Total Years of Experience: 12 Years, 8 Months
February 2016
To Present
Commissioning engineer
at Dar Engineering
Location :
Saudi Arabia
I am working as a Commissioning engineer in Saudi Electricity company. My job responsibilities includes the supervision of testing and commissioning activities, project coordination and design review of project as per SEC standards.
January 2012
To February 2016
Testing and commissioning engineer
at Quality Makers
Location :
Saudi Arabia - Jeddah
I worked as a testing and protection engineer in following projects
-Al Salamah 110kV/13.8kV
-Al Khumrah 110kV/13.8kV
-Al Taif-2 110kV/13.8kV
-Eskan-2 110kV/13.8kV
-Al Lith 380kV/110kV/13.8kV
-ET-2 110kV/13.8kV
-Al-Wajh 13.8kV Distribution Power Plant
-Rabigh Power Plant 2800MW Power Plant
-Taif central 380kV/110kV
-KAEC 110kV/13.8kV
-Makkah Services 110kV/13.8kV
-Makkah Security 110kV/13.8kV
Performed Following test
110kV Testing
-Scheme and modification
-Bay Control Unit Test
-Interlock test
-CT and VT
- Primary and Secondary Injection
-Busbar Contact resistance
-Circuit Breaker
-Gas Purity and Gas Gauges Testing
-Digital Multifunctional Meters and Analog meters
13.8kV Testing
-Scheme & Modification
-Bay Control Unit and Overcurrent Relay
-CT and VT
-Circuit Breaker
-Primary and secondary Injection
-Busbar stability test
-Busbar contact resistance
-Hi Voltage Test
-Digital Multifunctional Meter test
Protection
-Transformer
-Cable feeder
-Bus Coupler and Bussection
-110kV Busbar Protection
-Auto Voltage Regulator
-ABTS
-ACCS
-Under voltage and under frequency
-Interface Alarm Panel
-Fault Recorder Alarm check
Protection relay
-ABB tranformer differential relay RET670
-ABB BCU & overcurrent relay REF615
-ABB BCU & relay REC670
-Siemens Overcurrent 6SJ
-Al Salamah 110kV/13.8kV
-Al Khumrah 110kV/13.8kV
-Al Taif-2 110kV/13.8kV
-Eskan-2 110kV/13.8kV
-Al Lith 380kV/110kV/13.8kV
-ET-2 110kV/13.8kV
-Al-Wajh 13.8kV Distribution Power Plant
-Rabigh Power Plant 2800MW Power Plant
-Taif central 380kV/110kV
-KAEC 110kV/13.8kV
-Makkah Services 110kV/13.8kV
-Makkah Security 110kV/13.8kV
Performed Following test
110kV Testing
-Scheme and modification
-Bay Control Unit Test
-Interlock test
-CT and VT
- Primary and Secondary Injection
-Busbar Contact resistance
-Circuit Breaker
-Gas Purity and Gas Gauges Testing
-Digital Multifunctional Meters and Analog meters
13.8kV Testing
-Scheme & Modification
-Bay Control Unit and Overcurrent Relay
-CT and VT
-Circuit Breaker
-Primary and secondary Injection
-Busbar stability test
-Busbar contact resistance
-Hi Voltage Test
-Digital Multifunctional Meter test
Protection
-Transformer
-Cable feeder
-Bus Coupler and Bussection
-110kV Busbar Protection
-Auto Voltage Regulator
-ABTS
-ACCS
-Under voltage and under frequency
-Interface Alarm Panel
-Fault Recorder Alarm check
Protection relay
-ABB tranformer differential relay RET670
-ABB BCU & overcurrent relay REF615
-ABB BCU & relay REC670
-Siemens Overcurrent 6SJ
July 2011
To December 2011
Trainee Project engineer
at Al Osais Inabensa
Location :
Saudi Arabia - Jeddah
I have worked at Jeddah North West BSP, getting training about the Transmission standards relating substations. Apart worked with testing and commissioning contractor on technical activities.
Share on Facebook
Share on Twitter
Share Via Email