Construction Manager-Civil
Saudi Landscape Company
Total des années d'expérience :18 years, 1 Mois
Define and establish detailed project execution phases and sequencing of activities in coordination with the Project Manager
Job Roles:
Reviewing and approving document submittal of contractor.
Technical adviser of documents and activity on the construction site.
Guiding the contractor into the right track and as per requirement.
Checking execution of work on the ground, plans, drawings and quantities for accuracy of calculations.
Following the scope of work as per contract agreement stated.
Scope of Work:
Infrastructure Works (Monitoring and Planning site work as per miles stone plan to support and giving priority on the right track for contractors. Reporting to the manager as per site progress. Solving issues that can delay the progress of work.
Warehouse Steel Structure project, U/G Concrete Tanks, Civil work(Concrete Foundation, Beams, Slab on grade, Mezzanine, Roofing), Structural Steel (Erection of columns, beams, rafter) Finishing work (CMU, Plastering, Gypsum Board, Painting).
Reviewing and approving document submittal of contractor like MAR, MIR, PQP, PSP and PEP.
Technical adviser of documents and activity on the construction site.
Guiding the contractor into the right track and as per required standard.
Checking execution of work on the ground, plans, drawings and quantities for accuracy of calculations.
Ensuring all materials to be used and work performed are as per specifications and standard.
Following the scope of work as per contract agreement stated in BOQ.
Job R.oles:
Managing the planning and design stages of construction projects.
Contributing technical expertise to the project drawing and designs.
Performing cost calculations and preparing financial projections.
Preparing work schedules in collaboration with the project manager.
To control a projects time, delivery, cost and quality.
Responsible for the practical management and planning of every stage of the construction project.
Scope of Work:
Hospital Building and Commercial Building project, organizing the responsibilities of those worker, preparing budget, safety, scheduling and reporting to Project Manager.
Job Roles:
As the main contractor technical adviser on the construction site for subcontractors, skill people and operatives.
Checking execution of work on the ground, plans, drawings and quantities for accuracy of calculations.
Ensuring all materials to be used and work performed are as per specifications and standard.
Overseeing the safety of worker and requisition of materials.
Preparing reports as required.
Managing, implementing, monitoring and interpreting the contract design documents supplied.
Coordinating with subcontractors, supervisors, planners, quantity surveyors and the general
workforce involved in the project
Resolving any unexpected problem on site and technical difficulties that may arise.
Guiding the sub-contractor into the right track and as per required standard.
Scope of Work:
Civil work Infrastructure and structures foundation (Tanks, Dike Wall, Evaporation Pond
Duct Bank, Pipe Sleeper, Equipment, Trust Block, Structural, Manhole Pits, Lift Station, Trenches, Roads and Pavement),
Underground utilities line (Fire fighting line, Sewer line, Treated Water line, Potable line) and Electrical Line (Power cable, Grounding line, Communication line and CATV)
.
Job Roles:
Implementation, Co-ordination, Supervision of technical aspects of construction projects.
Checking plans, drawings and quantities for accuracy of calculations.
Ensuring all materials to be used and work performed are as per specifications and standard.
Scope of Work:
Supervision and implementing of internal floor, wall and ceiling finishes as per required architecture design.
Job Roles:
Planning, co-ordination and supervision of technical aspects of construction projects.
Overseeing the selection and requisition of pre-cast materials for erection.
Day-to-day management of the site, including monitoring the site labour force for installation of panels.
Planning the work and efficiently organizing the plant and site facilities.
Overseeing quality control and health safety matters on site.
Preparing reports as required.
Resolving any unexpected technical difficulties and other problem that may arise.
Extra work included preparing document for Inspection and invoice claim.
Scope of Work:
Pre-cast work for Villas, Apartment Buildings and Riyadh Metro Line 3 Park and Ride Station. Erection and Connecting of all members of building like columns, beams, shear wall, stairs, hollow core slab, parapet wall and Internal / external walls.
The company is contracting and implementing related civil, mechanical and Electrical work worth of multi-billion project. It has a manpower more less 20000 workforce. i am senior site engineer reporting to the construction manger. I supervised and implementing specification of work.
Main Responsibilities:
* Acting as the main technical adviser on the construction site for subcontractors, skill people and operatives.
* Checking plans, drawings and quantities for accuracy of calculations.
* Ensuring all materials to be used and work performed are as per specifications.
* Overseeing the selection and requisition of materials and plant.
* Managing, monitoring and interpreting the contract design documents supplied by the main contractors / client.
* Coordinating with any consultants, subcontractors, supervisors, planners, quantity surveyors and the general workforce involved in the project.
* Communicating with client and their representatives (engineers, architects, surveyors) including attending regular meeting to keep them informed of progress.
* Day-to-day management of the site, including supervising and monitoring the site labour force and the work of any subcontractors.
* Planning the work and efficiently organizing the plant and site facilities in order to meet agreed deadlines.
* Overseeing quality control and health safety matters on site.
* Preparing reports as required.
* Resolving any unexpected technical difficulties and other problem that may arise.
