Hemakrishna Tatineni, Associate manager

Hemakrishna Tatineni

Associate manager

Adani total gas limited

Location
India
Education
Bachelor's degree, Mechanics
Experience
20 years, 7 Months

Share My Profile

Block User


Work Experience

Total years of experience :20 years, 7 Months

Associate manager at Adani total gas limited
  • India - Delhi
  • March 2021 to August 2023

Designation: Associate manager- PNG
O & M In charge - Steel, PE, CGS | M/s Adani Total Gas Ltd - Khurja area, India| Mar 2021- Aug 2023

● Develop plans to implement and improve the existing and new process to rehabilitate the facilities. Technical support for Design of Facilities, budget plans, regulatory compliances, EHS plans, construction deliverable's, maintenance, shutdowns, and other package items.
● Building the teams of design, execution, emergency shutdowns, maintenance includes QRA studies, modifications of stations, the extension of pipelines, relocation of facilities, commissioning, start-ups, and continual maintenance.
● Overview of general operations of PNG (PE), Domestic, commercial, industrial maintenances, material shortfall, LUAG studies and recommendations to control gas losses.
● Seamless coordination with variety of AMC’s and other emergency contractors for smooth operations and maintenances.
● Participate in technical, operations, material management and other stake holder meetings and provide inputs to improve processes.

Manager construction at Tractebel engineering private limited
  • India - Chennai
  • December 2018 to December 2020

• Implement and improve process requirements, provide technical recommendations, identify risks and provide solutions to meet the project schedules
• Providing assistance to engineering, procurement, construction and management teams, evaluation of layouts, plot plans, delivery schedules, material requisitions, surveyor data, master schedules, Route maps and more
• Support construction teams meet plans, identify root causes, develop micro plans to recover delays, eliminate non-value added activities to improve the operational efficiency through technical and functional matters, control project requirements, implement statutory/ regulatory guidelines through the project completions, help in actual measurement and bill certification

Construction Manager at Sanmarg projects pvt. ltd
  • India - Ahmedabad
  • May 2017 to December 2018

• Review contractor's resources to meet daily plans, actual measurement and bill certification
• Application of good engineering practices through stage wise construction in either civil, mechanical, pipelines, Electrical & instrumentation of Site acceptance tests
• Exemplary assist stakeholders in Project controls, progress reviews, reporting, End to End Project Construction completions and adherence of Zero HSE policy
• Ensure projects were executed according to approved time, cost estimates and quality
• Maintain an excellent working relationship with retail operations

Achievement
• Flawless coordination with stakeholder teams helped in develop daily plans, complete tasks, progress reports, client approvals
• Learned, implemented and improved my Skills in team Management, technical to completions

Project scope:
• Construction supervision of 30-inch dia, 160km MBPL-Palanpur Pali Pipeline | Rajasthan, India |
Despatch terminal (Palanpur, Gujarat), Intermediate Pigging station (Shiv Talav, Rajasthan), SV stations (5 Nos.) and their associated emergency salient features

AGM- Pipelines (HOD) at Great Eastern Energy Corporation Ltd
  • India - Kolkata
  • July 2015 to May 2016

• Learned, Implemented and improved the existing and new process to rehabilitate the facilities
• Technical support for Design of Facilities, construction deliverable's, maintenance, shutdowns spares and other package items
• Leaded the teams of design, RoU, emergency shutdowns, maintenance includes modifications, the extension of pipelines, relocation of pipelines, commissioning, start up's and continual maintenance
• Inspected and tested pipe systems to ensure safety
• Assisted in repairing leaks and making adjustments to pipe systems
Achievement
• Flawless coordination with stakeholders, helped teams to develop plans, SoP’s for pipeline design, execution, maintenance
• Helped company on Foreclosure of third-party audit compliances, obtaining regulatory permissions, Risk assessment studies in-service pipelines, cathodic interference, pipeline health reviews with an external consultant, and recorded foreclosures.

Project:
• Design, projects and maintenance of pipeline packages (TS, RoU, O & M) and networks capable of 256kms HDPE, Steel pipeline comprising the upstream, transmission and distribution networks and associated emergency salient features

Section Manager- Pipelines at Mott MacDonald pvt. ltd.
  • India - Mumbai
  • June 2013 to June 2015

• Overviewed construction plans, managed resources and coached the team to meet the schedule of Main/booster Pumping terminal, pipeline network including fire & alarm package from detail engineering, material mgt, stage-wise construction, testing of packages to flawless completions
• Conducted assessments and developed action plans to anticipate and respond to problems
• Managed complex issues within functional area(s) of expertise
• Managed and directed team members within the Section to ensure effective project definition, planning, development, and delivery
• Helped contractors to meet daily plans

Project:
Mangalore Hassan Mysore & Solur LPG Pipeline (multi-inch dia, 356kms); envisages from existing Mangalore HPCL LPG terminal via Neriya & Hassan (IPS) to Yediyur and Spurline from Hassan to Mysore including 18nos. SV stations for future TOP facilities and Mangalore dispatch terminal providing with pumping facilities (launcher) and receiving the station at Yediyur & Mysore.

