Review construction drawings and resolve any discrepancies with Engineering
and / or the Consultant.
Follow up preparing shop drawings, coordination drawings and submittals.
Preparing the method of statement for installation and the procedures of inspection for these
trades (HVAC, Electrical & BMS ) to submit to MEP consultant for approval.
Installation of 2 Generators, 2 transformers, RMU, MDB & ATS .
Carrying out the start up and commissioning of the HVAC system (2 cooling
towers & 72 DX units) and DDC control system in Bien Elkasreen palace
● BMS & HVAC start up & Commissioning Site Engineer : Reporting to Project Manager.
Responsible for site construction for Mechanical, Electrical & BMS systems.
Submit progress reports to the MEP Project Manager.
Design review & Review construction drawings and resolve any discrepancies with Engineering
and / or the Consultant.
Follow up preparing shop drawings, coordination drawings and submittals.
Preparing the method of statement for installation and the procedures of inspection for these
trades (HVAC, Electrical & BMS ) to submit to MEP consultant for approval.
Installation of 1 Generators, 2 transformers, RMU, MDB & ATS .
Carrying out the start up and commissioning of the HVAC system (2 air cooled water chillers
each 75 T.R, 2 fresh air handling units and 149 fan coil units) and DDC system.
● BMS & HVAC start up & Commissioning Site Engineer : Reporting to Project Manager.
Business View (Adminstartion BLD
Client: UNI SON Company.
- Client : TABREED.
- Main- contractor : SLGC.
* Zayed sport city plant phase 3;
contractor : EBCL Bectel
HVAC DX system:
* Asab Gas Development (AGD II) DX system for Non-process building;
Responsible for SCADA system
* Maintenance for hot and cold rolling mill
* Maintenance for hot plate mill automation system
* Maintenance for hot plate mill master drives
* Maintenance for Electrical instruments
o Major Equipment involved in the above mentioned schemes:
•MV & LV Switch gears • Centrifugal and screw Chillers
•Power Transformers • Cooling towers and condensing units
•LV motor control centers • Pumps & Compressors
•MV motor control centers • Fire Alarm & Fire Fighting systems
•Variable frequency drives • Expansion tanks
• Valves & actuators
•UPS & battery chargers • HVAC fully automated control panels
•Programmable logic controllers • Air & water cooled condensing units
•Field instruments (Transmitters & Indicators) • Fan coil units
• Leak detection systems • Duct heaters
• Air Handling units • Humidifiers
• VAVs • Control Panels & Stations
• Various Lighting fixtures, small power & welding sockets
BMS Project Engineer