Total Years of Experience: 33 Years, 10 Months
March 2016
To May 2022
QAQC ENGINEER / PROJECT ENGINEER
at DOMOPAN QATAR
Location :
Qatar - Doha
As QA/QC Engineer
• Coordinates all inspections, monitor the required tests for the attainment of quality requirements concerning daily inspection schedule as stated in the Inspection Request.
• Coordinates and reports to the QA/QC Manager and Consultant representative on the quality related matters and recommends remedies on quality issues.
• Report to the QA/QC Manager regarding work performance in any areas where discrepancies remain uncorrected.
• Provides technical support to the site staff for the proper methods in undertaking any activities that concerns QA/QC matter.
• Checks and receives the order of concrete in co-ordination with site engineer and QS.
• Conducts and Witness for material testing (and of any form of testing) related to QA/QC and maintains a record.
As Senior Civil Site Engineer
• Supervises and conduct site inspections.
• Prepares daily and monthly report for the consultant.
• Prepares Work Inspection Request (WIR) for civil works activities.
• Coordinates all inspections, monitor the required tests for the attainment of quality requirements concerning daily inspection schedule as stated in the Inspection Request.
• Coordinates and reports to the QA/QC Manager and Consultant representative on the quality related matters and recommends remedies on quality issues.
• Report to the QA/QC Manager regarding work performance in any areas where discrepancies remain uncorrected.
• Provides technical support to the site staff for the proper methods in undertaking any activities that concerns QA/QC matter.
• Checks and receives the order of concrete in co-ordination with site engineer and QS.
• Conducts and Witness for material testing (and of any form of testing) related to QA/QC and maintains a record.
As Senior Civil Site Engineer
• Supervises and conduct site inspections.
• Prepares daily and monthly report for the consultant.
• Prepares Work Inspection Request (WIR) for civil works activities.
October 2012
To February 2014
PROJECT INSPECTOR
at SOGREAH CONSULTANTS- ARTELIA GROUP (DOHA, QATAR)
Location :
Qatar - Doha
Island and Base Project -Lusail Island Oct. 2012- March 2014
: Conduct Work inspection request for harbor basin, secondary channel and reclamation area.: Witnessed and checked Field Density Test (FDT) conducted at site.: Witnessed and checked top level survey conducted by the contractor at site.: Checked and inspect all formation level for handing over.: Checked and witnessed laying out of geotextile before proceeding under layer rock and armor rock.
Project: Island and Base Project- Lusail Island (Marine Works) Qatar
(Building and Infrastructure works)
: Conduct Work inspection request for harbor basin, secondary channel and reclamation area.: Witnessed and checked Field Density Test (FDT) conducted at site.: Witnessed and checked top level survey conducted by the contractor at site.: Checked and inspect all formation level for handing over.: Checked and witnessed laying out of geotextile before proceeding under layer rock and armor rock.
Project: Island and Base Project- Lusail Island (Marine Works) Qatar
(Building and Infrastructure works)
January 2012
To September 2012
PROJECT SUPERVISOR / BRIDGE ENGINEER (Consultant)
at ACES VENTURES LIMITED
Location :
Papua New Guinea
ACES VENTURES LIMITED (PAPUA NEW GUINEA)
PROJECT MANAGER / BRIDGE ENGINEER (Consultant) Jan. 2012 - Sept. 2012
: Supervised Actual Construction of Reinforced Concrete Bridge
: Project Scheduling and Cash Flow Estimates
: Estimates and Prepared Bill of Quantities needed at the jobsite
: Attended construction meetings with the Project Inspector (DoW) at jobsite and Project Monitoring
Project: Brugam Bridge (55 lm.)
(Brugam, Province of East Sepik, Papua New Guinea)
PROJECT MANAGER / BRIDGE ENGINEER (Consultant) Jan. 2012 - Sept. 2012
: Supervised Actual Construction of Reinforced Concrete Bridge
: Project Scheduling and Cash Flow Estimates
: Estimates and Prepared Bill of Quantities needed at the jobsite
: Attended construction meetings with the Project Inspector (DoW) at jobsite and Project Monitoring
Project: Brugam Bridge (55 lm.)
