→ Approved Project Manager on LTRA (ADDC (up to 33KV underground, OHL) Competent Engr./ GASCO Authorized Engineer)
→ Reporting to Sr. Project Manager.
→ Managing group of 80-100 workers/ Staff
Key responsibilities:
•General supervision and inspect the installation, modification and commissioning of Electrical HV & LV installation & low Current systems at construction sites
•Monitor, verify, and document the work being performed through subordinates.
•To ensure proper implementation of design at site.
•Provide technical assistance to the construction team as needed.
•To coordinate with other engineering discipline
le the complete Electrical design (Electrical, Low current, Fire Alarm, other Electrical services)
•Plan, review, and coordinate design and construction operations to ensure compliance with design drawings and specifications
•Liaise with local authorities such as ADDC (HV /LV), Transco, Etisalat, municipality, civil defense and ministerial agencies having jurisdiction over the project.
•Committed to DSI HSE requirements and all applicable legislations and contractual requirements affecting the HSE activities at project site and administrative office
•Installation/ Replacement of 11KV GSI/VCB Substation including QRMs/TRMs and Package Substations, Transformers (PMT & GMT), OHL, VMS, VMSF, Feeder Pillar (FP), Service Turret (ST).
•Installation of MV/LV cables, (up to 22KV) including jointing, termination & Megger test, VLF/DC, Hipot test.
•Diversion and recovery of MV/LV Cables including discarding of OHL, PMTs and substation, shifting them to ADDC stores
•Supervised and inspection of NDRC in many areas.
•Excavation and backfilling of cable trenches (multi depths) trial trenches to determine the underground services including reinstatement of asphalt, interlocking tiles, green, made - unmade areas
•Supervision of work progress at site and submitting weekly progress report to project managers including provision of logistic support
•Present Excavation of trial pits/preparation of drawings in order to reroute the underground services under the proposed route of Musaffah & MBZ city region.
•Operation and maintenance of 33 & 11 KV Network Duties include supervising & monitoring of radial & Loop network operation, checking/maintaining various types of isolators, MV/LV circuit breakers & multi size Transformers(PMT & GMT). Carried out periodic and preventative maintenance for complete system at regular basis.
•Installation/testing of ATS Panels, MV/LV panels, MDBs, Feeder Pillars, station DBs, Pkg sub stations, Gen sets, TRM/QRM, VMS, VMSF and transformers including parallel operation of transformers.
•Designing/laying/Jointing/ testing/termination of varies type of cables i.e 33 KV, 11KV and LV cables up to 300 mm.sq.
•Making the strategy and implementing the works schedules to achieve the goal within time frame.
•New connection for the 11kv substations including Meggering and Phasing with responsibility as approved Competent Person from ADDC
•Coordination and Communication with Client (ADDC) and consumers.
•Monitoring the work progress at site and submitting daily work plan & weekly progress report to project manager.
•Thoroughly checking/testing the quality of material, arrangement of cliental inspectors at site and coordination with suppliers and sub-contractors representatives
•Preparing shop drawings / B.O.Q and visiting the site for estimation purpose.
•Preparing Joint Measurements, as built drawings coordinate with ADDC for signed and approval up to final invoicing.
PROJECTS HANDLED:
LTRA for Installation of Underground Cables, Electrical Distribution Equipments and allied works. (ADDC)
o D-102052/B
o D-102054/B
o D-101707/B
o CMW-11000-FM076 (Installation of ATS Panel and Generators)
o CMW-08026-C001 (Installation of QRM, T/Fs and LV Panels)
o FSC-DSI-1213-CP052(Cable laying, cable testing and plugin type termination (KHAPRY-03))
- Company industry:
- Electric Power Production & Transmission
- Job role:
-
Engineering