أحمد مراد, project manager

أحمد مراد

project manager

Masco

البلد
المملكة العربية السعودية
التعليم
بكالوريوس, الهندسة المدنية
الخبرات
20 years, 8 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :20 years, 8 أشهر

project manager في Masco
  • المملكة العربية السعودية - الخرج
  • يونيو 2013 إلى أكتوبر 2016

# working in Masco, position : project manager,
owner :NCMS- MOD (Ministry of Defence)
consultant : Arch. center
Industrial buildings - project value 200 millions SAR.

Job duties:
- Implementation of project management plan for the construction.

- Manage all site activities.

- Dealing with client, designer, consultant and key stakeholders.

- Control of safety, quality as per standards, project duration and contract cost.

- Complete coordination between subcontractors and managing for all trades : civil, electromechanical, finishing..etc.

- Preparation of monthly invoices and getting them approved by consultant.

- Develop culture of continuous improvement.

- Completion of testing & commissioning and handing over of the project.

site manager في Saudi bin laden group
  • المملكة العربية السعودية - الرياض
  • أكتوبر 2007 إلى أبريل 2013

# Working in Saudi bin laden group Position : site manager
Projects:
(1) King Saud University for Health Sciences -Riyadh, SR 12 Billions.
.* consultant : dar al-handasah. Responsible for clinical skills development center -26000m2, deanship building 24000m2, 2nd.floor in children hospital-220000m2 and sports area.
(2) Security and administration buildings, ministry of interior- Riyadh, value of the project is 2 billions SR. * consultant : dar al-handasah.

Job duties : Complete coordination and managing for all trades : structure, precast cladding & curtain wall, electric, mechanical, medical and finishing.

Site manager في .AL-FANAR Co
  • المملكة العربية السعودية - جدة
  • مايو 2004 إلى أكتوبر 2007

Working in AL-FANAR Co. whose main Client is Saudi Electricity Company (SCE CO.)-K.S.A in the following projects as

A project manger civil.

*Jeddah North 380/110kv Substation - Jeddah (SR220millions)

*Alfanar trading warehouse and administration building- Jeddah
*AL-Zahra 110/13.8kv Substation - Makkah
*Dammam Bsp 69/13.8kv Substation - Dammam

* NEW SHARAEH 110/13.8 S/S, extension of Jabal Ennour 110/13.8 & NEW Misfalah-2 S/S - Makkah
* Extention of Shafa S/S- Taif
* Reinforcement of 380kv Jameia S/S-Jeddah
Brief of Job Description:
1- Pre-Check for the design drawings
2- Preparation of Suppliers prequalification and material submittals as per specifications and IFC drawings to get the client approval.
3- Responsible for execution managing of complete Civil works of :
- GIS building, Switchgear& Control rooms.
- Cable basements, tunnels, trenches & duct banks.
- Transformer foundations, fire walls & oil collection tank.
- Equipment & gantry foundations, steel structures, precast concrete & grouting.
- Special finishing work like raised floor, false ceiling, hollow metal doors, epoxy screed, special paints.
- External works.
4- Planning and scheduling of site activities through daily progress report and three weekly look ahead report.
5- Taking place in preparation of: mobilization and demobilization plan, updating the project schedule, material& manpower schedule, site monthly funds, analysis of suppliers& subcontractors quotations.
6- Attending for all meetings (technical, Safety, progress & coordination meetings)
7- Coordination between civil & electromechanical work.
8- Complete managing and supervision of subcontractors work.

(C) Projects execution manager في 1- Four towers in Naser city
  • مصر
  • يناير 2002 إلى يناير 2004

C) Projects execution manager from 2002 up to 2004, the following projects have been performed: 1- Four towers in Naser city - Cairo; complete finishing works.
2- Six residential buildings in Alobour city -Cairo, turn Key.
3- Service buildings in royal hills resort in 6 Oct. city
4- Construction of short span bridge, 7 nos., culvert and protection for Nile
River embankment 5L.KM - the client was Ministry of irrigation and drainage.
5- Several private villas
. 6- Grand mosques (3nos.) - Ministry of Islamic affairs.

# Employed by Ministry of electricity and energy Egypt as a civil site engineer at El-Kureimat 2x650MW thermal power station (project value $900 million) and I was assigned to work for Raytheon Engineers and Constructors, the American consultant and construction manager for the Egyptian Electricity Authority.
My responsibilities included inspection and supervision of -: A- The civil construction activities such as: 1 - Earth works: Excavation, backfilling and grading.
2 - Piles.
3 - Concrete works: Formwork, rebar and concrete pouring.
4 - Pre-cast, steel structure and grouting.
5 - Off-shore works: dewatering, sheet piling, riprap protection etc.
6 - Utilities.
7 - Finishing works.
B- Lab and site tests: 1 - Compaction (sand cone and truxilar test)
2 -Piles tests: Bentonite test, ultrasonic and loading.
3 - Concrete tests: slump, temp, strength and core test.
C- Office works: 1- Review of contractor's invoices and change orders.
2- Preparation of Contract deviations.
The project structures were: Turbine building, boiler, chimney, Control building, intake, discharge, cooling water pipe line, substation, water treatment plant, sewage treatment plant, warehouse, maintenance shop and administration building.

1992 to 1994

(A) SHARM EL SHEIKH Area manager في Holiday Inn crown blaza
  • يوليو 1994 إلى أغسطس 1998

July 1994 to August 1998
# Working in EGYPTION ENGINEERING GROUP COMPANY

A) SHARM EL SHEIKH Area manager in the following sites: Hilton Alshallalat hotel and resort, Holiday Inn crown blaza
Solelete resort, Sheraton and Akapolko resort (apartments, suites, hotel, villas and back of house areas)

Our scope of work was some finishing works: Plaster,
Ceramics and terrazzo - marble - painting - swimming pools and
Hardscape around swimming pools.
B) Project manager for thirteen schools in Giza governorate.

# Site engineer في Nasr city
  • مصر
  • يناير 1991 إلى ديسمبر 1992

1991 to 1992
# Site engineer in EGYPATION ARMED FORCES in a residential buildings project -built up area of the project 300, 000m2 -Nasr city - Cairo.

# * Site eng. in ARAB CONTRACTORS CO. in Cairo stadium main hall (steel and prestressed concrete works)
* Design works (part time) at Engineering group company.


2/2

الخلفية التعليمية

بكالوريوس, الهندسة المدنية
  • في Cairo University
  • نوفمبر 1991

Bachelor of Civil Engineering, Cairo University, 1991

Specialties & Skills

Project Management
AUTO BODY
CERAMICS
CHANGE ORDERS
CONCRETE
ENGINEER
FINISHING
PAINTING
PROJECT MANAGER

اللغات

العربية
اللغة الأم
الانجليزية
متمرّس