Construction Manager- Pipelines at Valdel Engineers & Constructors Pvt. Ltd.
  • India - Bengaluru
  • October 2009 to June 2013

• Provided project scheduling, budgeting projections and cost analysis
• Supervised and inspected stages of construction maintaining the highest quality control and code compliance
• Accountable in project review/ coordination meetings, client assistant, actual measurement _bill certification, resolving any discrepancies at the site and contractual matter's
• Supported team and contractors to meet aggressive daily plans
• Actual measurement and bill certification

Achievement
• Flawless coordination with Clients, Resolution of project interface issues, Contractors to complete works as per agreed schedules and allocation of the inspection team and leaded the team to project completion
• Proposed Site deviations (if any) are recommended as per policy and obtained approvals from owners/ Authorities
• Learned, implemented and improved my Skills in team Management, technical to completions

Projects:
Bodighodi Ambardi Gas Pipeline (12-inch dia, 46kms).
Tana Amreli Gas Pipeline Project (12-inch dia, 75kms).
Darod- Jafrabad Gas Pipeline Project (24-inch dia, 211Kms and associated emergency salient features

Pipeline Engineer at Punjlloyd ltd
  • Qatar - Doha
  • January 2009 to August 2009

• Supervised the mainline activities of the pipeline is carried out with Safety & project requirements are met as per QP specifications
• Responsible to manage resources, support lead manager through construction, coordination for the work permit, and negotiate with the client, subcontractors, consultant in counterparts to ensure that the construction is carried out in correspondence with plans and specifications
• Performed troubleshooting responsibilities on pipeline safety
• Maintained anti-corrosion systems to ensure longevity and functionality of buried structures
Achievements
• Flawless Site coordination on daily basis to supervise site inspections and progress reporting for Anti-corrosive coating (FBE), Micro-tunneling for gas pipeline Road crossing to complete works as per policy/client specifications
• QP has conducted personnel training and on successfully completions Awarded certificates for Level-1 'Gas Operations' and H2S/BA awareness programs

Project:
• Construction services of 36-inch dia, 211km SGT pipeline and associated emergency salient features

Pipeline Supervisor at StroyTransGaz
  • India - Hyderabad
  • October 2006 to November 2008

• Ensured the scope of activities are carried out as per codes & specification of client Coordinate with Client & sub-contractors to complete works within the schedule
• Carried out daily monitoring and inspection activities as indicated to the Site Supervisor
• Ensured balance back-end activities like tie-in/ final tie-ins, Hook up with Valve station piping/ terminal arrangements coatings, lowering, OFC & backfilling associate installations, controls, pressure testing, cleaning including crossing works
• Adhered to safety measures in all operations

Project:
48 inch dia, 250 km of East-west gas pipeline project (Section-B) and associated emergency salient features

Techniques:
● CRC-EVANS/USA -Automatic Welding Machines.
● AUT: RTD Services/ USA, Canada, New Zealand.
● Welders: Turkey welders.
● Shackles: Imported from USA and Germany.

Pipeline Engineer at Vijaya Engineering consultancy
  • India - Hyderabad
  • June 2000 to April 2005

• Coordinated with vendors for material inspection and reconciliations
• Effective coordination with TPI on stage wise inspection & Documentation works
• Prepared Pipe books in all construction & testing/commissioning works prepare RA bills and ensured verification procedure from TPI/ PMC /in line with project conditions
• Hands on experience in handling pipeline design and construction projects

Projects:
• Construction and maintenance service for flow lines (Wells); network pipelines; terminals - Storage Oil tans; and 12-inch Dia x 600 Km VSPL | Rajahmundry | June 2000- April 2005 |

Education

Bachelor's degree, Mechanics
  • at Peoples friendship university of russia, LUMUMBA
  • May 1999

MECHANICAL & EQUIPMENTAL ENGINEERING. four years full time higher level Education programme course is filed of study/specialty- Completed with Merit . Practical Training: manufacturing & process 4 weeks.- passed Maintenance & repair 2weeks- Excellent. Industrial Manufacturing Process 4 weeks- excellent. Preparation & defense of Diploma Thesis: Design of process planning & production of a horizontal milling machine main drive, 5 weeks- Excellent.

Specialties & Skills

Expediting
Turnkey Projects
Project Reporting
Client Handling
Resources Management
MS Word
Pipelines
problem solving
computer skills
ability of multi-task
decision making
good time management
Strong organization skills
good communication
inter personnel skills
Policies & Procedures
Strong Work-Ethic
commissioning

Languages

English
Expert
Russian
Intermediate
Hindi
Intermediate
Telugu
Native Speaker

Training and Certifications

six sigma green belt (Certificate)
Date Attended:
March 2019
NDE Certification (Certificate)
Date Attended:
July 2010
Valid Until:
July 2018
AutoCAD 2D (Training)
Training Institute:
CADD Center, Vijayawada
Date Attended:
July 2016
Duration:
80 hours

Hobbies