Project Manager
Mass Projects for Power & Telecommunications
Total years of experience :16 years, 4 Months
• Manage and execute EPC High Voltage UG Cable Installation projects up to 220kV in the region (UAE & Kuwait) for various government and industrial utility projects.
• Provide Technical solutions and route case analysis for circuits under service for diversion or any other
modifications.
• Coordinate with accessory manufactures for Type Test in line with client standard and requirements
Management of Site Activities.
* Assist Project Manager for site activities.
* Coordination of site activities.
* Supervision and coordination of erection and installation of electrical
equipment’s.
* Supervision and coordination of site testing activities.
* Overall functional checks of substation equipment’s.
* Receiving materials at site and inspecting as per delivery schedule and
packing list.
* Monitoring and ensuring project Quality and HSE policies.
Projects:
* 132/11kV CEMENT GIS Substation.
* 132/11kV PONDVIEW GIS Substation.
* 132/11kV FRSTKWNJ GIS Substation.
* 132/11kV AMWAJ GIS Substation.
* 132/11kV MBRSTATE GIS Substation.
* 132/11kV UMSQEMRD GIS Substation.
* 132/11kV VLGE GIS Substation IDT replacement.
* 132/11kV OMTN GIS Substation 15MVaR Shunt
reactor extension works.
* 132/11kV MRINACMN GIS Bay addition works.
* 132kV UG Cable laying works for OMTN-KWJN.
* 132kV UG Cable laying works for UMSQEMRD-
MBRSTATE substations.
* Various Close-out substation works- MCLB, JAIN,
OMTN, FOUNTAIN, SRANCHES, LBAC
132/11kV substations.
Client: Dubai Electricity and Water Authority (DEWA)
* Project Management of Overall construction, erection, installations, testing
and commissioning of substations.
* Preliminary review and tracking of all engineering drawings.
* Coordinating for engineering workshops for reviews and approvals.
* Ensuring the project is completing within the schedule time frame and
budget as per baseline plan.
* Ensuring the quality of works delivered by contractor.
* Coordination of all site activities with various end users and external
authorities.
Al Mashariq is an EPC Power project contractor executing National Grid -SA T&D projects up to 380kV.
* 115/13.8kV Al Awamia GIS Substation (NG-EOA).
* 132/33/13.8kV Mokthara GIS Substation(NG-SOA).
* 380/132/33kV BSP GIS Substation(NG-SOA).
* 132/33/13.8kV Najran Airport GIS Substation(NG-SOA).
* 115/13.8kV Al Firdhouse GIS Substation (NG-WOA).
* 132kV OHL from Ahad-Samptah cicuit(NG-SOA).
Is an EPC contractor taking and executing projects for PDO, MEDC, OETC, and other various Oil and Gas projects under PDO contract.
33/11kV Raysut Industrial Area Substation and 33kV UG Cable works.
33/11kV Port of Salalah Substation and 33kV UG Cable works.
33/11kV Substation works private owner at Muscat and Cable works.
11/0.4kV buster pumping stations for PDO pipeline projects.
110/33kV extension works at Kalloor Substation and associated
modification works.
33/11kV Lulu Mall Substation works and related UG Cable works.
Operation and Maintenance of 33/11kV Airport Substation at Calicut
International Airport.
Erection Testing and Commissioning Runway Perimeter Roads and
associated UG cable works.
Erection Testing and Commissioning of new Baggage Handling Systems
(M/s. Pteris Global- Singapore and M/s. Vanderlande- Netherland).
: Specialized in High Voltage Engineering