Ambrish Singh, Sr. Construction Manager

Ambrish Singh

Sr. Construction Manager

Larsen & Toubro Ltd

Location
Saudi Arabia - Riyadh
Education
Bachelor's degree, Civil
Experience
23 years, 7 Months

Share My Profile

Block User


Work Experience

Total years of experience :23 years, 7 Months

Sr. Construction Manager at Larsen & Toubro Ltd
  • Saudi Arabia - Riyadh
  • My current job since August 2014

In- Charge for the execution of Under Ground Metro Station with all Structural, MEP till handover to Client and TBM Lining for 980 RM on either side of Metro Station.

Sr. Construction Manager at Larsen & Toubro Ltd
  • United Arab Emirates
  • April 2012 to August 2014

to L&T SUCG JV (MTD)

Sr. Tunnel Expert at Larsen & Toubro Ltd
  • India
  • June 2008 to April 2012

for Independent Engineer services for Rehabilitation, Strengthening and 4- laning ofJammu - Udhampur section of NH-1A, from km 15.00 (on Jammu Bypass) to 67.00 on BOT(Annuity) basis in the State of Jammu & Kashmir.
The job involved construction supervision and design of 102.00Sqm cross section and 2.80KM length 4 no. twin bored tunnels using NATM for four lanes road project 65.00KM for Jammu to Udhampur section. The job responsibilities are review of tunnel designs, design development, Geotechnical investigation, preparation of monthly progress report of Tunnels, monthly progress review meeting, review of Feasibility Study report, review of method statements of shotcreting, Rock-bolting and tunnel excavation and regular co-ordination with NHAI and Concessionaire

Sr. Engineer at Larsen & Toubro Ltd
  • India
  • March 2006 to June 2008

TBM (EPB) for Delhi Metro Rail Project. The job involved construction supervision of 6.52 m diameter and 2.10Km underground bored tunnel using EPB shield TBM (Robbins) from Jorbagh station to Udyog Bhavan under consultancy of (PCI-PBI-JARTS-TONICHI-RITES). The job responsibilities of construction supervision of underground bored Tunnels and underground launching and receiving shafts. Liaise with site personnel to monitoring of tunnel activities and assist the technical queries related of TBM, and supports to provide spare parts from time to time as required. Liaise with site account, purchasing and document control departments for submission and receiving of Invoices, PO and Quotations and carryout monthly inventory check. Daily updating of all reports to Robbins Asia Pacific office, Hong Kong

at Scott Wilson Kirkpatrick India Pvt. Limited
  • India
  • February 2000 to November 2002

Tunnel expert for construction of underground station and bored tunnels and Diaphragm wall for station shaft for Underground Delhi Metro Rail Corporation. The Contractors are JT METRO JV (Mitsubishi, Obyashi Corporation, Kazima Corporation & Yepi Markezi) and Soletanche Bachy. The job involved construction supervision of Underground double track railway bored tunnels 9.56m diameter and 3.50 Km length using Mitsubishi shield TBM in EPB system from Kashmere Gate to Rajiv Chowk Station and Underground station shaft of Rajiv Chowk station The job responsibilities involved design development, design review, quality inspection of station activities, review of Diaphragm wall design, method statements of Diaphragm wall and station excavation, bored tunnels including construction supervision of Diaphragm wall, underground station shaft and underground bored tunnels. Preparation of monthly progress report

ASSISTANT ENGINEER at K.N.INTERNATIONAL Ltd
  • August 1997 to February 2000

CIVIL
The Job responsibilities include the Layout, Supervision, Costing and Construction of Heterogeneous Rock Fill Dam in the Rihand Reserviour at Anpara Dist. Sonebhadra (U.P) for their Anpara Thermal Power Project. The job contains construction of Rock fill dam of 1.6 K.M. Long with approved design with their Decantation Well, Spillway, Piling, Grouting and 7 km long 6.30 mtr. Dia. Water carrying tunnel with it’s CIFA gantry lining.

Project Engineer at Airport Metro Express Line, Delhi Metro Rail Corporation
  • India
  • October 2000 to

NATM with Alpine HCC JV for Airport Metro Express Line- C6 project cost INR3000 million for Delhi Metro Rail Project Corporation under consultancy of (PCI-PBI-JARTS-TONICHI-RITES) and Tunnel

Consultant at Riyadh Public Transpor
  • to
Design consultant at IDOM
  • Spain
  • to
Technical Manager In-charge
  • to

for the Underground station 3F1

Tunnel Expert
  • India
  • to

for underground bored tunnels for line 6 &7 for Delhi Metro Rail Corporation from Mandi House to Jama Masjid corridor including TBM launching shafts. The job responsibilities are review of construction drawings, review of method statements of TBM and review of progress reports. Regular site inspections related progress, quality and safety. Weekly site inspection at Casting yards, Mundka related quality of segments and safety. Regular coordination with Team Leader related quality and safety issues. Attending progress review meetings with DMRC and contractors

Education

Bachelor's degree, Civil
  • at Kharkov State of Automobile and Highway University
  • July 1996

Specialties & Skills

Tunnelling
Set Construction
Construction Methods
ENGINEERING
INVENTORY MANAGEMENT
LAYOUT DESIGN
MICROSOFT OFFICE
PERSONNEL
PROGRESS
PURCHASING
QUALITY
SUPERVISORY SKILLS