Turbine Control Systems Design and Commissioning Engineer
MAPNA Electric and Control Company (MECO).
Total years of experience :17 years, 10 Months
Study and review basic and detailed design documents related to the STG such as P&ID, Logic diagram, Single Line Diagrams, Arrangements Diagrams, I/O list, Instrument list, Equipments connection diagram, etc.
Attend in meetings to review, comment or clarify the input document
Design the detailed design documents related to the Steam Turbine Power Plants Control System such as I/O List, Interconnection Diagrams, Cable List, Field Wire List, etc.
Design Control Program according to the input documents such as System Description, Control Philosophy, Control Flowchart, etc using FUP Editor (TELEPERM XP, SPPA T2000) or SIMATIC S7
Issue procedure and documents for FAT and SAT of STG Control System
Supervisory on activities related to the Commissioning of the STG Control System (DCS) such as Earth Test, ECC, Energizing, etc.
Load STG Control and Protection Program in the DCS PLCs
Function Test of STG before Startup as well as I/O Check, Calibration of Control Valves and Stop Valves, Instruments Setting and Programming, etc.
Supervisory on Turbine Startup and Troubleshooting of Hardware and Software of Control System in case of any problem
Evaluate the measuring, values and Trends and modify and optimize the setting of Control Program
Supervisory on all the Tests related to the Steam Turbine Control System such as Load Rejection, Over Speed Protection Test, House Load, etc.
Modify Control Program and HMI (Human Machine Interface)
Attend in meeting with client to negotiate and clarify the defects.
PareSar CCPP Project (SIEMENS E type) 2x160 MW
Iran LNG CCPP Project (SIEMENS E type) 2x160 MW
Key Responsibilities:
Supervisory on activities related to the Commissioning of the GT Control System (DCS) such as Earth Test, ECC, Energizing, etc.
Load Control Program DCS PLCs (SPPA T2000)
Function Test of Auxiliary Systems of Gas Turbine (SIEMENS V94.2) such as Lub Oil system, Hydraulic System, Fuel Forwarding System, Cooling System, etc.
Supervisory on Turbine Startup and Troubleshooting of Hardware and Software of Control System (SPPA T2000)
Review Measurements and Trends to Optimize Control Logic
Attending in Meeting with Client to Clarify the Defects and Negotiate about claims
Prepare Commissioning Report for back office.
Power Plant Projects in Iran :
South Pars SIEMENS V94.2 2x159 MW
Iran LNG SIEMENS V94.2 2x162 MW
Chabahar SIEMENS V94.2 2x162 MW
Kashan SIEMENS V94.2 2x162 MW
Quaen SIEMENS V94.2 1x162 MW
Orumieh SIEMENS V94.2 1x162 MW
Semnan SIEMENS V94.2 1x162 MW
Isfahan II SIEMENS V94.2 2x162 MW
Projects in Syria :
¬¬¬Tishreen CCPP, Damascus 2x162 MW
Project in Iraq :
AL Sadr GTPP, Baqdad 2x162 MW
Kazeroon CCPP Project 3x159 MW
South Pars Oil and Gas Field GTPP 4x40 MW
Key Responsibilities:
Lead I&C Commissioning team in I/O Check, Function Check and other DCS Commissioning Activities
Function and Trip Test the BPS and BMS (Boiler Protection and Burner Management System)
Implement and Modify HMI and Control Program according to the Project Documents
Prepare Daily Commissioning Report for Daily Meetings
Attend in Site Meeting to Solve Commissioning Problems related to the Control Systems
Solve Problems and Defects of DCS Commissioning and Guaranty Period
Responsible Technician for Troubleshooting and maintenance of Electric Switchgears,
1&3 Phase Motors, Air Compressor, Boiler, Pneumatic Control Circuits, Instruments, etc.