Expériences professionnelles

Total des années d'expérience :27 years, 0 Mois

Resident Engineer à ECG
  • Egypte - Le Caire
  • Je travaille ici depuis janvier 2013

Works, as applicable, with the Technical Review Committee of the project in reviewing the design, construction tender documents.
Sets forth ECG responsibilities for site operations in accordance with the project contract and ECG Manuals.
Directs/supervises all construction activities and acts as the construction representative of ECG and in charge of all site work.
Holds weekly staff meetings to review detailed field schedules.
Prepares necessary daily, weekly and monthly progress reports for the CSD mobilization.
Reviews the Progress and Completion Reports prepared by Contractor.
Studies and approves the Contractors Claims.
Reviews the Contractors Valuations (Payments).
Prepare close out report often handing over the projectProject Name : PORTO October (Jan. 2014 Present)

Project overall Value : around 6 Billion Egyption Pounds ( 750 Million $ )
Project Period : 60 Month
Project maneger : DAR EL-Handasah
Consultant : ECG Engineering Consultants Group.
Client : AMER Group.
Contractor : Several Contractors.

Project Scope of Work : Construction Supervision Services for ( Porto October ) as highly Egyptian project including :
( Ordinary buildings and Villas with Constant style Commertial Zones with defferant shapes Mosques with different designs Schools with defferant style Lake with a huge area and all Infrastructure works).

Project Name : Cairo International Airport New Hotel (Le Meridian) (Jan. 2013 Jan. 2014)

Project overall Value : around 670 Million Egyption Pounds ( 85 Million $ )
Project Period : 50 Month
Project maneger : ECG Engineering Consultants Group
Consultant : ECG Engineering Consultants Group
Client : AIROTEL Company for Hotels, Touristic, Entertainment and Medication Services.
Contractor : Binladin Group / Al-Marasem International for Development JV, Egypt.

Project Scope of Work : Construction Supervision Services for ( Le Meridian ) Hotel inside Cairo international airport zone

Project Name :Landscape Development For Area Surrounding Airotel Hotel Cairo International Airport (Feb. 2012 Sep. 2012)

Project overall Value : around 6.5 Million Egyption Pounds ( 0.8 Million $ )
Project Period : 6 Month
Project maneger : ECG
Consultant : ECG
Client : AIROTEL Company for Hotels, Touristic, Entertainment and Medication Services.
Contractor : ELFATH FOR CONST. & BUILDING.

Project Scope of Work : Construction Supervision Services for Landscape Development at area Surrounding ( Le Meridian ) Hotel inside Cairo international airport zone including : Infrastructure work Civil work Key stone and earthwork Electromechanical Coordination and all archtectrual finishing softscape and hard scape

QA/QC Manager à ECG Engineering Consultants Group S.A., Cairo, Egypt
  • Egypte - Le Caire
  • septembre 2009 à janvier 2013

Duties:
Managing and performing the daily QA/QC responsibilities of projects to ensure the project is constructed in accordance with the established required standards.
Directing oversight and reviewing of the entiredocumentation and physical inspection phase of the work flow process and coordinating with in-hous / external personal to produce and document a quality product.
Directs/supervises all construction activities and acts as the construction representative of ECG and in charge of all site work.
Holds weekly staff meetings to review detailed field schedules.
Reviewing daily QC reports that reinorce activities that are being constructed inconformance with each specific project's established standard and constructively confronts non-conformances to produce the desired outcome in a timel manner.
Preparing and controlling of project quality system management documentation starting from project commencement as well as creating, updating and maintaining the project submittal log and all other project specific quality control reports which will lead to handing over the project easily.
Reviewing procurement documents to ensure that quality requirement have been correctly translated into purchase requisitions and design documents.
Reviews the Contractors Valuations (Payments).
Verifying and documenting that all materials received for the project are in conformance with the approved submittal, are handled and stored appropriately and are acceptable for use in the project.


Key projects to credit :

Project Name : Cairo International Airport New Hotel (Le Meridian) (Jan. 2010 Jan. 2013)

Project overall Value : around 670 Million Egyption Pounds ( 85 Million $ )
Project Period : 50 Month
Project maneger : ECG Engineering Consultants Group
Consultant : ECG Engineering Consultants Group
Client : AIROTEL Company for Hotels, Touristic, Entertainment and Medication Services.
Contractor : Binladin Group / Al-Marasem International for Development JV, Egypt.

