Total des années d'expérience: 23 Années, 0 Mois
octobre 2017
A mars 2023
project quantity surveyor
à Renardet S.A.
Lieu :
Oman - Sour
• Certify Contractors’ monthly progress Payments,
• Finalising partially completed project account,
• Managing the change management process; consult with other stakeholders to assess changes and risks to the overall project outturn,
• Finalisation of Variation Orders,
• Preparation of correspondence and maintenance of records necessary to ensure the effective administration of all contractual matters,
• Reviewing claims and identifying any potential claim by the contractor and its mitigating measure,
• Preparing tender documentation,
• Producing Consultant’s Monthly Progress Report,
• Representation of the project to the client (Ministry / funding Bank) on various Commercial / Contractual issues,
• Keeping tracks on Drawings, Insurances, Bank Guaranties etc.,
• Conducting regular site visits to check and record materials delivered to site, works progress achieved, change orders executed etc.,
• Providing support to the Senior Management on any Commercial and Contractual issues,
• Guiding site execution team on any issues.
• Finalising partially completed project account,
• Managing the change management process; consult with other stakeholders to assess changes and risks to the overall project outturn,
• Finalisation of Variation Orders,
• Preparation of correspondence and maintenance of records necessary to ensure the effective administration of all contractual matters,
• Reviewing claims and identifying any potential claim by the contractor and its mitigating measure,
• Preparing tender documentation,
• Producing Consultant’s Monthly Progress Report,
• Representation of the project to the client (Ministry / funding Bank) on various Commercial / Contractual issues,
• Keeping tracks on Drawings, Insurances, Bank Guaranties etc.,
• Conducting regular site visits to check and record materials delivered to site, works progress achieved, change orders executed etc.,
• Providing support to the Senior Management on any Commercial and Contractual issues,
• Guiding site execution team on any issues.
septembre 2015
A octobre 2016
Project Quantity Surveyor
à AAW Consulting Engineers
Lieu :
Oman - Sohar
• Contract Administration
• Certify Contractors’ Interim Payment
• Finalise Variation Order
• Control on Drawings, Insurances, Bank Guaranties, Contractors’ any claim, Works as per Specifications
• Quantity take off from drawings and Bar Bending Schedules
• Support Senior Management on any Commercial and Contractual issues
• Guide site execution team on contractual issues
• Certify Contractors’ Interim Payment
• Finalise Variation Order
• Control on Drawings, Insurances, Bank Guaranties, Contractors’ any claim, Works as per Specifications
• Quantity take off from drawings and Bar Bending Schedules
• Support Senior Management on any Commercial and Contractual issues
• Guide site execution team on contractual issues
décembre 2013
A juillet 2015
Senior Manager QS
à Parsons Brinckerhoff India Pvt. Ltd
Lieu :
Inde - Gurgaon
From December 2013 to till date
A. Residential Development - The Regal Gardens & The Primus at Sector 90 & Sector 82A Gurgaon
PMC: Parsons Brinckerhoff India Pvt. Ltd.
Value: USD 108 Million (Appx)
➢ Checking and certify Contractor's Monthly Progress Payment Application
➢ Activities related to selection of Nominated Sub contractors. Analysis Subcontractor terms and conditions for various risks such as ambiguities, conflicts or deviations from the scope of work, ensure Contract Conditions as per the Clients Standard Conditions
A. Residential Development - The Regal Gardens & The Primus at Sector 90 & Sector 82A Gurgaon
PMC: Parsons Brinckerhoff India Pvt. Ltd.
Value: USD 108 Million (Appx)
➢ Checking and certify Contractor's Monthly Progress Payment Application
➢ Activities related to selection of Nominated Sub contractors. Analysis Subcontractor terms and conditions for various risks such as ambiguities, conflicts or deviations from the scope of work, ensure Contract Conditions as per the Clients Standard Conditions
janvier 2011
A novembre 2013
Senior Manager Quantity Survey
à Parsons Brinckerhoff India Pvt. Ltd
Lieu :
Inde - Kolkata
Construction of Integrated Passenger Terminal Building at NSCBI Airport, Kolkata
Client: Airport Authority of India
CSC (Construction Supervision Consultant): Parsons Brinckerhoff International Inc and Parsons Brinckerhoff India Pvt. Ltd. - Consortium.
Value: USD 348 Million (Appx)
Checking and certify Contractor’s Monthly Progress Payment Application, Variation Claim
Quantity take off from As Built Drawing for reconciliation of measurements
Finalise rates for Extra Items after Rate Analysis
Interpretation and implementation of Condition of Contract in addressing and resolving various contractual issues during the Project
Assessment of EOT (Extension of Time) claim by the Contractor
Client: Airport Authority of India
CSC (Construction Supervision Consultant): Parsons Brinckerhoff International Inc and Parsons Brinckerhoff India Pvt. Ltd. - Consortium.
Value: USD 348 Million (Appx)
Checking and certify Contractor’s Monthly Progress Payment Application, Variation Claim
Quantity take off from As Built Drawing for reconciliation of measurements
Finalise rates for Extra Items after Rate Analysis
Interpretation and implementation of Condition of Contract in addressing and resolving various contractual issues during the Project
Assessment of EOT (Extension of Time) claim by the Contractor
septembre 2009
A décembre 2010
à Mumbai Metro One Pvt. Ltd
Lieu :
Inde
From September 2009 to December 2010
C. Construction of VAG Corridor of elevated MRTS (Mass Rapid Transit System) (Metro Rail) in Mumbai
Client: Mumbai Metro One Pvt. Ltd.