(Brugam, Province of East Sepik, Papua New Guinea)
August 2011
To December 2011
PROJECT SUPERINTENDENT
at BF CORPORATION (PHILIPPINES)
Location :
Philippines
BF CORPORATION (PHILIPPINES)
PROJECT SUPERINTENDENT Aug. 2011 - Dec. 2011: Supervised Actual Construction of Process Plant (Gold Room, Grinding Area,
Crushing Area, Concentrate Thickener Area, and Tailing Thickener Area): Prepare Bill of Materials needed at the jobsite: Coordinate with the Owner at jobsite regarding plans and specification: Attend construction meeting at jobsite
Project: Oceanagold Mining Project
(Kasibu, Nueva Viscaya)
PROJECT SUPERINTENDENT Aug. 2011 - Dec. 2011: Supervised Actual Construction of Process Plant (Gold Room, Grinding Area,
Crushing Area, Concentrate Thickener Area, and Tailing Thickener Area): Prepare Bill of Materials needed at the jobsite: Coordinate with the Owner at jobsite regarding plans and specification: Attend construction meeting at jobsite
Project: Oceanagold Mining Project
(Kasibu, Nueva Viscaya)
January 2002
To January 2011
SUPERVISING ENGINEER / BRIDGE INSTALLATION ENGINEER
at P.N. AVENTAJADO CONSTRUCTION CORPORATION (PHILIPPINES)
Location :
Philippines
P.N. AVENTAJADO CONSTRUCTION CORPORATION (PHILIPPINES)
SUPERVISING ENGINEER / BRIDGE INSTALLATION ENGINEER 2002- 2011
: Supervised Actual Installation of Austrian Modular Steel Bridge: Supervised Actual Construction of Steel and Concrete abutments
: Pile driving of Steel and Concrete Piles, Concreting of
Deck slab, Approach slab and Approach roads.: Prepare Microsoft Projects and Construction Methodology
Finished Project
: Construction of Culasian Bridge (50 lm)
Rizal Palawan (Subcontractor for Installation of Modular
Steel Bridge)
: Construction of Jones II Bridge (350 lm)
Jones Isabela (Bridge Installation Consultant)
: Construction of Rancho Bridge (55 lm)
Cuenca, Batangas (Subcontractor for Installation of Modular
Steel Bridge)
: Construction of Calaba Bridge (900 lm)
Bangued, Abra (Bridge Installation Consultant)
: Construction of Lepote Bridge (50lm)
Mataas na Kahoy, Batangas (Subcontractor for Installation of
Modular Steel Bridge)
: Upgrading Works of Modular Steel Bridges
30 lm Linapawan Bridge, Roxas Palawan
50 lm Culasian Bridge, Rizal Palawan
40 lm Altavas Bridge, Altavas Aklan
40 lm Caninguan Bridge, Lambunao IloIlo
40 lm Bato Bridge, Palauig Zambales
60 lm Mangamnan Bridge, Marinduque
60 lm Banica Bridge, Roxas City
: Construction of Bolanos Bridge (40 lm)
Narvacan, Ilocos Sur
: Construction of Baliwag Bridge (70 lm)
Lupao, Nueva Ecija
: Construction of Butac Bridge (55 lm)
Suyo, Ilocos Sur
: Construction of Caruan Bridge (30 lm)
Pasuquin, Ilocos Norte
OTHER MAJOR PROJECT INVOLVED (PHILIPPINES)
Project Name: President's Bridge Acceleration Program (BCAP)
Project Owner: Department of Interior and Local Government
Location: Luzon, Visayas and Mindanao
SUPERVISING ENGINEER / BRIDGE INSTALLATION ENGINEER 2002- 2011
: Supervised Actual Installation of Austrian Modular Steel Bridge: Supervised Actual Construction of Steel and Concrete abutments
