إسلام جول, Resident Civil Engineer

إسلام جول

Resident Civil Engineer

Mehinhardt Consultant Pakistan

البلد
باكستان - بيشاور
التعليم
بكالوريوس, Civil engineering
الخبرات
24 years, 2 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :24 years, 2 أشهر

Resident Civil Engineer في Mehinhardt Consultant Pakistan
  • باكستان - بيشاور
  • أشغل هذه الوظيفة منذ نوفمبر 2020

Building Project
(2+6) Stories
Construction Supervision of PEC Regional Office Building @Peshawar.

Resident Engineer Project Manager في Mott MacKDonal Pakistan-MMP
  • باكستان - بيشاور
  • ديسمبر 2018 إلى سبتمبر 2020

Project Type: Peshawar Sustainable Rapid Transit Corridor Project (BRT-Peshawar). Metro Project (6 Km Bridge, 4Underpasses, 14 Bus station 15 Km Mix traffic and 10 Km drainage work), 28 Km (3 Lane) road.

Project Manager في GKG Saaed JV
  • باكستان - إسلام أباد
  • يناير 2017 إلى ديسمبر 2018

Construction of 42 km Road

Construction Manager في Suido Kiko Middle East ( EPC-Specialized in Water Treatment)
  • المملكة العربية السعودية - جازان
  • يناير 2015 إلى ديسمبر 2016

MODOM (Saudi Industrial Property Authority) Sudair & MOWE (Jizan)
Waste Water Treatment Plant (WWTP-10000 CMD) an EPC Project & 16000 CMD along with left Station and Pipe line.
Main Parts of Project: Admin Building, Aeration Tank, Digesters, Primary & Secondary Clarifiers, Blower Rooms, GLS tanks, Pump rooms, Lift station, Electrical Substation, Equipment installation, pipe lines, evaporation ponds, Storm water network, specialized finishing etc.

Project Manager( Industrial Building) في AL ASAS United Co.
  • المملكة العربية السعودية - الرياض
  • مارس 2013 إلى ديسمبر 2014

o Plan, direct, co-ordinate, and control the work
o • Execute Project in accordance with corporate practices and Project procedures
o • Developing and implementing a project execution plan that meets with Company and Contract requirements
o • Provide leadership and commitment to the Project HSSE and Quality plan
o • Keeping to the control budget within the objectives established for the Project
o • To focus upon customer care and customer feedback
o • To understand the Project ‘business case’ and drivers
o • Act as focal point for Engineering, Procurement, and Project services resources deployed on the project
o • Interface closely with client management representatives to ensure client interests are being accommodated
o • Clearly define and communicate the project objectives and organisation to the Project team
o • To feedback to the Company data related to performance of work on a regular basis
o • To monitor and expedite account receivables for the Project
o • To document lessons learned and to review/implement lessons learned from other Projects
o • To protect the reputation of Mustang
o • To close out the project

Project Engineer-Infrastructure work في GIZ/Dewah
  • باكستان - بيشاور
  • يوليو 2012 إلى فبراير 2013

1-Identify different cluster for the work strategy with close consultation with Political administration, GIZ and local elders.
2- Formation of Community based organizations (CBO).
3-Initial assessment for the proposed grants in the presence of CBOs/prioritized by community.
4- Preparing technical proposals including BOQ, Schedule, budget, design and drawing and submitting to GIZ for the approval.
5-Conducting CBO training regarding capacity building including technical aspects, material purchasing, implementation, operation and maintenance.
6-Preparing and training the CBOs on procurement plan and cash flow chart.
7- Making sure that grant is smoothly implemented as per drawing and specification and GIZ Policies.,

Regional Engineer-Infrastructure work في Creative international (FSSP)
  • باكستان - بيشاور
  • فبراير 2011 إلى يوليو 2012

o Client: Funded by US AID Pakistan
o Location: Mohmand Agency Pakistan
o Project: Infra structure development
o Designation: Regional Engineer (Regional In charge)
o Duration: January 2011 to July 2012
Types of Community Grants completed.

Roads, Street Pavements, Culverts, Small bridges, Causeways, Microhydal, Irrigation channels, Flood protection walls, Schools, Water supply (Tube wells and Gravity), Small dames etc.