EPMC: Parsons Brinckerhoff -Systra JV
Value: USD 304 Million (Appx)
➢ Checking and certify Contractor's Monthly Progress Payment Application, Variation Claim
➢ Sourcing of quotations and evaluation of vendors pricing in Establishing Extra Items
➢ Monthly Cost Report of the project.
➢ Interpretation and implementation of Condition of Contract in addressing and resolving various contractual issues during the Project
Name of the Organization, Period & Position Nature of the Project My Responsibilities
C. Construction of VAG Corridor of elevated MRTS (Mass Rapid Transit System) (Metro Rail) in Mumbai
Client: Mumbai Metro One Pvt. Ltd.
EPMC: Parsons Brinckerhoff -Systra JV
Value: USD 304 Million (Appx)
➢ Checking and certify Contractor's Monthly Progress Payment Application, Variation Claim
➢ Sourcing of quotations and evaluation of vendors pricing in Establishing Extra Items
➢ Monthly Cost Report of the project.
➢ Interpretation and implementation of Condition of Contract in addressing and resolving various contractual issues during the Project
Name of the Organization, Period & Position Nature of the Project My Responsibilities
mars 2009
A août 2009
General Consultant
à Dedicated Freight Corridor Corporation India Ltd
Lieu :
Inde
From March 2009 to August 2009
D. Construction of Dedicated Freight Corridor between Bhaupur to Khurja on Eastern Corridor (Railway)
Client: Dedicated Freight Corridor Corporation India Ltd.
General Consultant: Parsons Brinckerhoff India Pvt.Ltd. as lead partner in consortium
➢ Pre Tender work - undertaking detailed Cost Estimation w.r.t. the conceptual design of the Project
➢ Contract Pricing Document with payment milestone
D. Construction of Dedicated Freight Corridor between Bhaupur to Khurja on Eastern Corridor (Railway)
Client: Dedicated Freight Corridor Corporation India Ltd.
General Consultant: Parsons Brinckerhoff India Pvt.Ltd. as lead partner in consortium
➢ Pre Tender work - undertaking detailed Cost Estimation w.r.t. the conceptual design of the Project
➢ Contract Pricing Document with payment milestone
mai 2008
A octobre 2008
Quantity Surveyor
à Transcore LP
Lieu :
Émirats Arabes Unis - Dubaï
Client and Subcontractor Billing, Variations, Contract, Commercial Reports
décembre 2007
A mars 2008
Quantity Engineer
à Wilbur Smith Associates India
Lieu :
Inde
Contractor Billing, Variations, Contract
mars 2005
A juillet 2006
Quantity Surveyor
à Al Naboodah Contracting LLC
Lieu :
Émirats Arabes Unis - Dubaï
Client and Subcontractor Billing, Commercial reports, Variations
janvier 2003
A février 2005
Quantity Surveyor
à Essar Constructions Ltd.
Lieu :
Inde
Client and Subcontractor Billing, Variations, Revised BOQ, Progress reporting
novembre 2001
A décembre 2002
Quantity Surveyor
à Elsamex-TWS-SNC Jv
Lieu :
Inde
Client and Subcontractor Billing, Progress reporting
avril 2001
A octobre 2001
QS Engineer
à SPCL
Lieu :
Inde - Mumbai
Client and Subcontractor Billing
février 1998
A janvier 2000
Quantity Surveyor
à BEB (P) Ltd.
Lieu :
Inde - Mumbai
Client and Subcontractor Billing, Estimation
mai 1996
A novembre 1997
A. S. Sengupta & Associate
à Tezpur (India)
Lieu :
Inde
A. S. Sengupta & Associate, Tezpur (India)
From: May '96 To: Nov '97
Engineer
Govt. of India Approved Engineering Consultancy in Execution of the PWD, MES (Military Engg. Services) Internal Roads and Building Constructional Works, Details Planning, Design, Estimation for the Construction of Residential and Commercial Building, also in the valuation of the Immovable Properties for the need of the National Banks, Court, Insurance Sectors, etc.
➢ Estimate the Quantity for the Project for the execution of the works by the Contractor
➢ Supervision of the Road and Building works by the contractor
➢ Planning, Design and Estimation for the construction of new Residential and Commercial Building
➢ Evaluate the valuation of the Properties (Land & Building Method)
From: May '96 To: Nov '97
Engineer
Govt. of India Approved Engineering Consultancy in Execution of the PWD, MES (Military Engg. Services) Internal Roads and Building Constructional Works, Details Planning, Design, Estimation for the Construction of Residential and Commercial Building, also in the valuation of the Immovable Properties for the need of the National Banks, Court, Insurance Sectors, etc.
➢ Estimate the Quantity for the Project for the execution of the works by the Contractor
➢ Supervision of the Road and Building works by the contractor
➢ Planning, Design and Estimation for the construction of new Residential and Commercial Building
➢ Evaluate the valuation of the Properties (Land & Building Method)
Partager sur Facebook