Project Scope of Work : Construction Supervision Services for ( Le Meridian ) Hotel inside Cairo international airport zone

Project Name : Domiatec Agricultural Packing Plant (Sep. 2009 Jan. 2010)

Project overall Value : around 180 Million Egyption Pounds ( 23 Million $ )
Project Period : 12 Month
Project maneger : ECG Engineering Consultants Group
Consultant : ECG Engineering Consultants Group
Client : AIROTEL Company for Hotels, Touristic, Entertainment and Medication Services.
Contractor : Binladin Group / Al-Marasem International for Development JV, Egypt.

Project Scope of Work : Construction Supervision Services for Agricultural Packing Plant Including The Civel & Architectural and Electromechanical Works for The adminstration building and Steel strusture planet building and all infrastructure work

Construction Supervision Manager à M.H.Z CONSULTANT ENGINEERING
  • Egypte - Le Caire
  • mars 2005 à septembre 2009

Duties:
Leading a group of site engineers .
Follow-up Main contractor .
Reviewing of Surveying works
Reviewing of all civil works
Reviewing of construction works
Reviewing of Shop drawing details through Autocad R2006 .
Control of Documentation in quality control department.
Follow-up and update of work activities
Reviewing of Surveying works As Built through Autocad R2006 and Microsoft Excel.
Handing over the project with clinte.

Key projects to credit :

Project Name : ALEXANDRIA CITY CENTER EXTENSION (May. 2008 Sep. 2009)

Project overall Value : around 278 Million Egyption Pounds ( 35 Million $ )
Project Period : 18 Month
Project maneger : HILL international
Consultant : M.H.Z CONSULTANT ENGINEERING
Client : MAF - Misr For Commercial & Real Estate Investments S.A.E.
Contractor : SIAC.

Project Scope of Work : Construction Supervision Services for ALEXANDRIA CITY CENTER EXTENSION at the entrance of Alexandria city As a mega mall including all the parking area arround it

Project Name : Judgment educational academy (Jul. 2007 May. 2008)

Project overall Value : around 2 Billion Egyption Pounds ( 250 Million $ )
Project Period : 50 Month
Project maneger : M.H.Z CONSULTANT ENGINEERING
Consultant : M.H.Z CONSULTANT ENGINEERING
Client : Ministery of judje
Contractor : Arab Contractors.

Project Scope of Work : Construction Supervision Services for Judgment educational academy at the 6th of October city as highly Egyptian project including :
( Educational huge buildings - Villas with Constant style Commertial mall Mosque and all Infrastructure works).

Project Name : MAADI CITY CENTER EXTENSION (Mar. 2006 Jul. 2007)

Project overall Value : around 89 Million Egyption Pounds ( 12 Million $ )
Project Period : 14 Month
Project maneger : M.H.Z CONSULTANT ENGINEERING
Consultant : M.H.Z CONSULTANT ENGINEERING
Client : MAF - Misr For Commercial & Real Estate Investments S.A.E.
Contractor : ORASCOM

Project Scope of Work : Construction Supervision Services for MAADI CITY CENTER EXTENSION at the ring road in cairo, As a mega mall including all the parking area arround it
Project Name : Dandy Mega Mall-Hyper Market Fit Out Carrefour Mega-Market At Alex-Cairo Desert Rod, Cairo, Egypt (Mar. 2005 Jan. 2006)
Project overall Value : around 56 Million Egyption Pounds ( 8 Million $ )
Project Period : 12 Month
Project maneger : M.H.Z CONSULTANT ENGINEERING
Consultant : M.H.Z CONSULTANT ENGINEERING
Client : MAF - EGYPT For installation & Management Of hypermarkets.
Contractor : SIAC - Siemens consortium

Project Scope of Work : Construction Supervision Services for Fit Out Carrefour Mega-Market At Alex-Cairo Desert Rod, Cairo, Egypt, including all Civil Architectural and Electromichanical woks

CIVIL Senior Site Engineer à M.H.Z CONSULTANT ENGINEERING
  • Egypte - Le Caire
  • mars 2005 à août 2009

