Project Construction manager at Metka-Egn
  • Tunisia - Sfax
  • My current job since April 2019

Employer: METKA-EGN.
Client: Eni -B.V Tunisia
Project: ADAM 5.5 MWp PV Solar Plant (BESS)

Successful Completion of 5 MW PV Solar Plant (Battery Energy Storage System), Alumil Structure product Line and PV Module Jinko Solar Product Line, Inverter Transformers BEST Turkish Product Line.

Electrical Construction manager at Larsen & Toubro
  • Egypt - Suez
  • August 2018 to April 2019

Position: Construction Manager. Egypt (From August.2018 Till April.2019)
Employer: Larsen & Toubro Construction Transmission and Distribution.
Client: Egyptian Electricity Transmission Company "EETC"
Project: EPC-Turn Key project (500/220 KV GIS Substations).
GIS Product Line: Hyundai Heavy Industries, Ltd, Korea.
• Erection of 2 Extension Bays 500 KV Double Bus Bar Double Breakers.
• Erection of 7 Bays 220 KV GIS (2 OHTL, 1 Coupler, 2 TR Bays, 2 UGC Bays) and installation of 7 three single phase Transformers.

Project construction manager at El Sewdy Electric
  • Egypt - Aswan
  • January 2018 to August 2018

Position: Project Construction Manager. Egypt (Jan.2018 till August.2018)
Employer: El Sewedy Electric
Owner Engineer "O.E": Tuv Nord
Client/Developer/EPC: EETC/El Sewedy-EDF /Sterling & Wilson.
Project: Aswan-Benban (FIT) Program 100 MW PV Solar Plant.
Major Responsibilities:
 EPC of 2*50 MW PV Plant turnkey and O&M project, Inverter Station (ABB), Single axial tracker (Next tracker), 325 MWP Double glass PV module (Trina Solar).
• Ensure the Projects are executed in full compliance with the PPA or as agreed with the off taker, the O&M Agreement, the EPC agreement, including review/preparation of Covenant List and Risk Matrix in coordination with the Contracts Manager where required, Oversee the required Permits are obtained on due time, Responsible for managing in daily basis all on-site activities for the construction supervision (Electromechanical, civil, HSE, QA/QC, … etc.).
• Supervise Ramming, Pull out tests, Torque Tubes, panel rails and module installation including all civil activities and fencing (MV Cable trenches, DC trenches, ITS Foundations, Water pipe line, MV Substation Building, O & M Building and UG Tanks.
• Identifies, evaluates resolves or escalates, and records all construction issues/problems and review the status of materials delivery, tracking, distribution.
• Oversee and monitor all resources (materials, manpower, IFC DWG's)required for project completion and coordinate with the O.E for updating master DWG's list and material tracking sheet and manpower histogram.
• Coordinates with the Owner’s Engineer, the EPC Contractor and the Quality Manager in order to facilitate the implementation of the Quality Plan (Oversee and Monitor) as well as tracking of Facility Management Company.
• Participates with the Project Manager in construction meetings with Project stakeholders’ and FMC (Facility Management Contractor).

site project manager at El Sewedy Electric
  • Egypt - Cairo
  • March 2017 to January 2018

Position: Project Manager. Egypt (March.2017 till Jan.2018)
Employer: El Sewedy Electric for Transmission & Distribution (EETD Gulf Sector).
Client: EETC Egyptian Electrical Transmission Company).
Project: EPC-Turn Key Four project (66/22 KV AIS Indoor Substations B&D PJT’s).
AIS and MV Switchgear Product Line (ABB): ABB 40 MVA Power Transformers
Major Responsibilities:
• Leads the project team, establishes the project execution approach.
• Manages project budget to ensure that the project financials are accurate as it pertains to revenue, cost and income forecasts.
• Checking drawings, BOQ ensuring that calculations are accurate and within budget.
• Facilitates testing & commissioning team for smooth running of the Project.
• To implement policies, establish procedure and expedite work flow.
• Maintain standards of safety and comply with Company’s HSE Policy.
• Quality planning, monitoring and follow-up during engineering, procurement.
• Coordination with engineering department to implement the technical lesson learnt points during engineering and design stage to avoid the same in forth coming.
• Ensure that all materials used and work performed are in accordance with the
Specifications & the selection and requisition of materials.
• Agree a price for materials and make cost-effective solutions and proposals.
• Manage, monitor and interpret contract design documents supplied by Client.
• Monitor the progress of the project and make adjustments as necessary to ensure the successful completion of the project.