Job Responsibilities

o Supervising an Engineering team.
o Preparing work plan in different clusters and Strategy plans.
o Site Survey for initial Feasibility reports and Cost Estimation.
o Preparing BOQ, Site Plan, Project Budget and Environmental document forms (EDF).
o Designing and managing different types of safe water supply system/schemes, Sanitation schemes, link roads, different types of retaining walls, light weight structures, irrigation channels and water courses along with preparation of detailed materials and cost estimates, standards BOQs, site plans and other technical documents etc
o Co ordination with client for the approval of Estimated Cost.
o Preparing Tender documents and Sub contracting for the approved Grants.
o Completion of Grants within Budget and schedule.
o Coordination for change orders, invoice bills and site issues with client and contractors.
o Making sure that construction activities are going as per QA/QC and HSE requirement.
o Preparing and processing contractor progress invoices.
o Preparing daily, weekly repots and updating portfolio manager.
o Preparing grants handovering and closing documents.

Construction Manager / Area superientendent في PCMC
  • المملكة العربية السعودية - حائل
  • مارس 2009 إلى نوفمبر 2010

o Client: Ministry of Water & Electricity/ FURAT
o Location: Hail Al-Shuqaiq Kingdom of Saudi Arabia
o Designation: Construction Manager
o Duration: March 2009 to November 2010

Scope of Work

Construction of Plant Building, Raw & Rejected water Tanks, Administration Building, Guard House, and Pump House, Control Room, Generator House, Valve Chambers, Roads, Pipe Lines, Trenches and Evaporation Pond (3 Km X1 Km).

Job Responsibilities
o To coordinate with sub contractors for designing, third party for testing, Concrete & Material suppliers, Client and Consultant.
o Preparing Material submittals and coordinating for approval.
o Coordinating with QA/QC in preparing QA/QC Plan, Inspection and Testing Plans (ITP) and Formats.
o Preparing Reports on Area concerns and early warnings and Coordinating with Project Manager.
o Supervising a Construction Team including Engineers, Supervisors, Surveyors and Forman.
o Preparing Material Requisitions and Coordinating with Procurement to make sure the material availability on time.
o Pre planning job execution and implementing as per schedule.
o Making sure that each and activity at site is going and per drawing & specification with proper documentation.
o Coordinating with safety and making sure that all employees, Equipment and other property are safe.

Senior Civil Engineer في Saudi Bin ladin Group
  • المملكة العربية السعودية - الجبيل
  • يوليو 2005 إلى مارس 2009

o SABIC / FLUOR
o Client: SABIC / FLUOR
o Location: YANSAB) Kingdom of Saudi Arabia
o Designation: Senior Civil Engineer
o Duration: July - 2005 to March 2009
Scope of Work

Construction of Petrochemical complex including site preparation, Admistration building, Fencing, Underground utilities, plant roads, Exchanger area, tie in area, Pipe racks area, Yansab backbone project, Royal commission sewer line, Butane & Propane line.


Job Responsibilities:

o To plan and implement all execution of job as per SABIC & ARAMCO standards and specification
o Coordinating with client which include Fosters Wheeler, Fluor, SABIC and ARAMCO, Royal Commission, Marafiq, Road &Land scrapping department.
o Worked to coordinate for the procurement activities.
o Preparing scope of work, project schedule, different letters, Submittals and reports, invoices, Book of quantities, Technical Enquiries.
o Plan and Execute infra structure work included sleepers for existing pipe line Re routing Project. Activities included pre casting sleepers their excavation, placing, grouting, and back filling.
o box & pipe culverts, plant entrance gate (sliding &swing), road, sluice box, ducts banks and manholes electrical trenches lighting poles, transformers, , .
o Worked for the construction of ware house. Activities included excavating, casting foundation, grade slab, giving bar bending schedule, material arranging, and erecting of structure.
o Worked for the re routing of IWW (Industrial waste water) pipe line. Activities included excavating and construction of Sump, manholes, thrust blocks schedule, laying GRP &FRP pipes, painting, back filling, installation of sanitary Sewer & Potable water line, construction of manholes and clean outs and other site prep works. Fire hydrants, etc.
o Supervising Plant roads, Activities involved survey, preparation of sub grad, sub base, Asphalting and their material approval.
o Road crossing activities including deep excavation around the

