Construction Manager à Consolidated Contractors Company
  • Koweït - Al Ahmadi
  • Je travaille ici depuis janvier 2009

1.Review contract/tendering documentation, to ensure a thorough understanding of the contract requirements.
2. Direct & co-ordinate site resources to ensure construction meet all requirements, both cost effectively & efficiently.
3. Establish along with relevant managers, the resourcing requirements for relevant parts of the project to ensure that
these are accurate and realistic and that any necessary steps needed to supply resource have been arranged with
reference to the critical path.
4. Co-ordinate/support in conjunction with relevant staff, the development and establishment of the Construction
Schedule together with the mechanisms for monitoring subsequent progress against that schedule.
5. Review and assess the integrity, frequency and value of all reporting, and establish revised systems where necessary to
ensure that Project Management has the necessary up to date information to effectively manage the project to meet its
objectives.
Projects executed:
A- Future Growth Project (Project value 600 Million USD)
Client : Tengiz Chevron Oil
Main Contractor : Consolidated Contractors Int’l Co.
B- Clean Fuels Project (Project value 540 Million USD)
Client : Kuwait National Petroleum Company
Main Contractor : Samsung/Petrofac
C- New Doha Port Project

Project Engineer à Consolidated Contractors Company
  • Qatar - Doha
  • août 2006 à décembre 2008

Ensure adequate resources (manpower and equipment) are provided according to project’s schedule.
Monitor and review the progress to ensure that E & I works are progressing in a timely manner and according to
project’s schedule at the following Oil & Gas projects:
A- Al Khaleej Gas Expansion Project Phase 2 (AKG-2) );Ras Laffan-Qatar
Client : Ras Gas
Main Contractor : Chiyoda/Technip Joint Venture
B- Ras Gas Onshore Expansion Project Phase 2 (RGX 2);Ras Laffan-Qatar
Client : Ras Gas
Main Contractor : Chiyoda/Technip Joint Venture

Section Engineer
  • février 2003 à juillet 2006

Assignment
Assign targets to Electrical & Instrumentation Site Engineers in order to execute the related E & I works in a timely
manner and according to project’s schedule at the following Oil & Gas projects:
A- Ras Laffan Onshore Expansion Project;Ras Laffan-Qatar
Client : Ras Gas
Main Contractor : Chiyoda/Snamprogetti Joint Venture
B- Common Cooling Water Project; Ras Laffan-Qatar
Client : Qatar Petroleum

Site Engineer à CCIC
  • Émirats Arabes Unis
  • janvier 1999 à janvier 2003
Electrical and Instrumentation Engineer à AL HUSAM GENERAL CONTRACTING ESTABLISHMENT - UNITED ARAB EMIRATES
  • septembre 1991 à août 1998

Assignment
Electrical & Instrumentation Engineer in charge of Electrical and Instrumentation works at various Power plants,
Substations, Desalination plants, etc.

Éducation

Baccalauréat, ELECTRICAL
  • à ENGINEERING ▪ E.S.I.B – Saint Joseph University Assessed by the University of Toronto
  • décembre 2019

..

Specialties & Skills

Installation
CUSTOMER RELATIONS
DOCUMENTATION
MICROSOFT WORKS
OIL PAINTING
PROGRESS
PROJECT MANAGEMENT
REPORTS
ENGINEERING

Langues

Anglais
Expert
Français
Expert