gamal eid, site Manager

gamal eid

site Manager

NESMA

Location
Saudi Arabia - Jeddah
Education
Bachelor's degree, English
Experience
14 years, 4 Months

Share My Profile

Block User


Work Experience

Total years of experience :14 years, 4 Months

site Manager at NESMA
  • Saudi Arabia - Jeddah
  • My current job since June 2018

Sitea manager of Jawad substation110kv/13.8kv
installation of
• Two (2) Main transformers (110KV/33KV)
• voltage switchgear .
• Installing Cable Ladder & Tray
• Installing Two 2 Battery 220 VDC
• Installing UPS system
• Pulling 30 Km cable including 64 Km medium voltage Cable
• Testing and commissioning for all cables and equipment
• Testing and commissioning for all cables, equipment and instruments
• Installation of GIS
• Installation of lighting
• Installation lightning

1. Preparing tender document of the project (Financial & Technical)
2. review for IFC drawing and its last revision
3. Prepare RFI's for any technical clarifications
4. Preparing RMI (request material inspection)
5. preparing any correspondence N.G
6. Coordinate with draftsmen for shop drawing preparation, Review shop drawing prior to submit to consultant
7. Make quantity take off for all material required.
8. Coordinate with main contractor/ consultant.
9. Manage and supervises all site electrical works.
10. Undertake the detailed short term planning and co-ordination at site in accordance with the baseline schedule.
11. Ensure that the works are carried out in a safe manner in accordance with the project safety plan and as the time schedule of the project in the contract.
12. Co-ordinate with other contractor and other sub-contractors at site.

Site Manager at Delta Limited
  • Saudi Arabia - Jeddah
  • February 2015 to June 2018

Sitea manager of adam substation110kv/33kv
installation of
• Two (2) Main transformers (110KV/33KV)
• voltage switchgear .
• Installing Cable Ladder & Tray
• Installing Two 2 Battery 220 VDC
• Installing UPS system
• Pulling 30 Km cable including 64 Km medium voltage Cable
• Testing and commissioning for all cables and equipment
• Testing and commissioning for all cables, equipment and instruments
• Installation of GIS
• Installation of lighting
• Installation lightning

1. Preparing tender document of the project (Financial & Technical)
2. review for IFC drawing and its last revision
3. Prepare RFI's for any technical clarifications
4. Preparing RMI (request material inspection)
5. preparing any correspondence N.G
6. Coordinate with draftsmen for shop drawing preparation, Review shop drawing prior to submit to consultant
7. Make quantity take off for all material required.
8. Coordinate with main contractor/ consultant.
9. Manage and supervises all site electrical works.
10. Undertake the detailed short term planning and co-ordination at site in accordance with the baseline schedule.
11. Ensure that the works are carried out in a safe manner in accordance with the project safety plan and as the time schedule of the project in the contract.
12. Co-ordinate with other contractor and other sub-contractors at site.

Project Engineer & Contract administrator at Electro Tharwat For tranding and contracting
  • Egypt - Cairo
  • January 2010 to February 2015

From Feb.2010 to Sep.2011 (ABU Qir power station 2*650 MW thermal units)
• Job description Material control, installing transformer, IPB, cable tray, conduit, cable laying and installing panel in ABU Qir power station 2*650 MW thermal units PGESCo Company was the consultant West Delta Electricity Production Company was the owner


From Oct.2011 to Feb. 2015 (Elsokhna power station 2*650 MW thermal units)
• Job description
1. Prepare a review for IFC drawing
2. Prepare RFI's for any technical clarifications
3. Monitoring and review MRR
4. preparing any correspondence to consultant(PGESCo)/owner(East delta electricity production company)
5. Coordinate with draftsmen for shop drawing preparation, Review shop drawing prior to submit to consultant
6. Make quantity take off for all material required.
7. Coordinate with main contractor/ consultant.
8. Participate where required in all aspects of the project management for the electrical works.
9. Manage and supervises the on all site electrical works.
10. Undertake the detailed short term planning and co-ordination at site in accordance with the master program.
11. Ensure that the works are carried out in a safe manner in accordance with the project safety plan and as the time schedule of the project in the contract.
12. Co-ordinate with the main contractor and other sub-contractors at site.
13. Maintains records of the changes to the working drawings to enable the record drawings to be produced.
14. Monitoring the monthly progress and prepare the invoice
15. Monitoring and review reports with planning team before submit it to consultant (Monthly report -4week look ahead-biweekly critical item report daily report )
16. Manage cable MV & LV with the requirement of the site and cable list
17. Monitoring the milestone in the contract and take any necessary action.
18. Contract administrator

Education

Bachelor's degree, English
  • at Faculty of engineer Helwan University Power & electrical machine departmnet
  • September 2008

• School El -Helal language experimental school- Maadi -Cairo. 2002-2003 skills: • Languages Very Good in spoken and written English, Fair knowledge about French and Fluent in Arabic (Mother Tongue) • Computer Skills Very good command of MS-Office, excellent Internet user, excellent Typing E&A. • Interpersonal Skills Very good communication, presentation, Good team player and able to work under stress and in challenging situations, Fast learning person, Diplomatic Character, High level of responsibility. Summer Trainings: • GUPCO Company for Petroleum One month's summer training. • GUPCO site in Shokeir 21Days summer training.

Specialties & Skills

Project Management
Electrical
Transformer
ENGINEER
MATERIAL CONTROL
PROJECT ENGINEER
Technical Office Engineer
Autocade

Languages

Arabic
Expert
English
Expert
French
Beginner

Memberships

PMI
  • Management
  • January 2018

Training and Certifications

PMP (Certificate)

Hobbies

  • soccer
    play twice per week