Project Manager
Bayanat Engineering Qatar (BEQ)
مجموع سنوات الخبرة :11 years, 5 أشهر
Approach Surveillance Radar, EPC Project, Value: USD 10 Million
• Managed civil and MEP work packages throughout the project life cycle from initiation till closure
• Managed design center to assure that all design milestones are in line with client requirements
• Engaged weekly with various stakeholders to get their requirements on design and construction
• Supervised the procurement process to ensure delivery of long lead items
• Managed the construction of L-Band radar facility by leading all subcontractors and team members
• Administered contracts for civil contractor, MEP contractor, ELV contractor, and various suppliers
• Achieved project completion without LTI, under budget, and on time
• Successfully managed the interface between clients, stakeholders, and subcontractors
• Managed projects budget and cashflow throughout the project lifecycle to keep a positive cashflow
• Monitored projects schedule and performance by utilizing the earned value methodology (EVM)
• Generated progress reports and monitoring program data to assess efficiency
• Interviewed and selecting staff with appropriate skills to fit for the project activities
• Built strong, lasting relationships and strategic partnerships with the Client
Riyadh Metro Project - Package 1, EPC Project, Value: USD 10 Billion
• Led a team of 6 engineers to complete MEP works on the National Museum and KAFD stations
• Managed projects schedule, cost, quality, and safety
• Managed subcontractors and monitored their performance to assure projects success
• Managed stakeholders and led the interface between all parties
• Managed the testing and commissioning process
• Monitored the projects performance by utilizing the earned value methodology (EVM)
• Collaborated with project leads and managers on different stations to achieve a uniformity in design, construction, and project handing over processes
• Assessed contractors and subcontractors claims from design and quantity perspectives
Riyadh Metro Project - Package 1, EPC Project, Value: USD 10 Billion
• Managed and developed level 4 schedule for 11 Elevated Stations
• Created monitoring tools to measure KPIs and advised on possible solutions to enhance performance
• Planned the MEP system handover process from the construction to the testing & commissioning team
Riyadh Metro Project - Package 1, EPC Project, Value: USD 10 Billion
• Managed design centers during design phase by establishing design requirements, populating schedule of submittals, and engaging them with clients, stakeholders, and subcontractors
• Engaged in weekly meetings with the designers to review progress on the submissions to the client
• Planned, managed, and populated the project wide MEPF procurement strategy
• Managed the works on variation orders and claims
• Designed Heating, Ventilation and Air Conditioning (HVAC) systems for schools in Erbil, Iraq
• Designed plumbing systems for Kudai Towers in Mekkah, KSA
• Engaged with other disciplines in value engineering workshops to minimize the cost and maximize energy savings
• Prepared and analyzed MEP BoQ for mega projects
Developed a permeability measurement device that would monitor and optimize the healing process of bones over specific period of time. Knowing that permeability depends on the pressure drop across the bone scaffold, many tasks were performed to build the device.
These tasks comprise of:
- Calibrating a differential pressure sensor
- Designing a bio-reactor using solid works
- Fabricating the bio-reactor using a laser cutting machine
- Developing a Labview program to save the permeability measurements during a specific period
- Preparing samples made from bio-mechanical blocks to represent the real bone scaffold
- Setting up the closed system by connecting the bioreactor, fluid tank, pressure sensor, peristaltic pump and data acquisition
- Running the system to save the preliminary permeability results of the samples
Gained and developed wide program skills (MATLAB, LabVIEW, and C++), maintained stock of all assets, prepared labs for experiments as per the class schedule, and assisted students in the conduction of experiments.
• Worked, under a rotation program, in each of the following departments: Quality Control/Quality Assurance, Heating Ventilation and Air Conditioning, Planning, Quantity Surveying and Contract Administration, Engineering, Procurement, Plant Machinery Vehicles and Health Safety Environment