site engineer
Alatia holding
مجموع سنوات الخبرة :5 years, 9 أشهر
Mobilization
* Submit progress reports to the Project Manager and Consultant.
* Check bill for sub-contractor, and preparing project invoices.
Page 5
* Concrete building (32 j 3500m3, 50 k 3200m3) from foundation( raft)
* Insulation: cooled apply, membrane and cartonel
* Backfilling
* Reflected celling
* Stones
* Ceramic
* Duct banks (L.v and fiber optics)
* Valve chambers (chilled water, air, declaration)
* Inspection chambers
* Pump room for lake
* Excavation and earth work
Civil work traditional concrete building from foundation (isolated footings) from excavation
* Check bill for sub-contractor, and preparing project invoices.
* Backfilling
* Gantry ramp, stair ramp and tenant pads (roof team)
* Block work (roof team)
* Plaster and painting (roof team)
* Repair for block work and screed (roof team)
* Insulation (combo system) (roof team)
* Columns cladding (pilaster) (portal A, B)
* Reflected celling (portal A, B)
* Stones
* Keystone
* Metal doors
* Employer: alshafar contracting
* Project name: cairo festival city
* Consultant: Alamar
* Owner represented: Hosny pacer
* General Contractor: alshafar
* Owner: elfuttem
Traditional concrete building 12 villas
* Water tank
* fence
* Pilaster
* Painting
* Blockwork
* Wooden doors
* Infrastructure
* Employer: OrascomBesix
* Project name: Mall of Egypt
* Consultant: Medhatabouzad
* Owner represented: David Langton
* General Contractor: orascom besix
January 2012The faculty of engineering Cairo university