Ehab Sobhy Mohamed, Director of Projects

Ehab Sobhy Mohamed

Director of Projects

TAMEER Real Estate

Lieu
Egypte - Le Caire
Éducation
Baccalauréat, Civil Engineer
Expérience
34 years, 7 Mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :34 years, 7 Mois

Director of Projects à TAMEER Real Estate
  • Egypte - Le Caire
  • Je travaille ici depuis juin 2022

With TAMEER Group Real Estate- Egypt
Project: UBL-AZAD VIEW (TAMEER) Investment with total value of 2.5 billion US$ - Cairo.

Manage all Portfolio projects scope starting from construction stage up to practical completion; and minimize exposure and risk across multiple projects. This includes but not limited to the following:
UBL: Area 55, 000 m2, Value 2.500, 000 le
Central Park & Infra: 233, 000 m2
AZAD VIEW: Area 72, 000 m2, Value 1, 500, 000 le
AZAD : (530) Apartments

Senior Projects Manager à Al-Futtaim Group Real Estate (AFGRE)
  • Egypte - Le Caire
  • novembre 2016 à mai 2022

Manage all Portfolio projects scope starting from construction stage up to practical completion; andminimize exposure and risk across multiple projects. This includes but not limited to the following:
 Assist on general constructability and overall feasibility of each project during the preconstruction stages and participate in performing the value engineering before and along the construction phase.
 Oversee all contracts up to and including practical completion ensuring that contractual obligations are met by all parties involved and establishing mechanisms for dealing with any contractual issues.
 Direct the Construction Consultants by monitoring and controlling their performance regarding budget, time and quality; and supervising the Contractor works, reviewing submittals, responding to queries, inspecting the progress and reviewing payment requests...etc to avoid the Contractors claims;
 Improve the work environment by enhancement the communications between the Engineer and the Contractor assuring smooth cooperation and coordination between them and supply further information to the Contractor as and when reasonably required;

Project Manager à Turner Construction International
  • Arabie Saoudite - Jeddah
  • septembre 2013 à octobre 2016

Security Force Medical City- Jeddah Consultant: Manens-Tifs- Italy
Position: Sr. Construction Manager

The project is one of the biggest healthcare projects on Jeddah. The budget of the Project about 11 Billions SR; The project includes: Building for medical facilities, College of applied medical sciences, academic affairs, Clinic Skills Center, College of Nursing, Medical Library, Accommodation for the staff including Villas and apartments

Sr.Construction Manager à Turner Construction International
  • Arabie Saoudite - Jeddah
  • mars 2012 à septembre 2013

•Project : The Link between Shoaybain & 3rd Floor of Jamarat- Mekkah.

Client : Ministry of Municipal and Rural Affairs
Central administration for Project Development.

Project Manager: Turner Construction International
Consultant Dar- al- handasah

Project Summary:

The project is one of the biggest projects on Makkah to serve the biligrim season . The budget of the Project about 1500 Million SR; The project includes : Five (5) Public road bridge with abutment piers & precast girder and slab cast in situe , Rock Cutting, Six (6) Tunnel through the mountain for more than 2 KM , Retaining walls devided into cast in situe and precast retaining wall to expedite the progress, , Service buildings, and more than new 662 tents for piligrims.

Construction Manager à Turner Construction International
  • Arabie Saoudite - Jeddah
  • mars 2008 à mars 2012

• Project : LAMAR Towers Project.
• Client : CAYAN Investment & Development.
• Project Manager: Turner Construction International
• Consultant : RMJM & SDC (Saudi Diyar Consultants )

Project Summary:

The site is located along the waterfront of Jeddah with a total 33200 square meters- 2 Towers 61 & 71 levels and 393000square meters built up area.
The Lamar Tower project is envisaged as a mixed use development that will include residential, commercial and retail facilities providing residents and visitors an unmatched living and recreational experience.
Responsibilities:

• Follow up mock-up modification, Approval & coordination with architect designer.
• Daily follow up of operation related materials and construction activities.
• Coordination with independent laboratories for offsite and onsite testing.
• Coordination with Client and Consultant at site.
• Conducting quality audits related to Civil &Finishing construction works.
Managing the process of generating and controlling quality records

QA/QC Manager à Dutco Balfour Beaty L.L.C and AL Ghandi & Consolidated Contractors International Company CCC
  • Émirats Arabes Unis - Dubaï
  • janvier 2005 à février 2008

Project : BURJ DUBAI DEVELOPMENT, THE DUBAI MALL PROJECT.
Consultant : Meinhardt & Turner International.
Client : Emaar Properties PJSC
Project Value: US $ 724, 748, 162.
Responsibilities:
1- Preparation of technical procedures, quality control and inspection test plans in line with project specification and applicable industry standards.
2- Organization operation of civil QC department and selection and supervising QC Engineers, Inspectors and technicians.
3- Daily follow up of operation related materials and construction activities.
4- Coordination with independent laboratories for offsite and onsite testing.
5- Coordination with Client and Consultant at site.
6- Attending construction meeting and QA/QC meeting.
7- Conducting quality audits related to civil construction works.
8- Managing the process of generating and controlling quality records for final handing over.

