Danilo Cesar, Quantity Surveyor

Danilo Cesar

Quantity Surveyor

SAIPEM ,KUWAIT KNPC Al-Zour Refinery

Location
Philippines
Education
High school or equivalent, DESIGN
Experience
21 years, 9 Months

Share My Profile

Block User


Work Experience

Total years of experience :21 years, 9 Months

Quantity Surveyor at SAIPEM ,KUWAIT KNPC Al-Zour Refinery
  • My current job since October 2017

of Duties : Preparing Itemizations for all Mechanical discipline and make a (PROM).
: Preparation of Daily Progress Report on-going work activities
for the Mechanical (Piping, Supports, Structural, Painting, Insulation).
: Monitoring of contractual schedule and progress based on the construction
execution plan generated by Project Control Department.
: Preparation of Weekly & Monthly Progress Report as per Company
standard.
: Project Cost Control and managing all concerns such as progress
measurements, payments, variation and additional claims.
: Final checking, review and loading of Subcontractor’s monthly Billing
into SAIPEM Accounting Database.
: Verify and approve payment of Subcontractor’s Monthly Billing (COLAV)
and inculcate Signature to finalize Accounting.
: Prepare correspondence to the Clients, to sites, inter-department
and subcontractors.

Quantity Surveyor at Saipem - Kuwait
  • Kuwait - Al Zour Mina Saud
  • October 2017 to April 2021

Preparing Itemizations for all Mechanical discipline and make a (PROM). Coordinates with Cost Engineers, Discipline Superintendents and Subcontractors Representatives in relation to Construction Management and Control. Verify the sequences of the Project Construction Items List, Construction schedule including scope of work change, Bill of Quantity (BOQ). Assists the Contract administration Coordinator and the Contracts Administrator in preparing Change Orders with respect to subcontractors.

Quantity Surveyor at SHAH Gas development Company
  • United Arab Emirates
  • May 2011 to February 2011

of Duties :
: Assist the management system and Quantity Manager for the
creation of the necessary reports.
: Re-measurement of Quantities; checking & verifying Subcontractor’s
Re-measurement submissions ( quantities, compliance with measurement
conventions, contractual entitlement ).
: Changes in the work and variations, examining all quantum justifications
given by subcontractor for any change or variation Request
Change proposal and the like.
: evaluating prices and unit rates proposed by subcontractor and advising
Subcontract administrator accordingly.

at GLOBAL PETROPROJECTS SERVICES AG
  • Cyprus
  • September 2009 to June 2010
Quantity Surveyor at SNAMPROGETTI Ltd. S.A
  • Saudi Arabia
  • February 2008 to April 2009

Updated & monitoring daily Production Report of Piping, Painting
and Insulation.
: Monitoring of variation orders, site instruction, extra works
Which is not included in the project original scope of work.
: Required to get and checked quantities measurements in all items
Of works executed in different stages for calculations required
for payment purposes.
: Quantity take off and rate analysis according to site situation,
Terms and condition.

Quantity Surveyor at CHIYODA COMPANY Ras Gas Onshore
  • Qatar
  • April 2007 to November 2007

of Duties : Checking, re-measurements and Surveying activities of
Piping, Insulation, Painting etc.
: Checking and verifying Subcontractor’s re-measurement
Submissions.
( quantities, compliance with measurement conventions,
Contractual Entitlement ).
: Examining all quantum justifications given by Subcontractor for
any change or Variation request, Change Proposals and
evaluating prices and unit rate proposed by Subcontractor.
: Evaluating and estimating Site Instruction works that potentially
produce a Change in the Work & assist back-charge .
: Verifying monthly progress and other Subcontractor payments
requests.
: Maintain updates forecast of main quantities, based upon internal
Information received, and maintain files for all re-measurement.

