HVAC Engineer A/C Al Shirawi Dec 2007- March 2013


Projects Handled & Handling.
Handled:
✓ DEWA Substation (Al barsah south with BEC)
✓ DEWA Substation (Al Qusius with BEC)
✓ DEWA Substation (Amman street with BEC)
✓ DEWA Substation ( Muhaisanah with BEC)
✓ DEWA Substation (Jumeriah Park with AREVA)
✓ DEWA Substation (Jumeriah Village with AREVA)
✓ DEWA Substation (China with DANWAY)
✓ DEWA Substation (New Earth with DANWAY)
✓ DEWA Substation (INVR with L&T)
✓ DEWA Substation (JHRC with L&T)
✓ DEWA Substation (REMRAM with SIEMENS)
✓ DEWA Substation (Wahat Silicon with SIEMENS)
✓ DEWA Substation (Nad Al Shiba with BEC)
✓ G+1 villa @ Sharjah = 2 nos,
✓ G+10 @ Sharjah.
✓ G+48 Al Rund tower @ Sharjah.

Handling:
# G+6 @ Al Raffa.
# G+1 Villa @ Emirates hills.


Responsibilities as
✓ Carry out the work at site as per approved shop drawing and as per specifications to the quality required for approval by the Main Contractor/Consultant.
✓ Prepare on the 20th of every month material requirement and raise SMR's for the next one month.
✓ Follow-up with suppliers for receipt of materials at stores/site as per LPO's issued.
✓ Allocate labor for various activities in Consultation with the foreman as per requirements at site on a daily basis.
✓ Monitor progress of work as per program and inform in writing through site memo to the Main Contractor for any delay in civil works, which is affecting MEP progress.
✓ Inform Main Contractor of any variation work in any scope of original MEP contract through confirmation of verbal instructions. Any variation work should be done only after written approval as a variation instruction from the Main Contractor/Consultant and after consulting your Project coordinator.
✓ Check labor output along with Forman and monitor to Planning Manager in HO every week on Thursday without fail.
✓ Prepare monthly measurement of work at site through measurement annexure. Get it approval and send it to project planning manager in HO for monthly billing before 23rd of every month.
✓ Attending all internal site coordination meeting and external meetings with Main Contractors/Consultant/Client.
✓ Take project progress photographs at twice a month for all activities being carried out at site and send it to Project Planning Manager.
✓ Responsible for getting approvals from Main Contractor for overtime work beyond normal working hours and holiday work permit.

الخلفية التعليمية

بكالوريوس,
  • يناير 2008

EXAMINATION INSTITUTE YEAR BE Vinayaka missions university 2005/2008

بكالوريوس,
  • في K.S.Rengasamy Institute Of Technology
  • يناير 2003

DME K.S.Rengasamy Institute Of Technology. 2000/2003

الثانوية العامة أو ما يعادلها,
  • في Holy Cross Matriculation Hr Sec School
  • يناير 2000

SSLC Holy Cross Matriculation Hr Sec School. 1999/2000

Specialties & Skills

اللغات

الهندية
مبتدئ
الملايام
مبتدئ
الانجليزية
مبتدئ
الكانادا
مبتدئ
التاميلية
مبتدئ