Project Site Engineer في Tharwat Sahrqawi
  • المملكة العربية السعودية - جدة
  • نوفمبر 2003 إلى يوليو 2005

o Client: Yanbu Industrial Port
o Location: Yanbu Kingdom of Saudi Arabia
o Designation: Project Engineer
o Duration: November 2003 to July 2005

Job Responsibilities / Achievement
o Site survey for the installation of security system.
o Preparing scope of work, project schedule, different letters, Submittals and reports, invoices, Book of quantities, Technical Quarries, Request for inspection.
o Mobilizing site, arranging manpower, tools and equipments.
o Making of duct banks, hand holes, drawpis, lighting poles & camera pole foundations as per HCIS standards.
o Construction of security guard rooms.
o Construction of security fence gates, Road blockers.
o Preparing scope of work, project schedule, different letters, Submittals and reports, invoices, Book of quantities, Technical Quarries, Request for inspection.
o To supervise maintenance works including, electrical duct bank, pipie sleepers, and Stansion foundations.
o To evaluate the invoices as per actual progress.
o To maintain all the reports regarding planning and document controlling.
o To correspondence with all departments involve in the project.

Site engineer في Nasrullah and Inamullah Khan contractors
  • باكستان - ملتان
  • يناير 2002 إلى نوفمبر 2003

o Client:Ministry of Transportation
o Location: Khyber Pukhtoonkhwa
o Designation: Project Engineer
o Duration: December 2002 to November 2003

Responsibilities:
o To correspondence with all departments involve in the project.
o Highlighting lack of progress according to plan and target schedule.
o To evaluates the invoices as per actual progress.
o Site survey for the site selection of petrol pump and their construction
o Rehabilitation works including buildings roads petrol pumps etc.
o Preparing bill of quantities, progress reports, BOQ, , Project schedule, invoices.
o Construction of form to market roads, pre stressed concrete bridges, culverts.

Site Engineer في Engineering consultants Int limited
  • باكستان - بيشاور
  • يناير 2000 إلى ديسمبر 2002

Primary Education Program in District Peshawar Pakistan
o Client: KFW /GTZ and Asian Development Bank
o Location: Peshawar, Khyber Pukhtoonkhwa
o Designation: Site Engineer
o Duration: Jan 2000 to December 2002

Responsibilities:

o Supervising the construction and rehabilitation of primary School.
o To plan the inspection schedules and ensure their implementation.
o To supervise maintenance works in existing School buildings.
o Site survey for the site selection of new primary school buildings and meeting with community.
o Preparing BOQ, Progress reports, Invoices, Technical quarries.
o Attending meeting with client and Sub contractors

الخلفية التعليمية

بكالوريوس, Civil engineering
  • في UET,Peshawar
  • يناير 2000

B.Sc Civil Engineering

Specialties & Skills

Client Co ordination
Time management skills
Cost Management
Construction Management
Construction Supervision
Estimation
Construction Management
Creativitity
Problem Resolver
Deceion Making
Construction Supervion

اللغات

الانجليزية
متمرّس
الأوردو
متمرّس
العربية
متوسط
الباشتو
متمرّس

العضويات

Pakistan Engineering Councile
  • Professional Engineer
  • June 2000
Saudi Council of Engineers
  • Civil Engineer / Professional
  • February 2013

التدريب و الشهادات

HSE (تدريب)
معهد التدريب:
SBG-PCM
Conrete Quality (تدريب)
معهد التدريب:
Fluor Arbia
Micro hydel (تدريب)
معهد التدريب:
FSSP
تاريخ الدورة:
July 2012
Surveying (تدريب)
معهد التدريب:
UEP Peshawar
تاريخ الدورة:
November 1998

الهوايات

  • Social Work
    Social awareness in the people of FATA, for education and improving their lives.Taking their priorities and negotiating with officials for the approval. Giving Monitoring training to the local communities and convincing them to play their important role.