Construction Manager
Ramaco Trading & Contracting
Total years of experience :15 years, 0 Months
- Preparing and implementing a construction schedule to execute the works in a timely manner and according to specifications & drawings.
• Coordinating on a daily basis with owner representative, consultant, UDC, subcontractor, & suppliers.
• Liaising with procurement/purchasing department for the proper selection &
requisition of subcontractors & construction materials
• Supporting the engineering department in shop drawing production
• Building and managing a team to deliver the project according to the agreed upon baselines.
• Executing works according to project specs and authorities' requirements (Ashghal, kahrama, Marafeq etc.)
• Preparing project schedule including 1-2 month look ahead to measure progress.
- Developing & managing a team to execute the work according to scope, schedule,
& cost baselines.
• Managing the proper selection & requisition of plant & construction materials.
• Liaising with owner representative, consultant, subcontractor, & suppliers.
• Coordination with MEP team to ensure the proper & timely succession of project activities.
• Overseeing the implementation of the project quality plan and the health/safety policy plan.
• Preparing status & progress reports for project manager.
• Measuring activity progress & comparing it to the schedule baseline. Developing a 2 weeks to
6 month look ahead schedules. Executing works according to project specs and authorities' requirements (Ashghal, kahrama, Marafeq etc.)
Concrete & Finishing Works at “Development of ISF Camp package CPC7A” a 1 billion dollar plus mega military camp construction project consisting of several barrack buildings, general stores, sub-stations, parking lots, & circulation roads.
Duties:
• Developing & managing a team to execute the work according to scope, schedule, & cost baselines.
• Managing the proper selection & requisition of plant & construction materials.
• Liaising with owner representative, consultant, subcontractor, & suppliers.
• Coordination with MEP team to ensure the proper & timely succession of project activities.
• Overseeing the implementation of the project quality plan and the health/safety policy plan.
• Preparing status & progress reports for project manager.
• Measuring activity progress & comparing it to the schedule baseline. Developing a 2 weeks to 6 month look ahead schedules.
Concrete & Finishing works at “Summerland Project” a 250 million dollar luxurious hotel & beach resort consisting of a hotel, several chalets, swimming pools, underground parking, & a marina.
Duties:
• Managing the construction team to execute the work according to drawings, specifications, schedule, & budget.
• Overseeing the compliance of subcontractors to specifications & scope of work.
• Supervising a quality control team & coordinating with the consultant on a daily basis.
• Coordination with suppliers to ensure the timely arrival of requested construction material.
• Preparing status & progress reports for upper manager.
• Providing technical advice for problems arising during construction.
Mobilization & Concrete works at "THE ONE
Project" An elliptical night club facility, Beirut
Concrete & Finishing work at "Le Patio Project"
Five residential buildings, Beirut
Full time Graduate/Teaching Assistant
Internship in the Geotechnical Department, Design work
Training in several Projects:
• Structural Work at Etihad Towers, Abu- Dhabi.
• Finishing Work at Sky Towers, Abu-Dhabi.
• Foundation Work at an Industrial plant, Fujairah.
• Structural Work at Elite Tower, Dubai.
Aug/07-Sept/07 Civil Engineering Camp organized by Civil Engineering
Society (AUB)
Road Surveying, House Construction, and AutoCAD drawing
Sept/09-Feb/11 American University of Beirut, Lebanon (AUB) Master's in Engineering Management, GPA 93
Sept/05-Jun/09 American University of Beirut, Lebanon (AUB) BE in Civil Engineering, Placed on Dean's Honor List