: Pile driving of Steel and Concrete Piles, Concreting of
Deck slab, Approach slab and Approach roads.: Prepare Microsoft Projects and Construction Methodology
Finished Project
: Construction of Culasian Bridge (50 lm)
Rizal Palawan (Subcontractor for Installation of Modular
Steel Bridge)
: Construction of Jones II Bridge (350 lm)
Jones Isabela (Bridge Installation Consultant)
: Construction of Rancho Bridge (55 lm)
Cuenca, Batangas (Subcontractor for Installation of Modular
Steel Bridge)
: Construction of Calaba Bridge (900 lm)
Bangued, Abra (Bridge Installation Consultant)
: Construction of Lepote Bridge (50lm)
Mataas na Kahoy, Batangas (Subcontractor for Installation of
Modular Steel Bridge)
: Upgrading Works of Modular Steel Bridges
30 lm Linapawan Bridge, Roxas Palawan
50 lm Culasian Bridge, Rizal Palawan
40 lm Altavas Bridge, Altavas Aklan
40 lm Caninguan Bridge, Lambunao IloIlo
40 lm Bato Bridge, Palauig Zambales
60 lm Mangamnan Bridge, Marinduque
60 lm Banica Bridge, Roxas City
: Construction of Bolanos Bridge (40 lm)
Narvacan, Ilocos Sur
: Construction of Baliwag Bridge (70 lm)
Lupao, Nueva Ecija
: Construction of Butac Bridge (55 lm)
Suyo, Ilocos Sur
: Construction of Caruan Bridge (30 lm)
Pasuquin, Ilocos Norte
OTHER MAJOR PROJECT INVOLVED (PHILIPPINES)
Project Name: President's Bridge Acceleration Program (BCAP)
Project Owner: Department of Interior and Local Government
Location: Luzon, Visayas and Mindanao
January 2002
To December 2004
PROJECT SUPERVISOR / BRIDGE INSTALLATION ENGINEER
at P.N. Aventajado Const. Corp.
Location :
Philippines
Inclusive Date: January 2002 - December 2004
Project Cost: P70, 000, 000.00
Project Description: Erection of 30 lm span - Waagner Biro Modular Steel Bridge
Includes Concreting of Deck slab, Construction of Abutments,
Approach slabs, and Roadways.
Project Cost: P70, 000, 000.00
Project Description: Erection of 30 lm span - Waagner Biro Modular Steel Bridge
Includes Concreting of Deck slab, Construction of Abutments,
Approach slabs, and Roadways.
January 1998
To January 2002
PROJECT SUPERVISOR / CONTRACTOR
at ALFB BUILDERS (PHILIPPINES)
Location :
Philippines
ALFB BUILDERS (PHILIPPINES)
SUBCONTRACTOR 1998- 2002
: Project Monitoring: Supervise Actual construction: Estimates and Prepare Bill of Materials needed at the jobsite: Preparing Quotation for the project: Preparing Contracts for the project
Finished Project: 2 Storey Residential Bldg
Mr. & Mrs. Nazario Ocenar
Silencio St. Q.C.
: Renovation of Residential Unit
Ipil St. South Greenpark Village, Tandang Sora, Quezon City
: Renovation of 3- Storey Residential Unit
Mr. & Mrs. Jessie G. Panit
Pittsburgh St., Cubao, Quezon City
: Renovation of 2- Storey Residential Unit
Mr. & Mrs. Richard Lao
Tahanan Village, Paranaque City
SUBCONTRACTOR 1998- 2002
: Project Monitoring: Supervise Actual construction: Estimates and Prepare Bill of Materials needed at the jobsite: Preparing Quotation for the project: Preparing Contracts for the project
Finished Project: 2 Storey Residential Bldg
Mr. & Mrs. Nazario Ocenar
Silencio St. Q.C.
