Quantity Surveyor
GREENLINE INTERIORS
Total years of experience :19 years, 4 Months
Preparation claim for Additional work and Variation.
Produce monthly cost, value report & cash flow information.
Prepare Sub-Contractors payment certificates.
Budgeting & Cost analysis of the project Fire Station-Pearl Qatar
Inspecting and Valuing completed work Lusail Marina 50- Lusail City
Produce monthly cost, value report & cash flow information TB Hospital-HMC
Preparation for claim Additional work and Variation
Prepare Sub-Contractors payment certificates
Prepare B.O.Qs for additional works
Checking B.O.Q’s and Drawings made a report for the Lawn facility
Inspection and Valuing completed construction work.
Inspection and Valuing properties for Lawn facility.
Re-valuation properties as per request.
Consulter-Spanish Red Cross (2009) - Tsunami Housing Projects
Communication with Organization, Local authorities and Contractors.
Attending project consultant meeting and liaising with our Delegate, Construction team and Contractors.
Communication with Organization, Local authorities and Contractors.
Attending project consultant meeting and liaising with our Delegate, Construction team and Contractors.
Responsible for managing all project cost from pitch to completion Belgium Recreate and Convention Centre
Undertake cost analysis for building project W. M. Mendis Hotels(PVT) Ltd
Attending Project meeting and liaising with stakeholders
Inspection and valuing completed work
Produce monthly cost value, value report and cash flow information
Preparation for claims additional work and variation
Prepare Sub-Contractors payment certificates
Budgeting and Cost analysis of the project. Colombo Air Port Project
Inspection and valuing completed work Factory Plant 04-Rhino Roofing Products
Produce monthly cost, value report and cash flow information
Preparation for claim additional work and variation
Prepare sub-Contractors payment certificates
Responsible for managing all projects cost from pitch to completion Housing Projects and Commercial Buildings
Inspection and Valuing completed work
Managing Housing maintenance services
Preparation for claims additional work and variations
Responsible managing all projects cost from pitch to completion. Housing Projects and Commercial Buildings
Inspection and valuing completed work
ALMA Group Structural Water Proofing (1998)
Inspection and valuing completion work Basements, Roof Tops and Structural Repairs
Leveler, Court Commissioner and Valuer)
Quantity Survey (National Certificate of Technology)