Total years of experience :10 years, 5 Months

piping engineer at Technip
  • India - Hyderabad
  • December 2018 to December 2019

 Ensuring compliance of the work with the project design and applicable company & International standards.
 Ensuring that the work performed in line with project schedule.
 Reviewing of sub contractors schedule and related activities logic sequence and workloads.
 Monitoring adequacy of sub-contractors quantity & quality of construction equipments & cranes etc.
 Monitoring adequacy of sub contractors quantity & quality of trade workforces and supervision.
 Monitoring & Appraising the quality of work, monitoring the daily progress and reporting to
management.
 Ensuring the availability and use by sub contractors of the latest revision of drawings.
 Reviewing sub contractors fabrication/ construction and lifting method of statements.
 Witnessing & supervising the construction activities, punch list issuing, hydro testing and precommissioning activities like air blowing, water flushing, chemical cleaning, steam blowing, pigging of pipelines.
 Dealing of any technical query in the site during construction.
 Ensuring that all As-built drawings and Certification documents are issued in due time.
 Following the line management instructions and providing adequate feedback.
 Overseeing of Safety management system at the work place and participating safety audits.
 Encouraging and promoting of all company performing objectives at work site.
 Coordinate with the Client Engineers/Inspectors for Mechanical Completion Walk Down

piping engineer at Daelim Engineering
  • Saudi Arabia - Jubail
  • February 2013 to June 2018

•Monitoring the work activities & workforce requirements to achieve the target on time together with optimized productivity.
•Planning & directing the work for all crafts involved in construction activities in alignment with available tools, construction equipment & materials.
•Coordinating & implementing indirect activities, internal & external, required to support a productive construction execution.
•Carry out Inspections, Site surveys and dimensional check to ensure piping fabrications are as per design drawing and comply with project specification.
•Coordinating with QC Dept for the execution of RT, PWHT, HT & Spool releasing.
•Preparation of Furnace piping test packages including limit identification, applying golden joints & getting approval from company.
•Preparation of Technical query, Site instruction & Request for variation
•Scheduling & executing the testing activities as per the priority list submitted by client.
•Monitoring the hydro test activities to make sure test execution as per project Specification.
•Monitoring the Re-instatement works and box up.
•Played an active role in the development of safety culture on the project and making safety an integral part of all work performed

(i) Piping Engineer at Mohammed Al Mojil Group
  • Saudi Arabia
  • September 2011 to August 2012

i) Piping Engineer Sep '11 - Till Date
Mohammed Al Mojil Group- Kingdom of Saudi Arabia.
Project: Manifa Cogeneration Project. Client: Saudi Aramco.
Project Value: USD 67 Million

Responsibilities
Supported the Discipline elements for the Construction of the Karan Utilities & Cogeneration Project, roles and responsibilities are detailed below as a Generic representation of Construction duties.

• Reviewing of construction drawings and specification as per contract.
• Preparation of the Red line Markup of all piping drawing.
• Take corrective action as per site memos, information and non-confirmation report (NCR)
• Resolve contractor raised queries in conjunction with technical support group.
• Carry out Inspections, Site surveys and dimensional check to ensure piping installations are as per design drawing and comply with project specification.
• Fluent with Standard Codes like ASME 31.3, 31.1, Section IX and ARAMCO specification.
• Preparation of all Hydro test packages mainly equipment related piping such as Gas Turbine, Steam Turbine etc based on priority of client.
• Monitoring the hydro test activities to make sure test execution as per project specification.
• Preparation of final list of Valves, Special piping items and their specification for Pre- Commissioning Work.
• Finalize billing based on bill of quantity and site progress report and reconcile the BOQ with client representative

Mechanical Engineer at JGC KBR
  • Qatar - Doha
  • October 2009 to March 2011

iii) Mechanical Engineer Oct '09 - Mar'11
JGC KBR, Doha, Qatar.
Project: Qatar Shell Pearl Gas to Liquid Project.
Contract Value of the Project: 60 Million U.S.Dollars

Responsibilities
Supported the discipline elements of the commissioning of the shell GTL C7 area which consist of on plot, off plot and product loading berth, roles and responsibilities are detailed below as a generic representation of commissioning duties

• Setting the test limits for all commissioning Test packs and worked as a commissioning test pack coordinator which includes Air blowing, Low Pressure & High Pressure test & purging of export pipelines.
• Checking the bolt tightness of the equipment's and Flange joints, Co-ordinates with final bolt torqueing document completion.
• Preparation of air blowing, Low Pressure & High Pressure test plans and procedure as per project specification and site condition.
• Preparation of commissioning packages for piping systems.
• Preparing and Implementing commissioning test plans and method statement for various activities involved in the construction of Oil &Gas facilities, Petrochemical plant as per shell project specification & Relevant International standards.
• Incoming inspection of various steel materials, consumables, tools and equipment's etc. with relevant documents like purchase order, Material test certificates. If required, perform mechanical test and chemical analysis in order to confirm specification and relevant International standards.
• Co-ordination with all Contractors and its Sub-Contractors staff, in order to ensure accurate, consistent and punctual reporting of all the data required.
• Coordinating with all RFP, RFC & RFSU activity.
• Preparation of Red line & Final As Built of all Piping Drawings.
• Preparation of system compilation manual for ready for Pre Commissioning, ready for Certificate & ready for startup.
• Assist in the resolution of Interface problems with other contractors.

(iv) Piping Engineer at Nasser.S.Al-Hajri Co. Ltd
  • India
  • November 2008 to October 2009

iv) Piping Engineer Nov '08 - Oct '09
Nasser.S.Al-Hajri Co. Ltd, Doha, Qatar.
Project: Qatar Shell Pearl Gas to Liquid Project.
Contract Value of the Project: 100 Million U.S.Dollars

Responsibilities

Supported the Discipline Elements of the Construction of piping in the Shell GTL C7 Area which
Consist of pipe errection, pipe support activity, hydro testing of export pipelines of C7 Shell project.
Roles and Responsibilities are detailed below as a Generic Representation of piping

• Dealing with Isometrics, General arrangement drawings & piping &instrumentation diagrams.
• Prepares the Welding Maps.
• Survey the quantity which will be fabricated in the fabrication shop as per Weld Map.
• Planning for daily site activities and allocation of resources for achieving the target.
• Monitoring the progress of manpower and equipment resources and planning for the mobilization and demobilization of the same.
• Preparing daily progress report and submitting to the planning department.
• Dealing with technical query on the site during construction.
• Punch list preparation for piping packages.
• Preparation and generate the all Hydro test packages as per the site Constructor and Client.
• Arranging and Scheduling Hydro test meeting.
• Controlling the activities of blowing the pipelines after hydro testing.
• Re-instatement works after the hydro test.
• Ensure safety and security of all construction activities.

(V) Junior Mechanical Engineer at Kiddie Engineering
  • India - Kerala
  • May 2008 to November 2008

Worked with Senior Mechanical Engineer for the Construction activities of Sulphur Recovery Unit
Following are the Activities.

• Planning the Work with available resources.
• Manpower Controlling and utilization.
• Preparation of Daily Site progress and welding report.

Education

Bachelor's degree, Mechanical Engineering
  • at Bharathiyar College Of Engineering
  • April 2008

Specialties & Skills

Social Profiles

Personal Website