Asst. General Manager
Shapoorji Pallonji Mideast LLC
Total years of experience :39 years, 1 Months
Project Director: Cayan Cantara 2B+G+M+4P+46/38 Floor Twin Tower Residential and Service Apartment.
Project Value: AED 657 Million
Location: Dubai Science Park Dubai.
Earlier Completed Project: Mudon Phase II 404 Villas (120 Town Houses and 284 Free Standing Villas)
Value: AED 588 Million.
Working as Asst.General manager.
Projects.
1. Meydan community center. 2013
2.Mock up villa for Meraas with cellate technology 2013.
3. Horizon English school additional construction 2013-2014.
4.Al Khail Heights residential Project Al Quoz 2014-2015.
5. 300 Villa envelopment in Um Nahad, Al Ain Road for Meraas. 2015-2016.
6.Land Mark Building in Dubai Marina Final Completion and Handing over 2016.
7. Mudon 404 Villas completion and final Handing over to Dubai Properties 2016.
8. SP own Labour Accommodation building in DIP 2015-2016.
WORKING EXPERIENCE:
Name of the company: Al Jaber Transport and General Contracting,
Position : Project Manager
Duration : Sep. 2011 to Till the Date
Assigned project : Construction of 2080 Villas at Al Falah, Abu Dhabi,
Client : Al Dar Developer,
Consultant : WS Atkins and Flour Project Management
Cost of the Project : Dhs.2.70 Billion
Project Description and Responsibility:
• In charge of One Section consist of 300 above Villas.
• In charge in boundary wall erecting for villas.
• Co-ordinate with infrastructure contractors, PM and Engineer office.
• To Monitor and control the sub-contractor (MEP and Civil).
Assigned project: Construction of 2080 Villas at Al Falah, Abu Dhabi,
Client: Al Dar Developer,
Consultant: WS Atkins and Flour Project Management
Cost of the Project: Dhs.2.70 Billion
Project Description and Responsibility: • In charge of One Section consist of 300 above Villas.
• In charge in boundary wall erecting for villas.
• Co-ordinate with infrastructure contractors, PM and Engineer office.
• To Monitor and control the sub-contractor (MEP and Civil)
Name of the company: Transfield Power & Constructions,
Position: Sr. CONSTRUCTION MANAGER / PROJECT MANAGER
Duration: Jan. 30, 2010 to Jan. 2011
Assigned project: Construction of 786 Villas at Gayathi, UAE.
Client: Musanada (Abu Dhabi General Services Company)
Consultant: Egis-Core Project management & Consultant.
Cost of the Project: Dhs.943 Million
Responsebility: • Direct and guide the Project Engineers to execution of works according to approved planning Schedule.
• Monitoring day to day activity against manpower verses productivity according to planning schedule.
• Monitor and controlling procurement of materials and resources.
• Co-ordinate with consultant / client for approvals and other issues.
• Conduct the site Progress meetings with Project engineers and sub contractors.
Name of the company: PIVOT ENGG & GEN. CONT. CO. W.L.L.
Position: CONSTRUCTION MANAGER / PROJECT MANAGER
Duration: June 18, 2007 to Jan. 2010. & 2011
Assigned project: 2B+G+6+1R Deluxe Hotel Apartment Al Barsha, Dubai.
Client: MTK Real Estate
Consultant: Al Baha Engineering Consultants
Cost of the Project: AED 59.5 Million
Project: Luxury Villas Resort in Bahraini Island in Abu Dhabi
Client: M/s Emirates land Group
Project Manager: M/s Roya International
Consultant: M/s Dewan Architects and Engineers
Project: 170 Villa at MBZ City in Abu Dhabi as Const. Manager
Client: M/s International capital Trading
Consultant: M/s Ewan Engineers and Architects.
Name of the company: Al Jaber Transport and General Contracting,
Position: Sr. CONSTRUCTION MANAGER
Duration: Sep. 2011 to Till the Date
Name of the company:, UGARIT INTERNATIONAL
Position: Sr. CONSTRUCTION MANAGER
Name of the company: NARESCO CONTRACTING LLC DUBAI 2005-06
Position: PROJECT ENGINEER
Assigned project: 1) B+G+M+3RES/COM.BLD Est.AED 50 million @ALBada
: 2) B+G+M+11+HC @PORT SAEED Est.AED 60 million.
DUTIES&RESPONSIBILITIES
• Managing the project for all kind of finishing works up to hand over.
• Monitoring the labor schedule and productivity.
• Convene the site meeting with finishing, MEP subcontractor.
• Co-ordinate with consultants and sub contractor.
Name of the company:, M/s CHERAN CONSTRUCTION Pvt.Ltd
Position: Senior Project Engineer
Duration: Sep. 2011 to Till the Date
DUTIES&RESPONSIBILITIES
• In-charge for initial conception to final handing over the projects (Various)
Name of the company: MR Hi-TECH ENGINEERS Pvt.Ltd; 1985-92.
Position: Project coordinator/site supervisor
DUTIES&RESPONSIBILITIES
• Preparation of sub contractor bill and site Q/S works.
• Supervising the civil, electro-mechanical and other works.
• Check the Quality on finishing and structural works as per the Quality plan.
• Preparation of inspection request as per the Inspection and Testing Plan.
• Preparation of weekly man power and material requisition.
• Preparation of work done report and manpower comparative schedule.
• Preparation of weekly progress and achievement report.
BACHELOR IN CIVIL ENGINEERING COMPUTER SKILL: MS OFFICE, AUTO CAD, PRIMAVERA (P6+PPM) PASSPORT: F 1899661 VALID UP TO 4 JAN 2015 KNOWN LANGUAGES: ENGLISH, HINDI, MALAYALAM AND TAMIL. I hereby declare that the above said information are true and correct to the best of my knowledge. M. NEDUNJERALATHAN.