Sr. Project Manager
ECG Engineering Consultants Group
Total years of experience :30 years, 0 Months
(3) + (2) Health Centers
Al Shamal Health Centre
Client: PWA
B+G+1st building including Administration Offices, Walk-In Clinics, Dental Clinics, Dialysis Units, X-Ray, Pharmacy and Laboratory, in addition to Wellness Centre including Swimming Pool, Massage and Steam Rooms.
The Project also includes Ancillary buildings such as Watchman rooms, Guard House, Service Building, Mosque, Ambulance Garage and Waste Hold
KAHRAAMA Project
Upgrading of Mesaieed Town RPS
New Two x 6 Million gallon working capacity rectangular reinforced concrete reservoirs, each consists of 2 nos. compartment including all necessary works of piping, electrical, instruments, landscaping, sewers etc. Addition of New VFD pumps to existing Mesaieed town. Standby pump house for existing tanker filling station and new chlorination building. Improvement of internal piping, refurbishment of existing services and addition of new facilities. Construction of approximately 8.1 Kilometers of new600mm and 3.9 kilometers of 900mm, rising mains pipelines and associated works chambers from inside.
Banana Island Resort
Banana Island is an uninhabited offshore island situated approx. 3 km from Doha airport. It comprises 141 keys and associated services comprising: over water villas, land villas, family suites, hotel suites, spa, restaurants, pools, jetties, marina for 50 boats, artificial reefs & entertaining areas.
* Managing & following up executing of Dukhan area projects for QATAR
PETROLEUM.
* Managing engineers/ labors. Organizing, supervising & following up all
sites crew; Engineers, Supervisors, & Labors.
* Coordination & following up with QATAR PETROLEUM ( projects
owners)
* Building and maintenance of petroleum buildings, Oil and Gas
departments and pipe lines in accordance with MEP& Electrical
departments.
* Coordination with Sub Contractors.
* Managing & following up supplying of material.
* List of projects :
1-EPIC OF CIVIL WORKS AT ZEKREET - DIYAB
CARRIAGEWAY INTERCHANGES WITHIN DUKHAN
FIELDS. GC-10107500.
2-EPIC OF EXTENSION OF DSSA MOSQUE WITHIN DUKHAN
FIELDS. LC-10108800.
3-EPIC FOR NEW CONTROL ROOMS AT KMDS, KSDS &
LOCAL EQUIPMENT ROOM AT KNDS. GC-09102000.
4-DESIGN OF STRUCTURES AND CONSTRUCTION OF
WORKSHOPS & OFFICES AT QPSFA IN DUKHAN. GC-
09111800.
5-CONSTRUCTION OF NEW PROJECT OFFICE, DRAWING
OFFICE & CENTRAL DOCUMENTATION LIBRARY AT
DUKHAN. GC-10107400.
6-INTERNAL REFRESHMENT, RENOVATION & UPGRADING
WORKS AT DUKHAN CINEMA. GC-10107700.
7-RESURFACING OF EXISTING ROADS & LANDSCAPING
WORKS AND BEAUTIFICATION IN DUKHAN. GTC
* Managing & following up executing of Post Tension work in sites.
* Managing 30 engineers/ technicians. Organizing, supervising &
following up all sites crew; Engineers, Technicians, Labors & Drivers.
* Coordination with Main Contractors & Consultants.
* Coordination with post tension 3rd
party.
* Submitting & following up project claims.
* Managing & following up supplying of PT material.
* Managing & following up the main store.
* Managing & controlling all the office stuff.
* Preparing & following up Quotations, Proposals and tenders for new
projects.
* Study & following up new contracts.
Post Tension Contractor.
• Managing & following up executing of Post Tension work in sites.
• Managing 30 engineers/ technicians. Organizing, supervising & following up all sites crew; Engineers, Technicians, Labors & Drivers.
• Coordination with Main Contractors & Consultants.
• Coordination with post tension 3rd party.
• Submitting & following up project claims.
• Managing & following up supplying of PT material.
• Managing & following up the main store.
• Managing & controlling all the office stuff.
• Preparing & following up Quotations, Proposals and tenders for new projects.
• Study & following up new contracts.
• List of projects:
1- HOTEL PROJECT IN UMM GHOLINA.-B+G+M+7
2- AL MAHA ENGLISH SCHOOL- B+G+1
3- AL NOOR TOWER IN ALDAFNA - 2B+G+F+S+22+R
4- GRAND REGENCY HOTEL EXTENTION -2B+G+6
5- KHALED TOWER IN ALDAFNA - G+1st+27
6- AL ASIRI TOWER IN ALDAFNA - B+G+21+R
7- GRAND HAYAT HOTEL
8- MADINAT KHALIFA RESIDENTAL BUILDING B+G+3
9- AL BAKER RESIDENTAL TOWER IN AL DAFNA- 2B+G+2P+42
10- SAHARA RESIDENTAL TOWER IN ALDAFNA - 1B+G+CH+25+2PH
* Managing all civil maintenance over a team of 25 Engineer/ Technician.
* Supervisions for all new constructions and pipe lines.
* Handling all direct relations with all Sub contractors.
* Building and maintenance of petroleum companies, tanks and stations,
Oil and Gas departments and pipe lines in accordance with MEP &
Responsible of executing the following projects :
1) Alexandria Green Plaza Mall:
* Interior finishing of the Cinema Complex.
* Exterior finishing of the Entertainment Building elevations.
* Water supplies, pipe system and the interior finishing of bathrooms.
2) Hilton Plaza, Annex and Conference building.
Supervision and executive work of the dewatering, piles and deep
foundations, concrete skeleton and steel constructions of Al- Horeya
Towers, Fawzi Ma’az St. Smouha Alexandria.
3 Buildings - B +2M+G+12
Deep foundations and retaining walls were done by ALTAHAN Co. as a
main contractor.
The steel constructions were done by MAMDOH HOSNY’s company as a
main contractor.
The concrete skeleton was done by a workmanship contractor.
The execution of the concrete skeleton was under the consultant
responsibility.
Supervising the following projects:
* Constructing the building of childcare, Koam El- Dekka.
* Repair works of the Labor Hospital of Karmouz.
* Repair works of the Cotton Warehouse, The National bank Of Egypt,
Mena Al- Bassal.
* Repair works of Al Shatbey child Hospital.
* Repair works of the Whitening Hanger Building, Rakta Paper Company.
* Executive Acid Resistant insulation and Flooring Work of the Whitening
Hanger Building, Rakta Paper Company.
* Demolishing and reconstructing the “HIBO Tanks” Of The Whitening
Hanger Building, Rakta Paper Company.
* Repair works of the hanger buildings of combustion and filtering of the
Whitening Hanger Building, Rakta Paper Company.
* Acid resistant insulation and flooring work of Whitening Hanger Building,
Rakta Paper Company.
* Repair works of the Factory of Medical Tapes, Alexandria Drugs
• Designing and supervising the Executive works of the Concrete Foundations and mass Steel constructions of the Following projects:
• Coating work of the ground yard of the BBC School, the Haykestep- Cairo.
• The factory of “Ceteroin” Automotive in Cairo.
• In addition to a number of minor operations.
courses: PROJECT OF GRADUATION: Surveying. Society of Engineers Membership & Certified from Sharja Municipality - UAE