• Develops project objectives by reviewing project proposals and plans; conferring with management.
• Determines project responsibilities by identifying project phases and elements; assigning personnel to phases and elements; reviewing bids from contractors.
• Determines project specifications by studying product design, customer requirements, and performance standards; completing technical studies; preparing cost estimates.
• Determines project schedule by studying project plan and specifications; calculating time requirements; sequencing project elements.
• Maintains project schedule by monitoring project progress; coordinating activities; resolving problems.
• Controls project plan by reviewing design, specifications, and plan and schedule changes; recommending actions.
• Controls project costs by approving expenditures; administering contractor contracts.
• Prepares project status reports by collecting, analyzing, and summarizing information and trends; recommending actions.
• Maintains safe and clean working environment by enforcing procedures, rules, and regulations.
• Maintains project database by writing computer programs; entering and backing up data.
• Maintains product and company reputation by complying with RoK normative and regulations.
• Contributes to team effort by accomplishing related results as needed.
• Coordinating, organizing and checking contractor’s works meet to designing system configuration, directing system installation, documenting, and enforcing system standard.
• Ensure accomplishing each construction stage (C0, C1, and C2) on time.
• Reporting to Piping and Mechanical Superintendent and providing a feedback to other discipline supervisors, Site Manager, QA/QC for any matters affecting quality and performance.
• Ensure contractor’s works within the safety requirements.
• Answering on customers inquiries (RFI, FCR, and MAR) and initiating NCRs.
• Support the evaluation of the impacts, in terms of costs and schedule, of any changes or deviations from approved design from an installation/erection viewpoint.
• Reviewing and commenting LME, VDDR and piping and mechanical design package.
• Designed the piping and mechanical drawings for modification of the refinery units.
• Provided construction support in engineering discipline (site survey, as build procedure)
• Participated in HAZID, HAZOP during the consideration design philosophy.
• Developed detailed projects documentation, direction of project execution for contractors.
• Coordinated the process of material and equipment requisitions development.
• Analyzed, reviewed & commented complete detail engineering package.
• Prepared of job pack for construction.
• Coordinated of construction & any changes agrees with design contractor by as-build procedure.
• Designed process piping and mechanical systems for oil-gas field and refining plant by ANSI and ASME (P&ID, plot plans, vessel connection scheme, piping GA, ISO, MTO, JOB PACK, MR).
• Prepared and issued mechanical data sheets, mechanical equipment list and plate work drawings.
• Participated in design works by piping and mechanical discipline.