Work Experience

Total years of experience :20 years, 5 Months

SENIOR PLANNING ENGINEER/DELAY ANALYST at HILL INTERNATIONAL
  • United Arab Emirates - Abu Dhabi
  • My current job since February 2014

:
 Review Contractors proposed site organization; Planners CV’s and report to
the Engineering/Construction Manager.
 Review and approve / comment on the Design schedules as submitted by the
Contractor and ensure the Design Schedule is in compliance with the overall
project schedule.
 Review and approve / comment on the procurement schedules as submitted
by the Contractor and ensure the procurement schedules are in compliance
and coordinated with current construction schedules.
 Review and continuously monitor, against approved project management
baselines, the Contractor’s major construction progress and ensure
equipment and manpower are adequate or in case of any shortage report to
Engineering/Construction Manager.
 Review in detail the recovery schedules/action plans as submitted by the
Contractors and ensure manpower and site supervision staffs are allocated
properly.
 Regular visits to project sites to validate whether the progress of work on site
is in compliance with approved schedules, major milestones have been met
and report deficiencies to Construction Manager.
 Review all daily, weekly and monthly reports as submitted by Contractor and
report to Construction Manager any deficiency or non-compliance.
 Review EOT claim (delay analysis) as submitted by Contractor and report his
assessment to Construction Manager.
 Review field design changes and Trend Notices and assess time impact, if
any.
 Advise the Construction Manager of any foreseen slippage of progress and
corrective actions to be taken.
 Attend weekly progress meeting and monthly Executive meetings and
participate in preparing the agenda.
 Assist Engineer/Construction Managers during preparation of Monthly
Progress reports and Monthly Executive Presentations.
 Reviews the commissioning plans as submitted by Contractor and ensure its
compliance with the approved construction schedule.
 Participate with PMC staff in reviewing the Close Out Reports as submitted
by Contractors.
 Identify the potential risks (RISK REGISTER) & ensure the implementation of
RISK MANAGEMENT according to the PMI Standards & ADNOC standard
procedures.

Senior Planning Engineer at Emirates Transport
  • United Arab Emirates - Dubai
  • May 2013 to January 2014

DESIGNATION:
Planning Engineer مهندس تخطيط مشاريع

RESPONSIBILITIES:
• Overseeing the overall progress of all under construction & under design projects in complete coordination with Consultants and End-users.
• Preparation of department’s Yearly budget.
• Assist in manage department projects with compliance to PMI standards including the nine knowledge areas and throughout the five process groups.
• Monitoring the KPIs for the different stages of projects and Property management department’s functions.
• Identifying and reporting potential critical Risks to Department head ensuring proper control for the progress.
• Progress analysis and productivity reporting, including histograms, S-curves and progress reports
• Provide input to the department’s budget based cost estimate of new projects through verify and endorse payment certificates and monitor and analyze the projects budget utilization.
• Review & analysis of EOT & Cost claims contractual claims from Contractor.
• Liaison with the Consultant, contractors and suppliers ensuring proper progress at site.
• Providing Vital assistance to department‘s manager in project management domain.
• Assist in handling department’s communications with projects stakeholders including other departments or divisions.

SENIOR PLANNING ENGINEER at ALI MOOSA & SONS GROUP
  • United Arab Emirates - Sharjah
  • September 2009 to April 2013

1. Prepare Baseline schedule and weekly updating for proposed Construction of Bus service station at Al Khwaneej for RTA/PTP.
2. Weekly updating of construction program for Construction of Bus Depot at Jebel Ali for RTA/PTP.
3. Prepare Master program for proposed Construction of 14 filling stations for ADNOC distribution & regular monitoring through updates.
4. Prepare Clause-14 program for proposed Extension of Qassimiah Hospital Sharjah for Ministry of Public works & regular monitoring through updates
5. Prepare Master program for proposed Construction of KG+ Primary school @ Al Nouf sharjah for ministry of public works.
Preparation of Master schedule of the works identifying project activities in
coordination with engineering, procurement, construction and
commissioning departments.
 Monitor the progress of project on regular basis through updating the
schedule.
 Identifying and reporting potential critical activities to Project manager
ensuring proper control for the progress.
 Progress analysis and productivity reporting, including histograms, S-curves
and progress reports
 Possess good knowledge of FIDIC and prepare contractual claims accordingly.
 EOT claims preparation and delay analysis (using IAP & TIA techniques).
 Liaison with the Client’s representative, Consultant, subcontractors and
suppliers ensuring proper progress at site.
 Methodological approach to scheduling with excellent attention to details.
 Attending weekly and monthly coordination meetings.
 Excellent written and verbal communication and correspondence skills.

