Al-Dhafra 400/132Kv switch gear station-Abu Dhabi Civil Engineer - (Aug 2018 to Dec 2019)
Client: Transco & Consultant's: WSP Project Value AED 180 Million Project Description: Construction of 400 KV Switchgear GIS, Control room buildings, Transformer yards Installation and Associated Works JAAC-TREATPLT 132/11kV UG Cable Works- Dubai
Assistant Construction Manager (Jan 2020 to Dec 2022)
Client: DEWA Project Value AED 70 Million
Project Description: Supply Installation Testing & Commissioning of
16.50 KM (21 Section) of 132 KV Cable Circuit from JAAC (Jabel Ali Airport) Substation to TREATPLT (Treatment plant) near DWC Airport area with 20 Major roads Crossing & Duct Bank
• Managed accounting duties such as revenue reporting and forecasting, enabling smooth financial operations.
• Supported long-term business need strategies, generating customer relations feedback for process improvements.
• Developed product pricing and promotions to reach revenue goals.
• Analyzed and resolved complex resource management issues for optimized scheduling.
• Visited site to review work progress and drive process improvement
• Reviewed construction plans and financial projections, verifying project scope accuracy and feasibility.
• Established clear budgets and cost controls strategies to meet objectives.
• Prepared accurate project cost estimates, schedules and specifications.
• Motivated site teams to achieve quality results against construction deadlines.
• Doha West Sewage Treatment Plant -June 2016 Till date
Client: ASHGAL • Main Contractor: Marubeni & SUEZ • Project Value: QAR 237 Million
Project Description: Construction of sewage treatment plant extension -05. This expansion will increase the plant’s treatment capacity from 104MLD to 280MLD. It involves construction of water retaining tanks, process buildings, pump rooms, 5no’s-11KVA substations, external landscaping & road works.
• Qatar Power Transmission System Expansion, Phase XII Substation packages-Nov 2015- May 2016
Client: KAHRAMAA • Main Contractor: National Consulting Company • Project Value: QAR 18 Million
Project Description: Construction of substation works for power supply to Metro.
RESIDENTAL APARTMENT BUILDING (Structure & Finishing works) ALAKKA PALAZZO (G+12, 94 FLATS
RESIDENTIAL VILLAS (Structure & Finishing works) (G+2)
COMMERCIAL BUILDING - TOWER (G+12).
RESIDENTIAL BUILDING JAMALS ORCHID PARK (G+4 - 32 FLATS)
State Board of Technical Education & Training. Deportment of Technical Education. Successfully Completed Bio-Gas Project in Practical Session