construction project manager
ACE Arab Consulting Engineers "Moharram.Bakhoum"
مجموع سنوات الخبرة :22 years, 9 أشهر
مهندس مقيم
مدير مشروع - تجمع قروي ميت العامل
اعمال شبكات انحدار
اعمال خطوط طرد
اعمال المدنيه و الكهروميكانيكية
اعمال محطات الرفع
النزح الجوفي
المتابعه والتنفيذ
المعاملات واعتماد كافه مراحل التنفيذ
PROJECT WITH DUBAI MUNICIPALITY
AL KHAWANEEJ, AL AWIR, MARGHAM, AL BARSHA, AL QUOZ
اعمال انشاءات
اعمال التشطيبات
Landscapes
اداره المشاريع
اداره المشتريات
• Infrastructure in waste water network thrust pouring (AVN method) pipe jacking (Concrete Pipes With hardness (2500 Newton / m 2)) DIA 2000 mm -1800 mm - 1400 mm - 1200 mm .
• PROJECTG PLANS ( SAFETY - Project Management Plan - quality plan - contingency pan )
• Open trench... sanitary pipe line (Fiberglass Pipe GRP - Pipes of Vitrified clay) with Drawing Submittals.
• Concrete Shafts ( D = 7.50 m H = 15 m )
• Safety ( HSE Plan - LIFTING PLAN- TRIFFIC MANGEMENT PLAN- Permits ( PTW ) - Risk assessment - Accidents and Incidents Reports - SOR - NCR )
• QC/QA …. Method of statement - Material approval ( MAT ) - Subcontractor-Manufacturer approval - WIR - QOR - RFI
• Road ( subgrade - subbase - asphalt )
• Payment Certificates - Claims - Variation Orders
• Communications ( Incoming _ Outgoing Correspondence - Project Meetings)
- Sewage BELUGAS DAHLIA
• Infrastructure work (four main lift station with mechanical work )
• Main waste water line ( VC pipe DIA ( 175 mm - 900 mm ) - cast iron pipe DIA 900 mm )
• Water supply network (HDPE ) DIA 600 mm
• Waste water supply network ( GRP ) DIA 300mm & 400 mm & 500 mm
• Pipe jacking under main road DIA 900 mm with three shafts ( one jacking and two receiving )
• Secant and piles DIA 600 mm
• Dewatering by ( well point system - deep well )
• Technical office and price studies.
• Project plan
• slow down chamber
• valve and washout and air chamber
-Sewage AlAGOZIN KAFER ALSHEIKH
Project manager
• TWO MAIN LIFT STATION WITH MECHANICAL WORKS
• Main waste water line ( VC pipe DIA ( 175 mm - 450 mm ) - UPVC ( 200 mm - 315 mm )
• Waste water supply network (H.D.P.E) DIA 250 mm & 400 mm.
• Pipe jacking (HDD) for two main sewer line dia 400 mm & 250 mm.
• Secant and piles dia 500 mm
• Dewatering by ( well point system - deep well - shallow well system )
• Technical office and price studies.
• Project plan
• valve and washout and air chamber
- Al mufti station and water supply network
Project manager
• water network diameters of 1400 mm ( Cast Iron - GRP - CCP - UPVC ) from 1400 mm to 200 mm
• main water station ( construction work )
• Secant and piles dia 500 mm
• Dewatering by ( well point system - deep well - shallow well system )
• Technical office and price studies.
• Project plan
• valve and washout and air chamber
government engineer
PROJECT DESCRIPTION
Project engineering ( 24/03/2002 - 30/06/2004 )
• concrete villa and casino in beach with walker interlock and umbrella station above all main street
• water supply and sewage line to villa on beach
- Company Industrial and Engineering Projects
PROJECT New Damietta ( 3 )
OWNER New Damietta
PROJECT DESCRIPTION
Project engineering
• roads
• irrigation water supply ( upvc 450 mm )
• water supply main line ( 200 - 500 mm )
• sanitary lines ( 200 - 600 mm )
• pump station with all construction and mechanical works
• Dewatering by ( well point system - deep well)
• Technical office and price studies.
• valve and washout and air chamber
Bachelor of Engineering Civil (Alexandria University) May 2001 Eleven year of Faculty of civil engineering Hydraulic Engineer