Work Experience

Total years of experience :18 years, 6 Months

General Electrical Engineer at SPECTRUM SYSTEM INTEGRATION SSI
  • Pakistan - Islamabad
  • January 2019 to March 2022

Project:(a) World Bank Refurbishment works Client World Bank (b)Ufone Towers Sites (c)
Microsoft office Electrical Works, (d) NTC Building Electrification works Client NTC

 To follow the time schedule of project activities and verify the progress on daily, weekly
and monthly basis
 Coordinate with the Construction Manager to meet the site requirement for materials,
equipment and manpower according the plan and follow-up the provisions of the same
with the Project Management and other departments.
 Prepare the monthly invoices for the works executed and material delivered within the
specified time and per the terms and conditions of the contract.
 Check the subcontractor’s monthly invoices according to the contractual conditions prior
to approval by the Project Manager.
 Supervision, Installation and maintenance of electric motor, transformers, generators, LV
and ATS panel boards.
 Preparing electrical material demand as per site requirement and pursuing it
 Supervision and maintenance of internal and external electrification, underground
cabling Networking, TV system, Telephone system, Fire alarm system, grounding,
lightning protection system and also look after the AC units
 Prepare the project requirements (materials, manpower and equipment) and submit the
technical advice after consulting with the Project Manager and Site Manger. Ensure timely release of drawings by the design team so that the project execution team
can quickly commence the work at site.
 Bring to the notice of Project Manager immediately any unresolved design, material and
approval of submittal issues so that the same can be settled with the client on urgent
basis.

Consultant Senior Engineer at Nespak/Turkpak
  • Pakistan - Islamabad
  • March 2018 to December 2018

Project: Construction of Infrastructure & Allied Facilities for NEW ISLAMABAD INTERNATIONAL AIR PORT Metro-bus-Service.


 Review the drawing with the cross check with BOQ.
 Review design documents/Drawings of all electrical systems to ensure compliance
with Project Technical specification and all applicable codes and standards.
 Inspection of Grounding system, power points for lighting, power plug, AC & Low
Current system Fire alarm, Magnetic door, Public address, security system,
Communication system & all technology systems.
 Check the essential arrangements before starting of any electrical activity
 Check the quality of the material at site and get all the unapproved/rejected
Material removes from the site.
 Appropriate and timely curative action for achieving of project objectives.
 Keep complete record of each activity by filling the Performa.
 Maintaining and updating record of project office.
 Preparation of monthly project progress report.

Electrical Engineer at DAR ENGINEERING
  • Saudi Arabia - Jeddah
  • October 2016 to February 2018

Project :(a) Prince Mohammed Medical City Jeddah, (b) Neuroscience Centre KFMC
Jeddah, (c) Construction of Jeddah Airport Housing-2 110/13.8KV substation Jeddah


Review design documents/Drawings of all electrical systems to ensure compliance
With Project Technical specification and all applicable codes and standards.i.e
SASO, IEC, ANSI, ASTM, IEEE, NEPA, UL, NEMA, EIA, ISO
 Design review of all types of schematics, Scaled, coordination, MEP drawings.
 Material inspection at site according to the requirement of specification and codes.
 Check the Field inspection report according to approved shop drawing and applicable
codes and standard.
 Ensuring that materials are received in accordance with the quantity & quality.
 Attending the daily and weekly progress meeting for site work.
Review the material quantity, material submittals and site check request and shop
Drawing.
 Coordinating with Architect in developing structural concepts & plans.
 Check the essential arrangements before starting of any electrical activity.
 Check the quality of the material at site and get all the unapproved/rejected
Material removes from the site.
 Assist P.M in meetings at project office with Clients and Contractors to scrutinize the
progress of work.
 Visiting the site to see the progress and supervise how to work in a better way.
 Keep complete record of each activity by filling the Performa.

Electrical Lead Engineer at SPECTRUM SYSTEM INTEGRATION SSI
  • Pakistan - Islamabad
  • October 2015 to September 2016

Project:1) Construction of 40 Villas At Golf City for Bahria Town Islamabad Phase 6, (2): 20
Apartments Block, (3): Construction of AU Residential Block client Bahria Town

Supervising the Installation, testing and commissioning of Electrical systems including
wiring and cabling for power distribution and Lighting as per IEE, and British standard.

 Supervising of installation of complete electrical works, grounding networks, lighting
protection system, AC/DC panel boards, LV and power cable networks, data and
Telephone system, CCTV & FA system indoor and outdoor electrification.Supervsion of
cable laying and installation Electrical equipment Transformer(67& 2MVA power
Transformer), local motor control centre, 11kVSWGR’s & Capacitor Banks/Power Fatcor
Improvement Condensers and making sure that installation is according to specification
and approved drawings.