: Renovation of Residential Unit
Ipil St. South Greenpark Village, Tandang Sora, Quezon City
: Renovation of 3- Storey Residential Unit
Mr. & Mrs. Jessie G. Panit
Pittsburgh St., Cubao, Quezon City
: Renovation of 2- Storey Residential Unit
Mr. & Mrs. Richard Lao
Tahanan Village, Paranaque City
January 1998
To December 1998
PROJECT ENGINEER/ ESTIMATOR
at CEREZ CONSTRUCTION (PHILIPPINES)
Location :
Philippines
CEREZ CONSTRUCTION (PHILIPPINES)
PROJECT ENGINEER/ ESTIMATOR 1998: Supervise Actual construction: Estimate all Bill materials needed at the jobsite: Coordinate with the Architects and Structural Engineers when there
are some changes at the Construction plans
Finished Project: Interior Finishing of 2 Storey Malaysian Bank
Pacific Center, San Miguel Ave. Ortigas Center, Pasig City
: 156 Units Residential Houses, Fontana Leisure Park
Clark Air base, Pampanga
PROJECT ENGINEER/ ESTIMATOR 1998: Supervise Actual construction: Estimate all Bill materials needed at the jobsite: Coordinate with the Architects and Structural Engineers when there
are some changes at the Construction plans
Finished Project: Interior Finishing of 2 Storey Malaysian Bank
Pacific Center, San Miguel Ave. Ortigas Center, Pasig City
: 156 Units Residential Houses, Fontana Leisure Park
Clark Air base, Pampanga
January 1994
To January 1998
PROJECT ENGINEER
at ASIA VERTIC CONSTRUCTION INC. (PHILIPPINES)
Location :
Philippines
ASIA VERTIC CONSTRUCTION INC. (PHILIPPINES)
PROJECT ENGINEER 1994 - 1998
: Supervise Actual construction at jobsite: Estimate all Bill materials needed for the construction: Coordinate with the Architects and Structural Engineers when there
are some changes at the Construction plans.: Conduct jobsite meeting with the owner, architects, and subcontractors.
Finished Project: 2-Storey Office Warehouse- JNV300 and JNV400
Jannov Holdings Corporation
Pasong Tamo Extension, Makati City
: 4-Storey Residential Building
Francisco Co Residential Building
A. Mabini St., San Juan, Metro Manila
: 2-Storey Residential Building
San Buenaventura Residential Building
Valle Verde VI, Pasig City
: 5-Storey Commercial/Residential/Warehouse Building
Ricklee Enterprises, Inc.
F. Blumentritt San Juan, Metro Manila
PROJECT ENGINEER 1994 - 1998
: Supervise Actual construction at jobsite: Estimate all Bill materials needed for the construction: Coordinate with the Architects and Structural Engineers when there
are some changes at the Construction plans.: Conduct jobsite meeting with the owner, architects, and subcontractors.
Finished Project: 2-Storey Office Warehouse- JNV300 and JNV400
Jannov Holdings Corporation
Pasong Tamo Extension, Makati City
: 4-Storey Residential Building
Francisco Co Residential Building
A. Mabini St., San Juan, Metro Manila
: 2-Storey Residential Building
San Buenaventura Residential Building
Valle Verde VI, Pasig City
: 5-Storey Commercial/Residential/Warehouse Building
Ricklee Enterprises, Inc.
F. Blumentritt San Juan, Metro Manila
January 1992
To December 1993
ENGINEERING STAFF
at COCA- COLA BOTTLER'S, INCORPORATED
Location :
Philippines
COCA- COLA BOTTLER'S, INCORPORATED (PHILIPPINES)
ENGINEERING STAFF 1992 - 1993
: Assist in Operation at Coca Cola Plant: Prepare Bill of Materials for the Project
ENGINEERING STAFF 1992 - 1993
: Assist in Operation at Coca Cola Plant: Prepare Bill of Materials for the Project
January 1991
To January 1992
PROJECT IN CHARGE
at PIONEER SPECIALTY BUILDING SYSTEMS, INC. (PHILIPPINES)
Location :
Philippines
PROJECT IN CHARGE 1991 - 1992: Supervised Waterproofing Works for Roof decks, toilets and Cistern tanks.: Supervised sealant works for Construction of Reinforced
concrete wall joints.
