Total years of experience :17 years, 6 Months

Manager Projects & Design at Tesla Power
  • United Arab Emirates - Dubai
  • September 2023 to December 2023

• Heading projects and design for Control, Protection and automation panels related to substation projects with overall value close to 40M AED
• Supervise team for establishing the project execution approach and overseas project handover, execution, planning, monitoring and control of both internal and external resources to accomplish all project goals
• Review of contract received from sales team
• Supervise Project Managers to Develop project schedule and freeze with respective stakeholders (internal and external)
• Preparation of project specific risk and opportunities management plan
• Coordination with Project team and design support for drawing approvals
• Coordination with Eng and SCM to place order on sub supplier for material procurement
• Coordinate with factories for production plan and follow up on production progress
• Coordination with suppliers for material readiness and with factory for completion of FAT
• Follow-up on Material shipment, material receipt at site and acknowledgment from sites for submission of Milestone billings (if any)
• Coordinate with stakeholders for Installation, testing and commissioning at site
• Closely coordinate and document change requests related to project scope and get approvals for time extension, additional cost etc
• Project handing over, as-built drawings, commercial closure etc and collection of PAC, close out of snags & FAC
• Payment follow-up with Customers
• Finalize the monthly production plan for the factory
• Supervise overall design related aspects of various type of systems like LCC panels, Control, Protection and Automations panels etc.
• Conduct Design scrutiny meeting with customer and end clients for getting approvals
• Support design team to finalize the material ordering BOQ
• Plan and forecast overall load of design team
• Support and follow-up design team in delivering all design documents on time
• Optimize design manhours by standardizing the design for various customers
• Support proposal team for the Preparation of all technical (offer, compliance, and deviations), commercial (costs and prices) workings
• Effective co-ordination with Engineering, Operations, Factory, SCM, Quality and Logistics team to understand the technical aspects and support the quotation review
• Review and scrutiny of customer specification, requirements and determine optimum solution for proposal
• Effective Communication with factories, OEM & other third-party items for technical and commercial clarifications
• Propose different solutions to Sales Team and support to identify the optimum solution
• Technical Support and clarification during bidding process
• Develop and establish positive relationship with existing and identify new customers
• Finalize orders and handover to Operation team by conducting Internal KOM
• Apply Effective methods to identify priorities, solve open points, preparation of schedule and identify the most efficient method to do the work
• Update proposal status and follow-up with Factories, contractors, Internal and External Customers
Projects Handled:
Successfully handling projects for utilities and Oil & Gas companies in Middle east.

Technical Project Manager at Govt of kerala
  • India - Thrissur
  • March 2018 to August 2023

• Technical Project Manager for turn key substation projects upto 220kV with value 660M INR(7.9M USD).
• Member of Planning board for Power projects
• Member IS to update and review the various standards.
• Responsible for finalizing the feasibility and DPR for EHV substation projects
• Conduct and Attend Bid meeting to finalize the contractors
• Chose the right vendor complying GTP and within budget for different scopes related to substation projects like primary equipments (CB, Disconnector, Busbar, LA, Power Transformer, CT, VT etc, .), secondary systems (CRP, Automation, Telecom, RTCC, MK, LVAC, DCDB etc, .), Generator, Earthing systems etc, .
• Preparation Project Master document list
• Arrange KOM with various contractors
• Drive contractors to run the projects within the main project schedule
• Apply Cost optimization techniques during detailed design stage
• Conduct Bi- Weekly progress meeting to make sure that projects is in line with the schedule
• Responsible for Approving conceptual and detail design approvals for all electrical system
• Implement Budget optimization techniques across various stages of the project so as to complete the project within the Govt budget.
• Attend and witness FAT as well as SAT.
• Giving approval for Contractor invoices/bills against different milestones achieved
• Identification of project specific risk and timely report to govt with response plan
• Conduct surprise inspections at site to make sure that all Safety practices are strictly followed
• Responsible for Approving contractors and issuing contractor/supervisor licenses
Projects Handled:
• 220/110kV Kunnamkulam Substation for KSEBL, Kerala, India
• 110/11kV Mannuthy Substation for KSEBL, Kerala, India

Technical Manager at Siemens
  • United Arab Emirates - Abu Dhabi
  • April 2011 to February 2018

Role:

Ä Design&engineeringofprotectionpanelsforTransmissionLines, Transformers, BusBars, Fault monitoring Systems etc.
Ä Design&engineeringofSubstationAutomationSystems.
Ä Design&engineeringofSubstationRTUsystems.
Ä Spearheadingprojectplanninginvolvingstudy, salientdesignaspects, riskmanagementplan, etc.
Ä Lookingaftermaterialrequirementplanning&ordering.
Ä Collatingdesignreviewsfromcustomersandobtainingapproval.

Projects Handled:

Ä SuccessfullyhandledSubstationprojectsforAbuDhabiTransmission&DespatchCompany(TRANSCO), ADDC, AADC, GASCO, DEWA, Qatar National Cement Co., KNPC & Kahramaa.