Resident Engineer.(Section Eng. Supervision Construction Task) à Lahmeyer International Consulting Engineers
  • Allemagne
  • juillet 2002 à janvier 2005

Electrowatt Engineering (Switzerland) and SOGREAH Consultants (France) in the New Naga Hammadi Barrage and Hydro-power plant
Position : Consultant Engineer.(Section Eng. Supervision Construction Task).
Project : New Nage Hammadi Barrage and Hydropower- Plant project.
Contractor : JV (Bilfinger Berger of German - VINCI of France -Orascom of
Egypt)
Consultant : LI Lahmeyer International-EWE Electrowatt-Sogreah in Association With ACE and electrical Power System Eng. Co.
Project Value: 333, 334, 811 EURO Equivalent.
Responsibilities: Supervision and approve the construction of main job -Civil Works
1- Survey, Excavate, Removal and level 3.5 million m3 to divert River Nile into diversion canal.
2- Pouring 338, 000 m3 of R.C Concrete multi - stages to built the plant connected with Hydro-mechanic, generating and electric works.
3- Finishing works, service buildings, workshops, Land reclamation ….. etc …. To complete the project in operation.

Arabian International Construction (aic) à Construction Manager
  • Egypte - Le Caire
  • mars 1998 à mai 2002

Company: Arabian International Construction (aic)
Project: Mubarak Pumping station - at Toshka “New valley south of Aswan”,
Upper Egypt
Position : Construction Manager.
Contractor: The Egyptian European Japanese consortium (Skanska of UK, AIC of Egypt &Hitachi of Japan)
Owner: Ministry of Water Resources and Public Works.
Consultant: Edipco - Sogreah Consortium (Egyptian/French)
Designer: Lahmeyer -Hamza (German/Egyptian)
Project Value: 1, 450 Millions L.E.
Project Description :
• The excavation works of Intake canal of a length of 3km inside Lake Nasser “Wet excavation”, 1.5 Km of the canal as dry excavation, the suction basin with about 11.5 million of excavated soil.
• The structures of the project include: 1-The Pumping station which contains 24 huge suction pumps, 10 services floors for the purpose of operating and maintenance of pumps, motors and control of operations, The Total concrete quantities of the project is 250, 000 M3
2-The discharge ducts and syphon outlet structures
3- Permanent workshop buildings & 11 K.V. Building & Two Bridges and Roads & landscaping works.
Responsibilities: Responsible for all construction works including(Earth works, concrete works, stressing & grouting of the Post- tension MacAlloy bar system, time controlling, Quantity survey in pumping station and siphon building)

Project Manager à The General Nile Company of Roads & Bridges.
  • Egypte
  • septembre 1996 à septembre 1998

Projects: 1- Navy Headquarters Building.
2- Maintenance of Desert Road of 50 Km length.
Position: Project Manager.
Consultant: Dr. Fathy Abd Rabou.
Owner: Navy Armed Forces & General Authority of Roads and Bridges.
Project Value: 50 million LE
Job Description : Coordinating of all site activities and quality control supervision in accordance with the British and American Specification. Contract administration, planning and reporting

Consultant Engineer à Riyadh Water Works Authority (Kingdom of Saudi Arabia).
  • Arabie Saoudite - Riyad
  • septembre 1993 à août 1996

Consultant : Riyadh Water Works Authority.
Owner : Ministry of Water Resources and Agriculture
Project Values : 50.0 million (Rial).
Job Description : Quality Contro l, supervision and inspection over Testing and leak detection in Riyadh Area Water Network.

Site Engineer. à The General Nile Company of Roads & Bridges
  • Egypte
  • mai 1992 à septembre 1993

Project :Renewal of Maritime passenger’s station.
Extension of Borg El-Arab Air Base (WestAir Port).
Position: :Site Engineer.
Contractor :The General Nile Company of Roads & Bridges.
Consultant :Engineering Authority of Armed Air Force.
Alexandria Port Authority.
Project Value :65 million LE

Site Engineer à Mansour Contracting Company
  • Egypte
  • septembre 1989 à mars 1992

Project: Sidi Krir Touristic Village
Position: Site Engineer
Contractor: Mansour Contracting Company
Consultant: Marine Armed Forces
Owner: Marine Armed Forces
Gross Area: 60 Feddans.
Project Value: 160 million LE
Job Description : Surveying works of cut & fill and supervision of civil works including concrete, finishing, networks of water supply & sewage

Éducation

Baccalauréat, Civil Engineer
  • à Faculty of Engineering
  • mai 1993

Certificate :B.Sc. of Civil Engineering, Faculty of Engineering, Alexandria University on June 1989. Grade : Very Good. Project's grade : Distinction.

Specialties & Skills

Site Supervision
Project Supervision
Certified Internal Auditor
Quality Assurance
Quality Assurance & Quality Control
Managment
Project Management Profesional
• Certified Internal auditor of ISO 9001:2000
OSHA – 30 Hours Course- Turner University on Jan 2010

Langues

Anglais
Expert

Adhésions

-UAE-Socity of Engineering
  • civil engineer
  • January 2007
Saudi Council Of Engineers
  • Civil Engineer
  • March 2012

Formation et Diplômes

Time Management (Certificat)
Date de la formation:
November 2007
Valide jusqu'à:
December 2007
PMP (Certificat)
Date de la formation:
November 2008
Valide jusqu'à:
December 2008
OSHA (Certificat)
Date de la formation:
January 2009
Valide jusqu'à:
February 2010
Certified Internal auditor (Certificat)
Date de la formation:
October 2007
Valide jusqu'à:
November 2007