Construction Manager
Carillion Qatar
Total years of experience :18 years, 10 Months
• Contributed comprehensive project management expertise in the areas of - Deploying manpower, equipment and material resources to optimize overall efficiency.
• Managed allocation of work to contractors and effectively liaising, supervising and monitored contractors and consultants to ensure all materials used and work performed are as per specifications.
• Strategically planned & controlled all project activities connected with safe and efficient operations; implementing quality standards for meeting the set targets within time & cost parameters.
• Handled and managed a team with distributed resources to ensure timely delivery of the project and resolve team conflicts, day to day issues as and when required. Mentoring the team by conducting various knowledge sharing sessions and trainings to achieve highest individual and team productivity.
• Identified & finalized the contractors ensuring quality supply of materials for effective project development.
• Managing Follow up of materials requirements at site with head office coordination with client/consultants and settle techno-commercial disputes/ clarifications during the execution of the project.
• Reviewed the operational practices, identifying the areas of obstruction / quality failures and advising on system and process changes for qualitative improvement in productivity.
• Supervised site activities including man and material management while providing technical inputs for methodologies Compliance of Health & Safety and maintenance.
• Contributed comprehensive project management expertise in the areas of - Deploying manpower, equipment and material resources to optimize overall efficiency.
• Managed allocation of work to contractors and effectively liaising, supervising and monitored contractors and consultants to ensure all materials used and work performed are as per specifications.
• Strategically planned & controlled all project activities connected with safe and efficient operations; implementing quality standards for meeting the set targets within time & cost parameters.
• Handled and managed a team with distributed resources to ensure timely delivery of the project and resolve team conflicts, day to day issues as and when required. Mentoring the team by conducting various knowledge sharing sessions and trainings to achieve highest individual and team productivity.
• Identified & finalized the contractors ensuring quality supply of materials for effective project development.
• Managing Follow up of materials requirements at site with head office coordination with client/consultants and settle techno-commercial disputes/ clarifications during the execution of the project.
• Reviewed the operational practices, identifying the areas of obstruction / quality failures and advising on system and process changes for qualitative improvement in productivity.
• Supervised site activities including man and material management while providing technical inputs for methodologies Compliance of Health & Safety and maintenance.
• Site monitoring and inspection of all civil/ structural works including reinforced concrete works of pile, diaphragm wall, raft.
• Witness Lab testing of Steel Reinforcing Bars. Conduct Plant Visit of Concrete batching plant and witness trail mixes and concrete sampling and testing.
• Review and approval of shop drawing.
• Prepare Daily Site Inspection/Observation Reports including recording of Safety violations and near misses.
• Prepare and Issue Non Conformance Report/Site Observation Report for work not compliant with drawings and specifications and follow-up for close out of NCRs and SORs.
• Report to senior Projects Manager for the projects status and progress.
• Site monitoring and inspection of all civil/ structural works including reinforced concrete work, installation of curtain wall framing glazing, & dry wall Installation, Hot Mix Asphalt Pavement etc.
• Review and approval of shop drawing.
• Review of method statement and Inspection Test Plan and confirm implementation at site.
• Participate in weekly technical meeting with client, consultants and contractor.
• Attend weekly QA/ QC meeting with contractor and Client.
• Review concrete test report, compaction test report, Asphalt test results for compliance with project specification and requirement.
• Review and Confirm correctness and completeness of 'AS BUILT' drawings
• Managed allocation of work to contractors and effectively liaising, supervising and monitored contractors and consultants to ensure all materials used and work performed are as per specifications.
• Strategically planned & controlled all project activities connected with safe and efficient operations; implementing quality standards for meeting the set targets within time & cost parameters.
• Handled and managed a team with distributed resources to ensure timely delivery of the project and resolve team conflicts, day to day issues as and when required. Mentoring the team by conducting various knowledge sharing sessions and trainings to achieve highest individual and team productivity.
• Identified & finalized the contractors ensuring quality supply of materials for effective project development.
• Reviewed the operational practices, identifying the areas of obstruction / quality failures and advising on system and process changes for qualitative improvement in productivity.
• Responsible for Management of Engineers & Foreman to achieve target, output & program.
• Performed the responsibility of control a team of Engineers to co-ordinate work and to liaison with consultant / contractor team.
• Monitor all sub contractor work closely to ensure the quality of the work is as per specification and is completed on time.
• Prepared weekly programs and allotted responsibilities to subordinates.
• Quality management and to liaison with consultant for drawings clarification.
• Report to project manager
Project: Construction of internal roads in Khlidia, Construction of overhead tank and pipeline works at Al-Qonfidah city (K.S.A) for Al Qonfidah Municipality, value 3 Million Saudi Riyal. 50m high overhead tank, two ground reservoirs of capacity 1million gallon & 20km water Pipeline, 3km sewer line
Residential building 7 buildings of (G+7), Value: 5.6 Million Indian Rupees.
First Class With 68%