Project Execution Manager at El Sewedy Electric T&D
  • Kuwait - Al Kuwait
  • March 2016 to March 2017

- Responsible for management of site execution as per design within the cost, time and quality for turnkey substations : EPC-Turn Key project (132/11 KV GIS 2 Nos. Substation).
-Verify that the procedures for construction work progress measurements are correctly implemented and the subcontractors are performing the work and mobilizing the resources according to the needs of construction schedule, also providing the weekly and monthly construction reports accomplished by look ahead.
- Agree a price for materials and make cost-effective solutions and proposals for the intended project
Manage,
- monitor and interpret the contract design documents supplied by the client or architect
- Liaise with any consultants, subcontractors,
- supervisors, planners, quantity surveyors and the general workforce involved in the project.
- Liaise with the local authority (where appropriate to the project) to ensure compliance with local construction regulations and by-laws.
- Communicate with clients and their representatives (architects, engineers and surveyors), including attending regular meetings to keep them informed of progress.
- Day-to-day management of the site, including supervising and monitoring the site labor force and the work of any subcontractors.
- Plan the work and efficiently organize the plant and site facilities in order to meet agreed deadlines
Oversee quality control and health and safety matters on site.
- Resolve any unexpected technical difficulties and other problems that may arise.
- Review the quality of the work completed with the project team on a regular basis to ensure that it meets the project standards.
- Monitor the progress of the project and make adjustments as necessary to ensure the successful completion of the project.
- Evaluate and report on milestone achievement and any deviation thereof.
-Erection and commissioning till startup of 220 KV GIS S/S (One and half C.B) 4 Bays.
- Supervision of all MEP Works inside the Substation.

- In-charge of Outdoor equipment’s installation and Testing (C.S.E&CCVT& LT&S.A and Gantry Towers accomplished with slack span conductor 400 mm sq. AAAC).
- Installation of DC System (Battery + Chargers).
- Installation and Testing of Communication system + Tel-protection.
- Installation of Substation Automation System (SAS) &OWS/EWS and DFR.
- Follow Up all Civil progress and construction Power.
- Small power/lighting/fire alarm/firefighting/Smoke detector and infrastructure is part of my responsibilities.
- Installation of Earthing (Main grid/pigtails”Primary”+secondary Earthing).
- Installation of Lightning protection system.
- Handling all contractual issues (P.O &V.O and change notes).
- Tracking all materials under custom clearance/Duties.
-Coordination with NECC and dispatch center is handling through me.

- Installation of 111/148/185 MVA step up 220 KV Transformers and related 6.6 KV Auxiliary TR.
- Preparing Method of statement for installation beside risk assessment job.

-Checking drawings and quantities and ensuring that the calculations are accurate for the work.

- Facilitate testing and commissioning team for smooth running of project to avoid any delay.

- To direct and monitor all personnel activities within engineering area including manpower forecasting, staff assignments and performance reviews.

-To take leadership of and provide direction to design team and manage and ensure resolution of problems (Red marks/shop DWG’S and As-Built drawings).

- To implement policies, established procedures and expedite workflow.

- Maintain standards of safety and comply with Company’s Health, Safety and Environment Management System requirements, Comply with (BESA & SESA and WESA).

-Quality planning, monitoring and follow-up during engineering, procurement.
Coordination with engineering department to implement the technical lesson learnt points during engineering and design stage to avoid the same in forth coming.

Site Manager at Alstom Grid
  • Egypt - Damietta
  • February 2015 to March 2016

Installation of 220 KV GIS Substation and it's auxiliaries.
Modifications work in all Remote End Substations till synchronization with main grid.

Senior Electrical Engineer at Alghanim International Company.
  • Kuwait - Al Jahra
  • November 2014 to January 2015

Electrical Construction I&C Electrical Engineer responsible for construction of Electrical Equipments of 2*250 MW OCGT Siemens product line.

Sales Manger and Engineering Support at Hyundai Heavy Industries, Ltd, Co, Korea
  • Kuwait - Al Kuwait
  • April 2014 to October 2014

• Tracking Kuwait Market for MEW Substation & Rotating machines Tenders.
• Apply for HHI product lines PQ (Pre-Qualifications) with KNPC and KOC.
• Follow up for all new Purchase orders (P.O) and Letter of Award (LOA).
• Dealing with Kuwait Ministry of Electricity and Water for issuing FAC.
• Handling all materials and new bidders with HHI Head Quarter.
• Handling all official documentation and clearances with MEW and EPC Contractors.

Construction Manager at Hyunadai Heavy Industries, Ltd.,Co,Korea
  • Egypt - Damietta
  • December 2011 to March 2014

- Installation and Commissioning till start up of 220 KV GIS Substation and connecting to grid.
- Installation of all Remote End Substations and feeders facilities and communication & Protection Systems.
- Installation of Outdoor Equipments and connection with Transmission lines with slack span conductors.
- Connection of Interface cables and 220 KV Cables with Transformers and GT systems.
- Releasing all Punch items after Energization till TOAC and FAC date
-Handling all shutdown schedules with NECC and dispatch center.
-Handing over all related As-Built DWG's.

