الاشراف على تنفيذ المشاريع بمدينة اسوان والحدود السودانية المصرية
August 2007 to October 2008: (Riyadh_ Saudi Arabia)
❑ Construction of Saudi National Fiber optic cable Network S.N.F.N (RING 5) 950 KM of main network extended from Riyadh -Hafer Elbatin -Khafgy_Jobil- Dammam) including the metro lines inside the above mentioned cities (25 million S.R) Under the supervision of ThALES & MOBILY CO
❑ Construction of Fiber optic cable Network inside Riyadh
Under the supervision of I T C_ CO (5 million S.R)
❑ Construction of (POTABLE WATER PIPE NETWORK) PHASE 30, 32 Under the supervision of Riyadh potable water &drainage authority (13 million S.R)
❑ Construction of (DRAINAGE WATER PIPES FOR HOUSE CONNECTIONS IN ALKHARG CITY) Under the supervision of Riyadh potable water &drainage authority (4.5 million S.R)
august 2006 to august 2007: (DOHA_ QATQR STATE)
❑ Construction of industrial structures and steel frames of the main storage of heavy machines at QATAR TRACTORS CO (1.5 million Q.R)
❑ Construction of the residential buildings for labors at QATAR TRACTORS CO (1.0 million Q.R)
❑ Construction of ELECTRO-MECHANICAL WORKS (WATER SUPLY- DRAINAGE - HVAC - ELECTRIC- SYSTEM) at EL FARDOUS COMPLEXE which consists of a hotel & 8 buildings (31 million Q.R)
❑ Excavation Works of RASLIFAN PIPE LINE as a subcontractors for CCC international co
April 2004 to January 2006: EGYPT
(as a COSULTANT ENGINEER FOR LEHAA CO)
❑ Construction of infra structure and Land reclamation of garfe-hossine farm which include an area of 2500 feddans (17.00million l.E)
❑ Construction of ( PUMP STATION & CIVEL WRKS) for above mentioned project
❑ Installation of steel frames of the main storage
February 1997 to march 2004
❑ Construction of infra structure and Land reclamation of ELSLAM &COASTAL farms which include an area of 7500 feddans (56+100million l.E)
❑ Construction of Branch 4&4dash South Valley development project in TUSHKA (160 million L.E)
❑ Construction of infrastructure for an area of 600 feddans in the pioneer Farm of Kadco (3 million L.E)
❑ Construction of infrastructure for an are of 1000 feddans in the experimental Farm of Mesreya. Co. (12 million L.E)
❑ Construction of administrative-housing and Laboratory buildings for under ground water investigation center (12 million L.E)
Jan. 1993 to june. 1997:
Senior Engineer in the following (Field of reclamation of Lands in Eslam Farm)
❑ Survying works for deffining and divisien of 2500 fedans.
❑ Construction of Steel Frames workshop for reinforced concrete pipes. Factory of 1500, 1300, 1000, 500, 800, 600 mm Dia.
❑ Setting dawn of reinforced concret pipes having Length of 27 Kms including Civil works issued (control rooms and divisional rooms)
❑ Civil works of Errigation structures (Culverts, Syphones and Pump station)
❑ Office works as (working details-Estimintion of costs & amounts of materials in the several items of works. Value Of works 56000000 L.E.
jan.1991 to dec.1992:
Field of devdlopping of (THE HIGH DAM LAKE) working as a senior Engineer in construction of hurbour of 1.350 KM length extended within the lake, servying, by it, s two sides for: (a) Fishing ships (b) passanger ships
Value Of Works 9000000 L.E.
Sept.1986 to dec.1990.: Behera Co. "in the folliwing (worked as a site Engineer in project of developing of ABOU - SIMBLE TOURISM CITY OF THE FOLLOWING)
❑ Construction of the "PHAROUS VILLAGE"WHICH CONSISTS OF 100 housing units having the nobion style.
❑ Construction of "RAMSIS VILLGE HOTEL" on high Dam Lakes coasts, which consists of the following: 1) 100 Double unetes of two levels.
2) The village center which involved resiption, head office resturant, night club, open coffe shope, billaire theater, swimming pool and shoping district.
3) Asmll port of boats for purpouses of nile criuse.
❑ Construction of the TOURISM SHOPING CENTER of Abou Simble city Centeral Market.
❑ Construction of ABOU SIMBEL CENTERAL-MARKET Value of workes 7500000 L.E
Aug.1984 to Aug.1986.:
THE HIGH DAM AUTHORITY " as a supervision Engineer at the following
❑ Construction of "Earthquakes investigation center".
❑ Construction of the administration building of Aswan Dam".
❑ Construction of "civil works of imergency mechanism Center of High Dam" Value of works 3000000 L.E.