• Standardized solution of first Parallel Redundant Protocol based Substation Automation Systems (SAS) for 45 Nos. of 132kV GIS Substations in Dubai Electricity and Water Authority Network.
• Protection & SAS Panels for 400kV Shabia-3 Power Plant in Kuwait.
• Protection & Automation systems for 132/22kV CUP2 AIRPORT Substation in TRANSCO.
• RTU panels for M20 S/S in Kuwait National Petroleum Company.
• Protection Panels for 400kV BARAKAH Nuclear Power Plant 1 1⁄2 Breaker switchyard in TRANSCO.
• Substation Automation Systems (SAS) for 33/11kV ME09 S/S in ADDC.
• Protection & Automation systems for 33/6.6kV E14 S/S in Qatar National Cement Co.
• Protection & Automation systems modifications in for 33kV S/S in ADDC.
• Fault Monitoring Systems for various 400/220/132/22/11kV substations in TRANSCO.
• Busbar Protection panels for various 132/11kV substations in TRANSCO.
• Substation Automation Systems (SAS) for 33/11kV DS3 S/S in Khalifa Port Industrial Zone.
• Protection & Automation systems for 132/33kV Taweelah-A Substation.
• Protection & Automation systems for 220/33kV ADCO Substation.
• Busbar & Breaker Failure Panels for 220kV ASAB Substation.
• Busbar & Breaker Failure Panels for 400/220/33kV BAB-2 Substation.
• Protection & RTU panels for Etihad Rail Project.
• Substation Protection & Automation Systems for 220/33kV Substation for Al Ain PowerHouse
• 220/132kV Transformer Protection & AVR panels for HABSHAN 5, GASCO Project.

Design Engineer at GE Grid Solutions
  • Saudi Arabia - Riyadh
  • June 2008 to February 2011

Role :
Ä Handlingdesign&engineeringofcontrol&protectionpanelsforGenerators, TransmissionLines, Transformers, Bus Bars, etc.
Ä Spearheadingprojectplanninginvolvingstudy, salientdesignaspects, riskmanagementplan, etc.
Ä Lookingaftermaterialrequirementplanning&ordering.
Ä Collatingdesignreviewsfromcustomersandobtainingapproval.
Ä CoordinatingwithManufacturing, procurementandprojectmanagementteams.
Ä SupportingproposalteamtofinalizetheTechnicaloffers.

Project Handled:

Ä Successfully handled projects for various customer in Middle East regions.
• 132kV Duba Power Plant Extension, SEC-East.
• Control and relay panel for 110/13.8kV STP Power Plant: SEC - South.
• Control and relay panel for 110/13.8kV STP Power Plant: SEC - South.
• Control and relay panel for 132/13.8kV Al-Oraijah Substation: SEC - Central.
• Protection panels for 110/13.8kV Substation in Knowledge Economic City: SEC - South.
• GCC Interconnection Authority (GCCIA) Phase-I Project.
• Phase-8 Package for Qatar General Electricity and water corporation (KHARAMA) including
various substations starting from 11 kV to 400kV.

project engineer at ABB
  • India - Bengaluru
  • June 2006 to May 2008

Key Highlights:

Ä Gainedexperienceindesign&engineeringofcontrol&relaypanelsforsubstationsupto400kV.
Ä Preparedgeneralarrangementandschemedrawingsforcontrol&relaypanelsbyselectingproperrelaysand
other equipment.
Ä Heldtechnicaldiscussionwiththecustomersandacquiredapprovalasperprojectactivitychart.
Ä PreparationofTechnicalspecificationforboughtitems(meters, annunciators, switches, etc.)andotherequipment
required for panel assembly using Office Automation Package.
Ä PreparationofWiringscheduleforcontrol&relaypanels.
Ä CoordinatedwithManufacturing, PurchaseandCustomerResponsedepartmenttomeetwiththedelivery
schedule of the project.
Ä EngineeringforsubstationautomationwithIEC-61850communicablerelays


Ä Successfullyhandledthefollowingprojects:

• GCC 110kV line control & relay panels for Zahi Rubbers, Pvt. Ltd., Kerala.
• 220kV control and relay panels for various substations (Feeder, Transformer, Bus Coupler, Bus Bar &
Revenue Metering) control & relay panels for Gujarat Energy Transmission Company, Gujarat.
• 220kV Amarkantak Low impedance Bus Bar Protection Panels for BHEL, Amarkantak.
• 220kV various substations for Power Grid Corporation of India Ltd., Assam.
• 400kV Korba substation (Feeder, Transformer, Bus Coupler, Bus Bar & Revenue Metering -control
relay panels & for L&T.
• 33kV various substation package for Ethiopia Electrical Power Corporation Ltd. (EEPCO), Ethiopia.

Education

Bachelor's degree, Electrical and Electronics Engineering
  • at University of Calicut
  • June 2006

B Tech in Electrical and Electronics Engineering

Specialties & Skills

Renewable Energy
Electrical Controls
Electrical Design
Electrical Engineering
PROJECT MANAGEMENT
PROPOSAL MANAGMENT
INSPECTION
electrical engineering

Languages

English
Expert

Training and Certifications

PMI MEMBER (Certificate)

Hobbies

  • Music Direction
    Have composed 60+ independant music productions