Mills & Vertical cement mill and Project Engineer (E&I) in Project section.
RESPONCIBILITIES:
Preparation of MCCs and Control & Protection Schemes
Testing, commissioning and maintenance of equipment
HV, MV and LV Switchgear
Protection Relays
Transformers
AC Induction Motors (MV & LV) up to 5000kw
Variable Frequency Drives (MV & LV) up to 2000kw
Preparation of Single Line Diagrams.
Review of schematics of Switchgear, MCC, Control & Protection panels and local control panels.
Inspection and testing of switchgear of powerhouse substation (37MW) with 3xDF, 2xSG & 2xHFO GENSETs and Waste Heat Recovery PowerPlant(20MW) with Steam Turbine, 7xWaste Heat Recovery Boiler and 1xCFB.
Conducting regular preventive and breakdown maintenance
Carrying out regular system checks, planned shutdowns and major repairs
Execute maintenance and repair operations in accordance with the manufacturer's specifications
Maintain all necessary records pertaining to work performed stock on hand and electrical equipment’s used as directed by the Maintenance Manager.
Project Coordination
PROJECTS
Worked as Project Engineer on the 225tph vertical cement mill project (July 2017 to Dec 2017)
Worked as Project Engineer on the Waste heat recovery power plant (20MW) and Coal fired boiler with Steam Turbine (2016~2017)
Worked as Project Engineer on the shifting of 1200tph limestone crusher and installation of downhill belt conveyor(3.15km) with Regenerative Drives (2015~2016)
Worked as Project Engineer at New Packing Plant with FLSmidth Ventomatic 16spouts. Designed the complete switchgear, MCCs and PLC Panels. Supervised the erection team and commissioned the packer. (2014~2015)
Worked as Site Engineer at ABB VFD(ACS800 and ACS2000) installation project at Cooler Fans. (2014)
Worked as Project Engineer at new 132Kv Grid station. It was energized at existing 66kv line. All the equipment installed are compatible both for 66kv and 132kv. Transformer of rating 46MVA dual winding 66, 132/6 kv OLTC. I worked as site engineer with Chint Electric Commissioning Engineers (2012~2013)
Worked as Site Engineer at 250tph and 300tph Hammer Crusher (2011~2012)
Erection, testing and commissioning of 1500KVA 6kv/.4kv Power transformer, 300tph hammer crusher with MV motor, 250tph hammer crusher and designing of motor starters, Control and protection scheme.
Worked as Project Engineer at new Stationery Packing Plant.(2011)
Worked with Commissioning Team at 66Kv Grid Station with 2x6MVA transformers (66/6kv) (2010~2011)
Designed the MCC for Pumping stations, cooling towers and crushers
Computer Aided Drawings in Semester Winter 07