Modification of Al Shaheen oil & gas fixed production platforms situated at North-East coast of offshore Qatar managed by North Oil Company - Qatar Petroleum & Total JV.
• Executed the assigned work in accordance with applicable standards and procedures, and within the man-hour budgets / scheduled targets.
• Identified deviations in scope of work from Tender documents, estimated changes, prepared additional input requirements, raised Technical Queries, and recommended solutions for improvement.
• Planned, scheduled, and controlled engineering activities of the team in co-ordination with Lead Engineer.
• Client and interdisciplinary co-ordination, led internal & client 3D model reviews, attended Engineering progress reviews. Participation in 3rd party studies, like HAZID, HAZOP workshops.
• Troubleshoot offshore site queries & recommended solutions.
• Reviewed 3D model based on Design Codes & company standards, P&ID, Safety & integrity, operation & maintenance, constructability, good engineering practices and client comments / requirements.
• Guided designers for space management and develop a better clash-free 3D Model.
• Checked and corrected piping engineering deliverables from technical and quality point of view.
• Experienced in developing & reviewing engineering design data (Plot Plan, Equipment Layout, Piping Layout, Isometrics, Valve datasheets & MTO) prior to Fabrication releases.
• Provided input to Weight Control Report (WCR) & final Weight Estimates for Piping & Manual Valves.
• Prepared the demolition / construction and execution scope for Brownfield modification jobs.
• Performed stress analysis for production & test flowlines, gas lift & water injection lines considering wellhead displacements, slug, PSV reaction forces. Calculated & checked fatigue, flow & acoustic induced vibration, trunnion calculation.
•
Projects - Upstream Fixed Offshore Oil & Gas Production Platforms - Al Shaheen Field
• Flowline Projects for Platforms at Locations A, B, C, D, E & H
• Performed & reviewed flowline layout study and well-bay planning as per drilling sequence for Oil Producer, Gas Injection and Water Injection wells.
• Performed X-Mas tree installation study and drilling envelope study.
• Checked and issued piping engineering deliverables within scheduled targets. Interdisciplinary checks.
• Client and inter-disciplinary co-ordination. Led internal and client model reviews for multiple wells.
• De-bottlenecking Pipeline Project for Platforms at Locations A & F
• Performed riser / flowline detailed design under topside scope for pig launcher / receiver for 14” wet Oil and 20” Sea water Injection.
• Performed design check for all piping engineering deliverables from technical and quality point of view.
• Performed pipe routing studies, material handling studies following best engineering practices and optimization in term of cost, construction simplicity, operability and maintainability, HSSE.
• Conducted Material Handling studies to assist Lead Engineer to finalize Material Handling Procedures and Report.
• Client and inter-disciplinary co-ordination. Attended 30%, 60% & 90% model review and close-out.
• Prepared the demolition / construction and execution scope as per project scope.
• Water Disposal Wells on B Location Concept Study
• Performed & optimized piping routing study of 24” water disposal line from BD platform to wells at BA platform via BA-BD bridge following best engineering practices, construction simplicity, HSSE.