Construction Manager at ABC Building contracting
  • United Arab Emirates - Dubai
  • March 2007 to August 2009

PROJECTS
1. G+M+2 typical floor buildings (3buildings) warehouses (4numbers) and G+1 labor accommodation (UAQ)
2. Office & logistic facility (10 warehouses) on plot no.598-1110 for Grand stores in Dubai investment park Dubai.
3. G+1 labor accommodation and warehouse at Sajjah(planning only)
4. Construction of proposed biscuit factory at Sharjah industrial area.(planning only)
DESIGNATION:
Project Engineer+ Planning Engineer

RESPONSIBILITIES
• Supervising the execution of the project carrying out all activities in accordance with the contract requirement, quality plans, and appropriate inspection /testing plans, ensuring that all the resource such as manpower machinery equipment and materials are effectively utilized, monitoring & controlling all activities of personal including subcontractors at the project sites in line with project program and schedule.
• Being very familiar with Primavera (V 3 & 3.1), prepare Master schedule of the works identifying project activities in coordination with engineering,
procurement, construction and commissioning departments.
• Monitor the progress of project on regular basis through updating the schedule.
• Preparation of method statements in line with the contract specifications.
• Ensure time & cost control of the project.
• Coordination with MEP engineers for the complex services like (Cold stores,
BMS system, VESDA system, dock levelers & shelters, smoke ventilators
etc).
• Liaison with the Client’s representative, Consultant, subcontractors and
suppliers ensuring proper progress at site.
• Proficient in dealing with and responding to subcontractor variance reports and claims settlements.
• Preparation of all interim valuations (BOQ), method statements and shop drawing & material submittals for the approval of the consultant.
• Attending weekly and monthly coordination meetings.
• To Prepare Monthly Progress Reports in order to update the Client and Consultant regarding the progress of the project.

Project Engineer/Planning engineer at SOLANKI CONSTRUCTION CO. L.L.C
  • United Arab Emirates - Sharjah
  • February 2005 to February 2007

COMPANY PROFILE:
A Civil Construction & contracting company founded in 1975 and having projects in Dubai, Sharjah and Ajman, mainly high rise residential and commercial buildings with a number of consulting companies.

PROJECT:
G+3P+HC+14 typical floors+ HP building for Sheikha Moza bint Zayed bin Sultan al Nahian in Al Nahda Sharjah. (Dhs 25 million worth)

DESIGNATION:
Project Engineer + Planning Engineer

RESPONSIBILITIES:

• Plan, supervise and monitor all day to day site activities
• Allocating responsibilities to Supervisors, Foremen and charge hands.
• Quality control of workmanship and materials
• Prepare contractual claims as per FIDIC.
• .Execution of all the Structural & Civil works strictly in compliance with the drawings and specifications.
• Coordination with MEP engineers.
• Prepare and certify the subcontractor’s bills and payments.
• Preparation of all interim valuations (BOQ), method statements and shop drawing & material submittals for the approval of the consultant.
• Attending weekly and monthly coordination meetings.
• All incoming and outgoing correspondence with Client, Consultant and subcontractors.
• Provide necessary backups to the Project Manager.
• Prepare Progress Reports to update the Client and Consultant regarding the progress of the project.

Planning Experience
Prepare Master schedule of the works for the project G+3P+HC+17 Typical+HP on Primavera V3.1 and monitor the progress of project on regular basis through updating the schedule.

Prepare Master schedule of the works for the project G+3P+11 typical floors building on Primavera V3.1.

Prepare Master schedule of the works for the project G+10 Typical floors on Primavera V3.1 and monitor the progress of project on regular basis through updating the schedule.

Prepare the Base line schedule of works for the project G+4P+15 typical floors on Primavera V3.1.

Site Engineer at Adnan Asdar & Associates.(Pakistan)
  • Pakistan - Karachi
  • January 2004 to January 2005

COMPANY PROFILE:
Project and Construction Management Firm providing the overall planning, management and coordination of projects from inspection, through design and construction to completion and maintenance.

PROJECT:
Pearl Continental (PC) Hotel, (four star hotel) Gwadar, Pakistan.
DESIGNATION:
Site Engineer

RESPONSIBILITIES:

• Supervised the Excavation work up to the desired structural level.
• To check and confirm the fixing of steel and formwork for Footings, Retaining walls, slabs, UGWT, Beams, Lift Walls and Columns etc.
• To check and ensure the quality of concrete for pouring.
• To check and approve the quality of construction material like coarse and fine aggregates and water etc through laboratory tests.
• Being a Site Engineer from Management, coordinate with consultants and contractors.
• Preparation of Monthly Progress Reports in order to update the Management and Client regarding the progress of the project & scheduling of P3 based construction program.

Education

Bachelor's degree, Civil engineering
  • at NED university of Engg.& Tech
  • December 2003

• Primavera Project Planner V3 & V3.1 6.7 • AutoCAD 2002 & 2008 • Windows XP, MS Office XP,2003 • AutoCAD 2008

Specialties & Skills

Time impact analysis
Primavera
Schedule Analysis
EOT Claims
Autocad2008
Primavera 3 ,6
pmp aspirant
Time Impact analysis
Hospital Construction
DELAY ANALYSIS
PRIMAVERA 6

Languages

English
Expert
Urdu
Expert
Arabic
Beginner

Memberships

PAKISTAN ENGINEERING COUNCIL
  • MEMBER
  • January 2004
PMI-USA
  • Member
  • April 2010

Training and Certifications

Prepcast (Certificate)
Date Attended:
July 2011
Valid Until:
August 2011

Hobbies

  • Acrylic painting
    Use acrylic meduim to paint .... abstracts normally
  • Books
    Reading books is best i enjoy...