Main Achievements:
* Successfully I completed the project for almost 1 years and 7 months.
* I finished duct bank and half of the structural foundation.
This is my last project in CCC, I will end up my service this coming on November 08 due to family and personal reason. All the years that I spend my career for almost 11year and 8 months, i entirely fade up of what i expected. I hope to use my skills in the best possible way for achieving the company’s goals, to enhance my professional skills in a dynamic and stable workplace.
The company is contracting and implementing related civil and mechanical work worth of multi-billion project. It has a manpower more less 7000 workforce. I am site civil engineer working as a QS engineer reporting to the project manger. i manage a team of 6 Quantity Surveyor and 1 clerk.
Main Responsibilities:
* Material Take Off (Sub-structures, Super structures, Civil and Finishing).
* It was re-measure job including Field Execution Report for additional work.
* Analyze drawing and specification.
* Understand contractual terms and conditions.
* Providing clear detail of Quantity Take Off.
* Organize sub-contractors quotations, negotiate to insure quotes meet contract documents and issue proper documented purchase orders.
* Complete budgeting and scheduling for projects and track name. Monitor progress, requisition change orders and identify any potentials risks.
* Maintain relationships with sub-contractors and clients.
* Insure site personnel are provided with proper documentation related to project.
* Work and deal with concerns of field personnel.
* Provide and maintain unit pricing and database for material and labour costing.
* Formulate cost break down from estimates and for project progress.
* Meet with potential clients to discuss options for proposed services.
* Assemble accurate and well organized estimates and proposals in a timely manner for specified price, design-build and construction/project management formatted projects.
Main Achievements:
* Successfully I saved the cost of the project and claimed additional amount through FER.
* I finished the Material Take Off using Cost X Estimation program and Auto Cad.
The company is contracting and implementing related civil, mechanical and Electrical work worth of million project. It has a manpower more less 3000 workforce. I became office engineer reporting to the control manger. i managed engineering department, assistant planning engineer, procurement and quantities surveyor.
Main Responsibilities:
* Preparing bills of quantities.
* Material Take Off (Sub-structures, Super structures, Civil and Finishing).
* Preparing report for weekly basis.
* Preparing 4 weeks look ahead report.
Main Achievements:
* Successfully I completed the project.
* I finished the Material Take Off using Cost X Estimation program and Auto Cad.
The company is contracting and implementing related civil, mechanical and Electrical work worth of multi-billion project. It has a manpower more less 15000 workforce. i am site engineer reporting to the construction manger. I supervised and constructed Warehouse (500 meter x 120 meters x 12.0 meters) with solar system 3000 units at the roof.
Main Responsibilities:
* Acting as the main technical adviser on the construction site for subcontractors, skill people and operatives.
* Checking plans, drawings and quantities for accuracy of calculations.
* Ensuring all materials to be used and work performed are as per specifications.
* Overseeing the selection and requisition of materials and plant.
* Managing, monitoring and interpreting the contract design documents supplied by the main contractors / client.
* Coordinating with any consultants, subcontractors, supervisors, planners, quantity surveyors and the general workforce involved in the project.
* Communicating with client and their representatives (engineers, architects, surveyors) including attending regular meeting to keep them informed of progress.
* Day-to-day management of the site, including supervising and monitoring the site labour force and the work of any subcontractors.
* Planning the work and efficiently organizing the plant and site facilities in order to meet agreed deadlines.
* Overseeing quality control and health safety matters on site.
* Preparing reports as required.
* Resolving any unexpected technical difficulties and other problem that may arise.
Main Achievements:
* Successfully I completed the project for almost 2 years and 3 months.
* Another pavement of experience through building a huge warehouse.
The company is contracting and implementing related civil, mechanical and electrical work worth of multi-billion project. It has a manpower more less 50000 workforce. I am site civil engineer reporting to the construction manager with a large scale of work including Structural foundation, Pipe rack, Pipe support, Equipment Foundation, Manholes, Sump pit, Pavement and Trenches.
Main Responsibilities:
* Acting as the main technical adviser on the construction site for subcontractors, skill people and operatives.
* Checking plans, drawings and quantities for accuracy of calculations.
* Ensuring all materials to be used and work performed are as per specifications.
* Overseeing the selection and requisition of materials and plant.
* Managing, monitoring and interpreting the contract design documents supplied by the main contractors / client.
* Coordinating with any consultants, subcontractors, supervisors, planners, quantity surveyors and the general workforce involved in the project.
* Communicating with client and their representatives (engineers, architects, surveyors) including attending regular meeting to keep them informed of progress.
* Day-to-day management of the site, including supervising and monitoring the site labor force and the work of any subcontractors.
* Planning the work and efficiently organizing the plant and site facilities in order to meet agreed deadlines.
* Overseeing quality control and health safety matters on site.
* Preparing reports as required.
* Resolving any unexpected technical difficulties and other problem that may arise.
Main Achievements:
* Successfully I completed the project for almost 3 years and 3 months.
* Another pavement of experience building a large gas plant project..