Finished Project: Carlo Restorante (Waterproofing of Roof and Parapet Wall)
Ortigas Avenue Extension
: Shakey's Pizza Restaurant (Waterproofing of Cooling Tower)
T.M. Kalaw, Manila
: Hotel Nikko (waterproofing of Existing Canopy Deck)
Makati City, Metro Manila
: Locsin Building (Waterproofing of Cooling Tower)
Makati City, Metro Manila
: SGV II Building (Application of Epoxy Tanklining)
Makati City, Metro Manila
: SGV Development Center Building (Waterproofing of Cooling
Tower and Application of Polyurethane Foam for roof deck)
Makati City, Metro Manila
: Makati Shangri-la Hotel (Application of Sealant Works for
R.C. walls and Application of Epoxy Tanklining for
concrete wall joints.
Finished Project: Carlo Restorante (Waterproofing of Roof and Parapet Wall)
Ortigas Avenue Extension
: Shakey's Pizza Restaurant (Waterproofing of Cooling Tower)
T.M. Kalaw, Manila
: Hotel Nikko (waterproofing of Existing Canopy Deck)
Makati City, Metro Manila
: Locsin Building (Waterproofing of Cooling Tower)
Makati City, Metro Manila
: SGV II Building (Application of Epoxy Tanklining)
Makati City, Metro Manila
: SGV Development Center Building (Waterproofing of Cooling
Tower and Application of Polyurethane Foam for roof deck)
Makati City, Metro Manila
: Makati Shangri-la Hotel (Application of Sealant Works for
R.C. walls and Application of Epoxy Tanklining for
January 1990
To January 1991
PROJECT ENGINEER
at NATIONAL POWER CORPORATION (PHILIPPINES)
Location :
Philippines
PROJECT ENGINEER 1990 - 1991
: Supervised Actual construction of Mini Diesel Plant: Prepare Bill of materials for the construction
Finished Project: Occidental Mindoro Diesel Plant
Mamburao, Occidental Mindoro
: Supervised Actual construction of Mini Diesel Plant: Prepare Bill of materials for the construction
Finished Project: Occidental Mindoro Diesel Plant
Mamburao, Occidental Mindoro
January 1988
To January 1991
ESTIMATOR / FIELD INSPECTOR
at DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (PHILIPPINES)
Location :
Philippines
ESTIMATOR / FIELD INSPECTOR 1988 - 1991
: Inspect all actual construction at jobsite.: Checked all materials installed for actual implementation.: Estimate Bill of Materials.
Finished Projects: 3-Storey Public School Building
Fourth Estate Elementary School
Paranaque, Metro Manila
: 2-Storey Public School Building
Padre Zamora Elementary School
Pasay City, Metro Manila
: 2-Storey Public School Building
Dongalo Elementary School
Paranaque, Metro Manila
: 2-Storey Public School Building
La Huerta Elementary School
Paranaque, Metro Manila
Engineering Assistant A
Company: National Irrigation Administration
Name of Children and
Dean Frederick M. Bongco February 5, 1992
Don Francis M. Bongco November 19, 1997
: Inspect all actual construction at jobsite.: Checked all materials installed for actual implementation.: Estimate Bill of Materials.
Finished Projects: 3-Storey Public School Building
Fourth Estate Elementary School
Paranaque, Metro Manila
: 2-Storey Public School Building
Padre Zamora Elementary School
Pasay City, Metro Manila
: 2-Storey Public School Building
Dongalo Elementary School
Paranaque, Metro Manila
: 2-Storey Public School Building
La Huerta Elementary School
Paranaque, Metro Manila
Engineering Assistant A
Company: National Irrigation Administration
Name of Children and
Dean Frederick M. Bongco February 5, 1992
Don Francis M. Bongco November 19, 1997
Share on Facebook