Site Project Engineer at Kharafi National for Mechanical Electrical Works SAE.
  • Egypt - Damietta
  • December 2010 to December 2011

Project Name: Damietta Simple Cycle Power Plant (500MW GAS TURBINE Project).
Owner: EAST DELTA ELECTRICAL PRODUCTION COMPANY (EDEPC).
Consultant: (PGESCO/BECHTEL)
Job position: I&C Electrical Construction Engineer.

Duties:

- Supervision of All Electrical construction activities on 4*250 MW GT GE frames 9E.
-Installation of GAS INSULATING SWITCH GEAR 220 KV (GIS) and Gantry Area.
-Pulling and Termination of 220KV Cables from Main Transformer to GIS.
-Erection of all EARTHING NETWOK including risers (pigtails) &Mesh, lightning protection and all MANHOLE (Duct Banks) and HAND HOLE.
-Installation of all GIS equipments including Crans&GIB&CCVT&CT&LINE TRAP (LMU) &Surge Arrestors (SA) &cable sealing end and Gantry.
-Installation of Batteries and Batteries Charger system for (220&48) VDC and UPS.
-Installation of Digital Power Line Carrier (DPLC) and all communication systems.
-Coupling With OHTL With slack span conductor.
-Installation of Over Head crane 10 Ton.
-Handling all related works after Energization (Punch list) clearance and warranty period.
- Issuing all Clearance Certificates until receiving FAC (Final Acceptance Certificate).

Site Electrical Engineer at hitachi
  • Egypt - Cairo
  • April 2010 to December 2010

1) Erection of BMS PANEL (BOILER MANGEMENT SYSTEM).
2) Erection of Marshalling cabinet & Vibration monitor panel.
3) Erection of impulse tube, air & control tube piping.
4) Pulling & terminetation of all kinds of cables in (GRF, FDF & BURNERS).
5) Making all construction works for lighting & fire protection system.

Site Electrical Engineer at ALSTOM
  • Egypt - Cairo
  • December 2008 to April 2010

1) Installation of one Main 220 KV & Auxiliary 6.6 KV transformers and isolated phase bus duct (IPBD)
2) Erection for M.V Switch gear, load centers, low voltage panel such as MCC (Motor Control Center).
3) Termination for all MV Cables & LV Cables.
4) Conduits, Raceway and cable tray installation.
5) Pulling of fiber cables, network cables and special cables.
6) Erection of (SF6 GCB) Generator circuit breaker.
7) Erection of All Earthing Network cables.

Education

Bachelor's degree, BSC of Electrical Engineering Power and Control
  • at Mansoura University Egypt, Faculity of Elkectrical Engineering
  • May 2008

BSC of Electrical Engineering and Excellent grade in project. Degree : Bachelor of Electrical Engineering. University : Mansoura University. Faculty : Faculty Of Engineering. Major : Electrical Power and Control. Graduation Year : May 2008. Graduation Grade : VERY GOOD. Graduation Project : Proposed Adaptive Time Delay Over Current Relay & Simulation By PSCAD. Project Grade : Excellent.

Specialties & Skills

Set Construction
Management
Electrical Safety
Electrical Controls
Electrical Installation
- Good command of: 1. AutoCAD.
Electrical Engineer/Manger for H.V Substations and Power Transformers.
Electrical Project Engineer Power Plant ( GT& Thermal) Projects.
Electrical Construction Engineer for H.V / GIS Substations and Power plant projects
project execution
marketing
ms project
operation
project planning
primavera
materials
negotiation
GIS Substations
Construction
Site Management
Site Management
Transformers
Construction Management
Turn Key Projects
Construction Management
Thermal Power Plants
Gas Turbine
negiotiation
Project Close Up
Oil & Gas
Project Close Up
Transmission Line and Distribution
Procurement

Social Profiles

Personal Website
Personal Website

URL removed due to policy violation. Please contact support for further information.

Languages

English
Expert
Arabic
Expert
Korean
Beginner

Training and Certifications

Protrection training for GIS Relay System (Training)
Training Institute:
Schnieder Electyric France
Date Attended:
July 2012
Duration:
12 hours
Traing Program from Hyosung Coropoaration for 220 KV GIS System (Training)
Training Institute:
Korean Hyosung Company
Date Attended:
July 2011
Duration:
32 hours
Maintenance Training for Telecommunication System for GIS (Training)
Training Institute:
PLCI
Date Attended:
March 2013
Duration:
8 hours

Hobbies

  • To evaluate my soal and increase my mind expansion
     Reading books and browsing internet.  Playing football & traveling.
  • Browsing Internet for last updates and reading books