Electrical Engineer at JUMA AL MAJID GROUP
  • United Arab Emirates - Dubai
  • June 2012 to September 2015

Project:(1) Constrution of Jubilee(Flag staff house), (2):20 Apartments Block, (3) :Construction
of AU Residential Block

 Preparing the design for Electrical Power, Low current, Fire Alarm Elect Load Calculation
(Cable sizing, Voltage drop, short circuit coordinates study, Power factor calculation,
single and three phase power calculations ).Based on International study as I.E.E.E
, BS, UL etc and local authorities.
 Providing show drg scheme from contract drawing to prepare shop drawing for approval
and site works. Preparing Material submitted as per specifications in coordination with consultant &
Local authorities for approval.
 Preparing work Schedule/Planning, Sequencing of work monitoring progress &
coordination with other services (Arch, Structure, Plumbing A/C).
 Cost Estimation & Quotation preparation for Electrical System.
 Manpower allocation, giving technical guideline to Foreman & Supervisor, Execution of
Project with Installation & ensuring good quality/workshop hour.
 Testing & commissioning of the Electrical system (wiring, cabling and equipment) as per
Q/C procedures and manufacturer recommendation till final handover to the end user.
 Coordination with technical department for electrical issues.

JUNIOR ELECTRIAL ENGINEER at EL ALAN Construction Nigeria Ltd
  • Nigeria - Lagos
  • June 2009 to May 2012

Project: TANGO TOWER, OAK VILLA IKOAI (VILLAS)

 Detail site inspection of the Electrical work to ensure strict adherence to the approved
Construction drawings and technical specifications.
 To prepare realistic plans for implementation, critically monitor execution and
recommend
 Appropriate and timely curative action for achieving of project objectives.
 Review the documents and test reports of materials regarding quality and specification
requirements.
 Check the quality of the material at site and get all the unapproved/rejected material
remove from the site.
 Review the material quantity, material submittals and site check request and shop
drawings.
 Assist P.M in meetings at project office with Clients and Contractors to scrutinize the
Progress of work.
 Assist P.M in Correspondence with the Client, Regional Office and Contractor.
 Check the essential arrangements before starting of any electrical activity.
 Keep complete record of each activity by filling the Performa.
 Maintaining and updating record of project office.
 Preparation of monthly project progress report.
 Preparation of physical & financial status reports on monthly basis

Electrical Engineer at Ericsson Pakistan PVT LIMITED
  • Pakistan - Islamabad
  • October 2004 to May 2009

Projects:
Insta phone Tower project Gensets padding, Moblink Ph2, PH3, ph4, Warid Project 7.1, 7.11

 D.G Sets, Power Transformers, HT Switchboard, LT Switchboard, LT Distribution boards,
HT / LT Cables, Bus-Bar Trunking System, Small Power / Lighting Wiring, MCCS,
Earthing, Light Fixtures, Lightning Protection, Structured Cabling, Fire alarm & detection
system etc.
 Commissioning & Integration of Ericsson Product Radio-Base-Station RBS/BTS 6000
series (6301, 6101, 6102, and 6201).
 Commissioning includes loading of DUG’s, RRU’s01 for 6301(B3 for DCS and B8 for
900 band), RUS’s02 (B3 & B8) for 6101, 6102, 6201 via OMT.
 Implementation of MCTR power for RRU’s & RUS’s of RBS 6000 via OMT.
 Performing soft, hard, and band addition expansion as per RF plan.
 Trouble shooting & Support of RBS (BTS) 6000 series for internal alarms rectification.
Connectivity and verification of external alarms with switch AXE E// BSC via latest
release SW version OMT.
 Reduce the RF KPI’s on GRAN Sites for newly integrated sites.
 Communicate with RF Engineers and BSC integrators for rectification of Internal alarms,
DCR drop call rates, TCH availability degradation, SDCCH drops, cells sector
degradation and unavailability, DUG malfunctioning, high VSWR, Antenna Jumper
mismatch, Health check & support provided from Antenna jumper to Bts RRU/RUS
termination.
 Problem solving highly escalated Customer support Requests on RAN RBS/BTS
6000(6101, 6102, 6201, 6301) series.
 Software Used for RAN 2GOMT ver. (48, 49, 50, & 52).
 Commissioning & Troubleshooting of Ericsson Transmission Equipment TN MinilinkTN
Release 4.0 nodes 6p/2p/20p and CN Nodes.

Trainee Engineer at Ericsson Pakistan PVT LIMITED
  • Pakistan - Islamabad
  • October 2003 to September 2004

Complete Planning of Pad Mounted Transformers and Distribution Boxes in all sectors
On the basis of the calculated approximate load required per subscriber.
 Laying of Underground 3-phase Power Lines
 Megger testing of the cables before giving connections
 Connecting, testing and commissioning of the RMU’S and Pad Mounted Transformers
Distribution Boxes and SLCP (Street Light Panels)
 Preparation of Quotation and B.O.Q’s, Maintain all the project data, coordination with
customers
 Presentation of Project status in front of our customer as per our progress at each stage
 Coordination with customer and site engineers and supervisors to overcome their problems
 Visiting site to see the progress and supervise engineers how to work in a better way
 Also conducting meetings in office how to work as a team and to achieve our goals on
time

Education

Bachelor's degree, ENGINEERING (ELECTRICAL AND ELECTRONICS
  • at N.W.F.P UNIVERSITY OF ENGINEERING AND TECHNOLOGY PESHAWAR
  • October 2003

Having been placed with First Division with HONOURS

Specialties & Skills

Integration
Planning
Microwave
CABLING
LIGHTING
MEETING FACILITATION
MICROSOFT OFFICE
TELEPHONE SKILLS
FILE MANAGEMENT
GRAPHIC DESIGN
NETWORKING

Languages

English
Expert
Urdu
Expert
Arabic
Intermediate