Senior Planning Engineer
SENDAN International Company Limited
Total years of experience :5 years, 0 Months
• Preparing project activity schedule.
• Preparing monthly cost reports.
• Material planning and control with coordination with SENDAN CWH and Procurement departments.
FIRE PROTECTION SYSTEM UPGRADE Project, Saudi Aramco, Abqaiq
• Preparing daily and weekly progress reports.
• Revising, monitoring and controlling project budget.
• Monitoring the resource utilization.
• Raising purchase requests for materials and services.
• Monitoring manpower plan and raising staff requisitions.
• Project Team’s Planning and scheduling activities.
• Preparing, monitor and control project budget.
• Monitoring the resource utilization.
• Preparation of invoices and following with clients for acceptance and payment.
• Responsible for material receiving Inspection and other inspections for site activities.
• Inspecting subcontractor activities and following for closing Punch List.
• Supervising 15 employees in substation 03.
• Coordinating with supervisors for installed and balanced lights, receptacles, panels, JBs and cable trays.
Coop Training in Qurayyah Power Plant
• Overview of electrical system in steam power plant.
• Participated in some periodic preventive maintenance for DC batteries, air circuit breakers, cathodic protection, and transformers.
• Overview of GE mark VI control system.