MECHANICAL COMMISSIONING SUPERVISOR
NPCC
Total years of experience :12 years, 9 Months
AS PER CV
involve with TOTAL E & P YEMEN for 38.6 MW. Kharir Power Project as a Mechanical Equipment Installation Supervisor I am involve in Installation of Rolls-Royce Gas Turbine, Turbine Auxiliaries, Emergency Diesel Generator, Air Compressor, Air Receiver Vessel, Pumps, all rotating equipment alignment, arrange materials, planning and preparing for inspection. Involve in Pre - Commissioning, Commissioning, Start up and overhauling & stabilizing of Power Plant.
INSTALLATION OF ALL ROTATING AND STATIC EQUIPMENT .