hussein salah, Project

hussein salah

Project

AAW Consulting Engineers

Location
Egypt - Cairo
Education
Bachelor's degree, Mechanical Engineering
Experience
15 years, 1 Months

Share My Profile

Block User


Work Experience

Total years of experience :15 years, 1 Months

Project at AAW Consulting Engineers
  • Egypt
  • January 2007 to January 2008

Bashteel left station Sewage Project Total construction cost is (70 million L.E

Mechanical Engineer at Helwan Construction for Hotels and Resorts
  • Egypt
  • January 1998 to January 2007

200000 m3/day m3 /day, consists of 4 KSB Pumps discharge 1400 L/sec with delivery head of 56m, pipes cost iron, non return valves gates and butterfly valves anti hummer system.

- 4 nos. of ITSA 5000 Roher (V) Pumps - 6 m/head, 20L/s discharge
-4 nos. of IBSHWAI 10000 KSB (V) Pumps - 14mhead, 100L/s discharge
-3 nos. of ELAGAMEN 4000 Homa (sub.) Pumps- 18m head, 30L/s discharge
-4 nos. of KASR RASHWAN 8000 Flow Serve (V)Pumps - 24m head, 50L/s discharge .
1- Responsible on installation, erection, operation & maintenance of all equipment used in the above mentioned projects.*
2-Technical office works of estimation, preparing technical & financial prequalification several bids study and revision for Contractor.*
3-Mechanical submittals, site inspection and supervision for all erection works in the project & coordinating with the owner contacting the project’s Sub- contractors.*
4-Responsible with the main transmission discharge water pipe line works including excavation, trenches side support, bedding, pipe laying, hydraulic test and backfilling.*
5-Dewatering pumps, overhead cranes, workshop equipment, fans and steel structure.*
6-All pipes work, fitting, valves, gates, flow level meter.

Project at Canal Suez Bank
  • January 2006 to January 2007

Supply, Installation, testing and commissioning of UPVC drainage pipes with diameters ranging from 90mm to 250mm with all fitting and installation of house connections and gully trap
•Construction and superision of all manholes
•Connection with the existing systems
•Construction and supervision of all raisers(water&sewage)
•Erection and supervision of all accessories
•Erection and supervision of fire fighting system
•Erection and supervision of air conditioning system

Project at Construct a Tourist Village Hotel in Hurghad
  • January 2002 to January 2006

1-Design and installation networks (sewage & water). 2-Construct an Irrigation mains & distribution network with diameters ranging from 50to250 mm & approximate length of 3 km to feed all land scape.
3-Installation for firefighting system &distribution networks.
4-Installation for air conditioning system (chiller, ducts& A.U.H).
5- Construct for underground tank(1000m3)with all pipes and fittings.
6- Revision of all shop drawing and coordinate between(civil, electrical & mechanical) department.
7-Design &shop drawing for all swimming pools and artificial pond and installation.
8-Design and installation (mechanical room &Lift station &booster pump)
1-Materials and equipment inspection according to the recommended specifications.
2-Supervision of all mechanical equipment installation, provisional tests, trials and operation.
3- Reviews and approves Contractor’s submittals.
4- Review and approve shop drawings .
5-Technical support for the execution site.

Resident Engineer at Beach Resor
  • January 1998 to January 2002

1- Design and installation networks (sewage & water).
2-Construction of irrigation mains & distribution network with diameters ranging from 50-250mm &approximate length of 3 km to feed all land scape.
3- Installation for firefighting system &distribution networks.
4- Installation for air conditioning system (chiller, ducts& A.U.H).
5- Construction of underground tank (1000m3) with all pipes and fittings.
6- Designs the shop drawing for all swimming pools and artificial pond and installation .
7- Design and installation (mechanical room, lift station& booster pump).
8- Design and installation of the plumbing system.




1- Installation for sewage network (pipes, manhole & treatment plant) air condition system, firefighting system & swimming pools.
2-Reviews and approves Contractor’s submittals.
3- Technical support for the execution site.
4- Materials and equipment inspection according to the recommended specifications.

Site Engineer at Consulting co
  • January 1993 to January 1998
Senior Mechanical Engineer
  • to
Project at KSB Pumps
  • India
  • to

Wastewater Pump Station 1 & 2 at New Cairo City
Capacity: 20.000 m3/day Consists of: 4

Project
  • to

Water & Waste water Treatment Equipment Design.* Gravity oil water separation units with capacity 2 -5 m³/hr.* Dissolved Air Flotation unit for Emulsion oil water (DAF)capacity 10 - 15 m³/hr.* Aeration and settling tanks, piping layout for any capacity.* Cairo Co. for Oil & Soap - Alex. CO. for Edible oil refinery -Miser for Petroleum products.
Makes work shop drawing for the equipment of water treatment.* Supervises and assists on solving manufacture problems

Project at Hayat Regency Hotel
  • United Arab Emirates
  • to

The project consists of a building with 420 rooms, 18 nos. of villa, 2 nos. of main swimming pools and 2 nos. of artificial pond.

at Installation of networks
  • to
at Irrigation networks
  • to

) UPVC.

at firefighting networks
  • to

5- Installation of air conditioning system networks (400mm, 300mm, 250mm & 150mm) Seamless sch40.
6- Installation of swimming pools system, artificial pond and mechanical rooms.
7-Erection of plumbing system (fitting-risers-valves) and all accessories.

Education

Bachelor's degree, Mechanical Engineering
  • at Helwan University
  • January 1993

Specialties & Skills

GRAPHIC DESIGN
MATERIALS MANAGEMENT
MECHANICAL
NETWORKING
PLUMBING
SUPERVISORY SKILLS
TECHNICAL SUPPORT
DELIVERY
HUMAN RESOURCES