Quantity Surveyor at TOYO ENGINEERING COMPANY ( TEC ) South Pars GAS Phases
  • United Arab Emirates
  • August 2004 to November 2006

of Duties : Cost and Surveying activities.
: Preparation and making daily Invoice from the sub-contractor
: Preparation of project control reports and evaluate the project
Performance of the unit rate.
: Monitor and maintain a daily log of manpower, equipment
utilization and resources as well as daily direct and indirect
activities.
: Preparation of daily work and look ahead schedules for operation
group.
: Attend daily Safety / Toolbox meeting before execution of works.

Quantity Surveyor at Qatar Fertilizer Company Project, State of Qatar
  • to January 2005

of Duties
: Periodical Reconciliation of Materials ( Piping & Mechanical ) freely issued
to contractors and to In-house team.
: Final Settlement of contractor’s quantities.
: Provide assistance in terms of working out the quantities and unit rate
analysis for the contract variation works.
: Coordinate with the Construction team, planning team and other
departments for overall performance as a Quantity Surveying.
: Perform the role and undertake responsibility assigned to the position in line
with the companies HSEMS policies.

Quantity Surveyor at MOHAMMAD AL-MOJIL GROUP ( MMG )
  • Saudi Arabia
  • December 1997 to July 2004

of Duties : Cost and Surveying activities
: Updated & Input daily Production Report of Piping & Structural
Support.
: Daily Update of the manpower & Equipment.
: Assigned Plant Quantity tracker for mechanical piping
Installation, painting & insulation.
: And Perform the following duty such as monitoring of daily piping
Spool in site installation.
: Preparation of Project control reports and billings to the Client.
: Evaluate the project’s performance in relation to the budget and schedule
: Ensure strict implementation of Safety Procedures and the
Company’s Rules and Regulation.

at BIN QUARAYA COMPANY
  • Saudi Arabia
  • June 1993 to September 1996

Quantity Tracker - Project Control Department (PCD)
Summary of Duties :
: Monitoring and preparation of daily reports for the manpower,
Piping installation & installation of insulation.
Weekly / Monthly basis.
: Evaluate billing of Subcontractors.
: Perform other duties as may be assigned or required of the Job.
: Attend Weekly Safety / Tool box meeting before execution of
works.

MECHANICAL QUANTITY SURVEYOR
  • to
Quantity Surveyor at MOHAMMAD AL-MOJIL GROUP (MMG)
  • Saudi Arabia
  • to

b.) ISO 9000
c.) Implementation of Project Control Procedure

Quantity Surveyor at 2004 : TOYO COMPANY
  • to

b.) Implementation of Project Control Manual

Project at MMG- Fabrication Shop Steel Factory ( Pipe & Structural Steel )
  • United Arab Emirates
  • to
Desalination Plant at Kemya Olifins Petrochemical Al-Jubail
  • United Arab Emirates
  • to
at Power Plan
  • United Arab Emirates
  • to

Education

High school or equivalent, DESIGN
  • at IliganILIGAN CITY
  • January 1993

Bachelor's degree, Mechanical
  • at St Peter's University
  • March 1992
Bachelor's degree,
  • at Saint Peters College
  • January 1992

:

Specialties & Skills

Account Finalization
Measurement System Analysis
Contract Administration
Process Monitoring
Quantity Surveying
BILLING
CUSTOMER RELATIONS
MECHANICAL
MICROSOFT WORKS
PAINTING
PROGRESS
BILLING SYSTEMS
BUDGETING
ACCOUNTANCY

Languages

English
Intermediate

Training and Certifications

Safety Training (Training)
Training Institute:
Saipem Company
Date Attended:
July 2012
Duration:
6 hours

Hobbies

  • Playing Tennis , Guitar, Fishing
    Company Certificates whole middle east any projects. last Oct .2017 To April 2021 KNPC Al-Zour Refinery Project –EPC Package-4, Kuwait as a Quantity Surveyor and Company Certificates last Sept.’2016 To March’2017 -and SHAH Gas development Company, Pipeline Project Abu Dhabi last May .2011 to Feb’2014-as a Mechanical Quantity Surveyor.