site engineer
chaddad group
مجموع سنوات الخبرة :8 years, 7 أشهر
Key Responsibilities:
---------------------------------------------------------------------------------------------------------------
• Managed day-to-day operational aspects of construction projects and making sure budgets, timescales and project specifications are met.
• Oversaw scheduling, supervision of construction sites, and construction resources and assigning field-specialists and individual responsibilities.
• Performed comprehensive site management for various civil works and seeking approval for the same from respective managers.
• Monitored construction schedules and milestones for various disciplines and prepared daily work progress reports.
• Liaising effectively with all project stakeholders and participated in design review, quantity calculations (concrete, steel, and plaster), and safety control as well as change requests in compliance with the organizational guidelines and project requirements.
• Utilized defined project processes to manage quality, risks, changes, issues and evaluated plans and specifications for completeness, accuracy, and constructability.
• Prepared daily and weekly progress/technical reports, site diary for management review and provided data to ensure alignment with all engineering standards, codes, specifications and design instruction.
• Served as a technical support at construction site; checked quantities and ensuring the accuracy of calculations in addition to resolving all site problems.
Project Involved:
---------------------------------------------------------------------------------------------------------------
• American University of Beirut Clinical Center
Key Responsibilities:
--------------------------------------------------------------------------------------------------------------
• Oversaw site works of American University of Beirut Clinical Center and set out the works in accordance with the drawings and specification.
• Assisted the Site Manager organise the site paperwork, quantity take off, daily site records and management resource on and off site.
• Collected metrics data (such as baseline, actual values for costs, schedule, work in progress, and work completed) and reports on project progress and other project specific information and helped the Site Manager in handling project variances.
• Checked and prepared site reports, designs and drawings and made cost-effective solutions and proposals for the intended project.
Key Responsibilities:
--------------------------------------------------------------------------------------------------------
• Oversaw facets of administration functions and reviewed all documents to ascertain precision and reported variances to the management.
• Provided technical support to construction sites by supervising site activities and performing quantity calculations for concrete, steel, and plaster in addition to ensuring site safety control and change orders requests.
• Supported data collection, preparation of drawing of building maps and conducting field tests.
• Applied acquired knowledge to plan and efficiently organize the site facilities to meet deadlines.
• Participated in hands-on projects, learned new skills, gained familiarity with new tools/techniques and got opportunity to meet professionals of rich and varied background within the industry.
,