Responsible for maintains daily diaries of events associated with the work on site; supervises his subordinate staff members in the execution of their responsibilities; monitors, reviews, comments and reports on progress payments, quality control and safety; logs and monitors all Contractors submittals (correspondence and shop drawings) to assure timely response, and process change and field orders for review by Construction Manager; prepares necessary draft correspondence for final approval by the Construction Manager; assists as applicable, with pre-tender and pre-construction activities for contracts relative to his site and provides input for all change orders and claims analysis; holds daily meeting with the contractor’s representative; assists the Construction Manager in preparing the Monthly Progress Reports; reviews and approves the As Built Drawings for final approval by Construction Manager; assists in preparing the Final Acceptance and Completion Report; reviews and presents the Contractors Valuations Payments for final approval by Construction Manager; witnesses and supervises commissioning and start-up activities; studies and gives comments on the Contractors Claims; handing over the project with client for the following projects:
 MAY. 2008- SEP. 2009 -ALEXANDRIA CITY CENTER - EXTENSION
 MAR. 2006- MAY. 2008 -MAADI CITY CENTER - EXTENSION,
 MAR. 2005- DEC. 2005 -Fit Out Carrefour Mega-Market At Alex-Cairo Desert Rod, Cairo, Egypt

Technical Office Engineer & Site Engineer à ALEX. CO. FOR CONSTRUCTIONS "TALAAT MOSTAFA GROUP";
  • Egypte - Le Caire
  • décembre 1998 à mars 2005

Technical Office Engineer. Responsible for prepare shop drawing details through; Surveying works “As - Built”; Quantity And Procure equipments, resources, materials and subcontractors; Control of Documentation between construction departments; assist in the preparation of coordination drawings .
- Site Engineer. Responsible for prepare Monthly & daily Reports of Manpower and Equipment; Follow up all construction activities (civil & finish works & plumping & Electromechanical) and its subcontractors; Follow-up and update of work activities.
In Project (EL-REHAB CITY)
Construction of highly Egyptian project "EL-REHAB CITY" including:
( ordinary buildings and villas with many styles - 2 commercial centers with different shapes - 4 mosques with different designs - 4 schools with different designs - and all electromechanically works - and all roads in and out of city )

Site Engineer à ALEX. CO. FOR CONSTRUCTIONS "TALAAT MOSTAFA GROUP"
  • Egypte - Le Caire
  • mai 1997 à décembre 1998

Project Name : Dar EL-Ahly Bank ( ALEX.), Egypt (May. 1998 Dec. 1998)

Project Scope of Work : Construction of highly Social club including :
( Admenistry building Bank branch with high line finishes A hotel with 120 Guest rooms and 2 resturants with all facilities Some internal roods ).
Position held : * Site Manager.
MAY. 1998 DEC. 1998
Duties:
Lead a group consistes of 3 engineers and 4 supervisores to construct a required buildings .
Monthly & daily Reports of Manpower and Equipment.
Follow up all construction activities ( civil & finish works & plumping & electromichanical) and its subcontractors .
Shop drawing details through Autocad R2000 .
Technical office, Quantity And Procure equipments, resources, materials and subcontractors .
Follow-up and update of work activities

Project Name : Main Stores of EL-Ahly Bank ( 6th of October.) (May. 1997 May. 1998)

Project Scope of Work : Construction of Stores including :
( Admenistry building Bank branch with high line finishes 3 Multifloor Stoors with all facilities Some internal roods ).
Position held : * Site Engineer.
MAY. 1997 MAY. 1998
Duties:
Monthly & daily Reports of Manpower and Equipment.
Follow up all construction activities ( civil & finish works & plumping & electromichanical) and its Coordinations .
Shop drawing details through Autocad R2000 .
Technical office, Quantity And Procure equipments, resources, materials and subcontractors .
Follow-up and update of work activities

Éducation

Baccalauréat, civil engineering
  • à B.H.I.T
  • janvier 1998

Genral Grade : GOOD Project : “ Steel construction “ Project Grade : Very Good

Specialties & Skills

Quality Systems
Technical Documentation
Civil Works
Technical Reports
Technical Coordination
computer

Langues

Anglais
Moyen

Adhésions

Society Of Engineers
  • Member
  • January 1998

Formation et Diplômes

ISO 9001 Lead-Auditor course (Certificat)
Date de la formation:
May 2014
Valide jusqu'à:
January 9999
OSHA-Occupational Safety and Health Administration (Certificat)
Date de la formation:
May 2011
Valide jusqu'à:
January 9999

Loisirs

  • Music, Reading, Football