• Participate in the internal auditing process: audit planning, conducting audits, preparing audit reports, and follow up on non-conformances
• Drive quality in the organization through preventive actions
• Share best practices among projects and teams
• Support projects during start-up phase and full life cycle
• Prepare the Project Quality Plan, under which the project team proceed
• Prepare the project overall Quality report and highlights for Project Manager/Engineer and Client’s information
• Plan and conduct the Client Surveys and submit the corresponding report.
• Plan and attend pass gate reviews
• Stimulate the Project team on Value Engineering, Value Plus, Sustainability Plus
• Prepare and issue Value Plus and Sustainability Plus Ideas
• Follow up and close out of the Performance Improvement Action Plans
• Prepare and issue Lessons Learned Action Plan
• Coordinate and participate in the establishment of the quality management system through elaboration of Work instruction and procedures
• Coordinate the standardization of the Work instruction and typicals for the engineering and support disciplines
Maintenance and rebuilt Responsible for vertical cylindrical aboveground tanks within the ISOMONTAGE Company at SAMIR refinery MAROCCO:
-Implementation of the RBI method (Risk Based Inspection) in
accordance with API standards 580/581/653.
-teams Management and Monitoring the progress of
undertaken work within the good practices and deadline
respects.
SAMIR REFINERY 2014 turnaround Responsible with ISOMANTAGE company, furnaces and blowers parts:
-Scheduling and technical procedures elaboration.
- Monitoring execution and ensure compliance and
deadlines respects.
- Management and supervision of the project.
SITE PROJECT MANAGER within the ROHRER GROUP (industrial services) for MITSUI-DAEWOO thermal insulation project of JLEC(Client) unite 5&6 thermal power Plant and OCP(Client) ODI P1&P3, Project turnover exceeds 220 million dirham
• Ensure completion of work within the rules of art and application of standards and norms of quality and Safety.
• Project and staff management from the departure phase to the receipt by the client.
•Management of a thermal insulation project (turnover 23 MMAD ) for TEKFEN (EPC Contractor.) and JACOBS Engineering SA (PMC role), OCP as Client
•Writing necessary procedures: technical, HSE and quality.
•Progress monitoring of undertaken work: drawing preparations, coordination with the various parties (TEKFEN, JACOBS, OCP) through regular meetings, estimation and procurement of all needed materials for the project.
•Ensure completion of work within the rules of art and application of quality and HSE procedures and policies
•Project and staff management from the feasibility phase to the close out