Total years of experience :31 years, 2 Months
unemployed
Checking on site fabrication (in Italy and Kazakhstan) mechanical activities for a Kazakh crude oil industry project.
On job training for Iraqi mechanical technicians about rotating equipment specific maintenance (pumps, compressors, fans, blowers, etc), and static equipments (tanks, vessels, piping, etc).
Chemimontazh (Atyrau) Ltd. \nApril to December 2012 \nConstruction Engineer \nControl of construction of Water Treatment Facility for the American-Kazakh joint venture "TENGIZCHEVROIL" in Tengiz Oil Field, Kazakhstan
Petrofac/TTE/ ISS International Spa \nJune 2009 July 2011 \nMechanical Instructor \nPreparing course materials and teaching future Omani/Kuwaiti field operators about specific mechanical maintenance of equipments on a crude oil field in classroom and on the site.
Karachaganak Petroleum Operation bv (KPO), Kazakhstan \nSept 2005- June 2008 \nMechanical Supervisor \nResponsible for technical support of a comprehensive maintenance service, covering planning, monitoring, reporting, \nsupervision and execution of routine, scheduled preventative and breakdown maintenance for all equipment, interconnecting piping and pipelines operating within KPO oil production facilities. \nAccountable for work pack planning and spare parts, material management in Maximo Asset Management System \nTraining local personnel regarding mechanical maintenance
Rheinhold & Mahla International Ltd. \nApril 2003 to March 2005 \nConstruction Manager \nControl of several industrial (mainly pipeline/piping) projects for the American-Kazakh joint venture "TENGIZCHEVROIL" in Tengiz Oil Field, Kazakhstan
TECNIMONT S.p.A Milano \nAugust 1996 to January 1999 \nTechnical Advisor / Senior Supervisor \nTechnical back-up service on a Nigerian polyethylene plant at Port Harcourt. Advising, consultancy, holding training courses on maintenance and operation of rotating and static equipments, piping systems for the local maintenance and operation personnel. \n \n \nEarlier Positions:
Commissioning Engineer - TENGIZCHEVROIL, Kazakhstan - 1994 \nControl of pre-commissioning activities on site in Tengiz, Kazakhstan, for the American-Kazakh joint venture
Project Engineer - National Nigerian Oil Corporation Germany/Nigeria - 1993 to 1994 \nManagement of Design and Vetting Team of 12 engineers representing the Nigerian National \nPetroleum Corporation at contractors design office in Munich, Germany. \nProject scheduling and cost planning. Allocation and control of work package, covering bid \nassessment, hydraulic calculation for the 24" multi product pipeline, tank farms and substations. \nPhase2 in Nigeria (Suleja) acting as Pipeline Engineer, responsible for the construction for the pipeline.
Area Engineer - Gas and Oil Transportation Company - Hungary - 1984 to 1992 \nEngineering tasks for the Company operating nearly 10000 km long high-pressure HC pipeline system including pump stations, natural gas turbo-compressor units, gas delivery and metering stations etc. \nPlanning and supervising of mechanical activities for maintenance, new installations and some technical developments. \nThe very first time introducing the on-line pipeline inspection technology to the Company in co-operation with TUBOSCOPE and BRITISH GAS. Analysis and evaluation of results, preparation of repair technologies on the basis of inspection reports and recommendations. Supervising of rehabilitation activities on site. \nSupervising of new Hungarian pipeline constructions.