Technical & Design Manager
Al Jaber Group
Total years of experience :20 years, 3 Months
Technical & Design Department Manager.
Major or Responsibilities & Accountabilities:
- Design-build project follows up the design with the consultant till the issue of IFC drawings and obtain the client approval. Prepare Shop Drawings, Architecture, Structure, Mechanical and Electrical.
- Organizes and presides over execution coordination meetings with all trades/sub-contractors and project's staff.
- Technical follow up and coordination after sub-contract's signatures.
- coordination and the preparation of technical submittals.
Work on Mega projects, Infrastructure, roads and housing.
- Abha Airport, Value, SR. 1.800.000.000. 1.8 Billion.
Main Terminal Building, Airside, Landside Infrastructure & Utilities.
- Ehssa Housing Project (Infrastructure) Value, SR. 3150.000.000.
- Half moon Road Value, SR. 96.000.000.
Private Residence - Riyadh, Saudi Arabia.
Value: SR. 38.000.000. Project Coordinator.
Site mobilization,
Prepare shop drawings for approval.
Study cost & Time - Time Schedule.
Tracking activities against the detailed project plans.
Updating project plans to include agreed changes.
General Projects Construction Division
Prince Meteeb Ben Abdullah Residence - Riyadh,
Value: SR. 78.000.000. Consists of 13 villas-5 VIP Villa & 8 Staff Villa.
- Major Responsibilities & Accountabilities:
Architect & Design (value engineering) which need modifications, re-design.
Shop Drawings some additional buildings & External work.
Responsible for costing, estimating and planning projects.
Preparing Project Initiation documentation.
Responsible for ensuring best value is obtained for the project including supplier base,
use of internal and external resources.
Maintaining and completing Project Key Performance Indicators.
Writing detailed and summarized project progress reports.
Identifying, costing and processing any contract variations.
Tracking activities against the detailed project plans.
Updating project plans to include agreed changes.
Producing accurate financial reports.
Monitoring actual expenditure figures against project budgets.
Organising and facilitating Project Steering / Operating Committees meetings.
King Abdullah City for Atomic & Renewable Energy - President’s Office - Phase I, Value: SR. 25.000.000.
Major Responsibilities & Accountabilities:
Supervision over a full project.
Participation in Kick off Meetings.
Participation in Commissioning Stage.
Suggest Solutions, if needed.
Carry Higher Management Giddiness.
Approve/Disapprove Work change orders
King Abdullah City for Atomic & Renewable Energy - Exhibition Hall.
Value: SR. 65.000.000. Project Coordinator,
Work with Sub-Contractors and Design:
- Bruce mau design. - Obscura Digital. - Oasis Enterprises. - POWERleap Inc.
Major Responsibilities & Accountabilities:
Managed a team of 80 labars & sub-contractors.
• Supervision over a full project.
• Participation in Kick off Meetings.
• Participation in the Execution Stage.
Estimating Department
Architect & Design (value engineering) projects which need modifications, re-design, List of projects:
King Abdullah Financial District, Monorail System - EPCO Tender.
King Abdullah Financial District, Chilled Water Cooling OBO.
Information Technology and Communication Complex, Chilled Water Plant Design Build - Operation.
Major Responsibilities & Accountabilities:
Prepare presentable posters & all graphics of bidding documents.
Prepare technical proposal.
Pricing architectural and finishes items, List of Projects:
Name: 150 Health Clinics Kingdom Wide, Client: (MOH), Value: SR. 504.000.000.
Major Responsibilities & Accountabilities
• Preparation of Shop drawing,
• Participation in Kick off Meetings
• Participation in the Execution Stage.
• Supervision over a full project. (Al-Ghadeer Clinic- Area 1140 m² @ Value : SR. 3.3 M)
• Participation in Commissioning Stage.
• Site Surveys to make sure:
Execution is going according to Engineering Plan & Specs.
Execution is going according to time frame schedule.
Report Committed Violations, if any.
Suggest Solutions, if needed.
Carry Higher Management Giddiness.
Engagement of Project Management over project management Primavera technology.
• Negotiate technical Makeovers with subcontractors and/or execution teams.
• Approve/Disapprove Work change orders.
• Establish payment linkage between subcontractors & firm.
• Establish Work Flow linkage according to plan.
• Participation in Back to Client stage.
Architect & Design Residential Complexes, Apt. Complexes and Business Unit Towers.
Identify client’s needs.
Translate Technical Terms to Common language aspects for clients.
Assemble Common language aspects in to Technical Plan.
Utilize presentations for clients.
Edit, Alter & Insert Client’s needs into prospective plan.
Explain work change orders feasibilities.
Setup master work scope plan & alternative plan.
Prepare presentable Basic Sketches.
Incorporate the use of available office automations & technology to produce:
Final Presentation.
Final Blue Print.
Final Work Scope.
Final Quantity Tables.
Adhesive Consultancies.
All Designs & Architect rituals in 3D & Colored.
• Survey Sites to determine; Case study, accurate measurements & Interior Architect.
• Shoulder the full obligation according to commitment with clients.
• Entertain clients into company designing word drop.
• Share Case studies with foreign business affiliates.
• Conclude all business aspects according to company policies.
• Constitute & govern relations with clients for future comebacks.
List of Popular Clients; includes but not limited to:
• HE. Sheik Hamad Al-Obaidulla.
• Sheik Nasser Al-Mutawa.
• Sheik Mohammed Al-Omran.
• Rajhi Bank Tower.
• Al-Billad Bank, Associated branches.
Survey Sites to determine; Case study, accurate measurements & Interior Architect.
Share Case studies with foreign business affiliates
Survey Sites to determine; Case study, accurate measurements & Interior Architect.
Share Case studies with foreign business affiliates