MEP Procurement Manager
AE ARMA-ELEKTROPANC
Total years of experience :7 years, 10 Months
Mar 2010-Present AE ARMA ELEKTROPANC Dubai / UAE
MEP Procurement Manager at Dubai Head Office
Procurement and Logistics coordination and applications (specification controls,
QRFs, price comparisons, budget analysis, monthly reports, accounts and credit
coordinations (cheque and L/C coordinations)
Completed/Ongoing Projects:
Completed: - Bab Al Qasr Hotel & Serviced Apartments (Contract Amount: 225.7M AED)
Client: EMROC / Consultant: Surbana /Main Contractor: NUROL LLC
Completed: - Legoland Phase 2 (Contract Amount: 80M AED)
Client: DUBAI PARKS and RESORTS / Consultant: Kling Consult / Main Contractor: JVBO (JV Besix Orascom)
Completed: - Legoland Phase 3 (Contract Amount: 37M AED)
Client: DUBAI PARKS and RESORTS / Consultant: Kling Consult / Main Contractor: JVBO (JV Besix Orascom)
Completed: - Riverland (Contract Amount: 60.6M AED)
Client: DUBAI PARKS and RESORTS / Consultant: Dewan / Main Contractor: KIER DUBAI
Completed: - Al Fattan Rixos Hotel, Dubai (Contract Amount: 56M AED)
Client: RIXOS HOTELS / Consultant: CKR Consulting / Main Contractor: SML
Completed: - Al Shohub School, Abu Dhabi (Contract Amount: 24.7M AED)
Client: H.H.Dr.Shk.Sultan Bin Khalifa Al Nayhan / Consultant: MAKAN / Main Contractor: NUROL LLC
Completed: - Jumeriah Village (Contract Amount: 187M AED)
Client: NAKHEEL / Consultant: Dar Al Handasah /Main Contractor: NUROL LLC
Completed: - University of Dubai (Contract Amount: 30.7M AED)
Client: Dubai Champer of Commerce / Consultant: Dar Al Handasah / Main Contractor: KIER DUBAI
Completed: - Police Barracks Project, Abu Dhabi (Contract Amount: 17.5M AED)
Client: Abu Dhabi Police / Consultant: AEC / Main Contractor: Dhabi Contracting
Ongoing: - Al Maktoum Int.l Airport Pas. Ter. Building Exp. (Contract Amount: 195M AED)
Client: Dubai Aviation Engineering Projects (DAEP) / Consultant: Dar Al Handasah /
Main Contractor: ALEC
Ongoing: - Bluewaters Wharf Retail (Contract Amount: 274.3M AED)
Client: MERAAS Properties / Consultant: WSP / Main Contractor: ALEC
Ongoing: - Marsa Al Seef - Phase4 (Contract Amount: 121.1M AED)
Client: MERAAS Properties / Consultant: ATKINS / Main Contractor: Dutco Balfour Beatty (DBB)
Ongoing: - Al Maktoum Hospital Redevelopment (Contract Amount: 157.4M AED)
Client: AL WASL / Consultant: Kling Consult / Main Contractor: Shapoorji Paloonji (SPML)
Ongoing: - Abu Dhabi Marina City (Contract Amount: 127.6M AED)
Client: NIC / Consultant: ATKINS / Main Contractor: NUROL LLC
Apr 2008-Jan 2009 AE ARMA ELEKTROPANC A.S. Istanbul / Turkey
Electrical Site Manager at Sapphire Istanbul Project
Immediate Supervisor: Mr.Ali Karaves (Project Manager): 0090 532 716 82 77
Site Coordination, Installation Planning & Control, Contractor Coordination & Control, Interim Payment Calculations, Material & Equipment Selection & Approval,
Drawing Control & Application
4/20/2014 CV_EFSAN ALTINCABA_Electrical Engineer
Apr 2007-Apr 2008 AE ARMA ELEKTROPANC A.S. Istanbul / Turkey
Estimation Engineer at Istanbul Head Office
Immediate Supervisor: Ms.Tugba Yuksel (Tender Manager): 0090 532 770 44 35
Drawing and Specification control, RFQ, price comparisons, budget and sale
estimations.
Apr 2006-Apr 2007 AE ARMA ELEKTROPANC A.S. Istanbul / Turkey
Technical Office & Site Engineer at Novotel-Ibis Hotel Project
Immediate Supervisor: Mr.Murat Bakar (Project Manager): 0090 532 686 14 15
Work Schedule, Interim Payment Calculations, Material & Equipment Selection & Approval, Drawing Control & Application, Budget Control
Jun 2005-Apr 2006 SASEL ELEKTROMEKANIK A.S. Istanbul / Turkey
Technical Office & Site Engineer at Novotel & Ibis Hotel Project
Immediate Supervisor: Mr.Sami Atabey (Regional Manager): 0090 533 227 86 64
Work Schedule, Interim Payment Calculations, Material & Equipment Selection & Approval, Drawing Control & Application, Budget Control
1999-2004 Istanbul Technical University Istanbul / Turkey Bc.S. Electrical Engineering