Johan van der berg, Project Controls Manager

Johan van der berg

Project Controls Manager

SNC lavalin

Location
South Africa
Education
Diploma, MDP Business Management / Project Management
Experience
33 years, 6 Months

Share My Profile

Block User


Work Experience

Total years of experience :33 years, 6 Months

Project Controls Manager at SNC lavalin
  • South Africa
  • My current job since April 2012

• Project Controls management on five projects which consist of Copper Smelter project, AGA SX Plant upgrade, ENRC and various Sasol petrochemical projects.
• Manage costing commitments and expenditures following cash flow procedures and ensuring accurate forecast reporting.
• Spearheaded the project management functions including estimating, risk assessment, quality control, cost control, scheduling, and project accounting on projects with great results.
• Set-up project support costing, estimating, forecasting and reporting in PM+ project management system for accurate reporting resulting in on-time and within budget project outcomes.
• Assist and lead on proposal development, risk analysis and project commencements.
• Engineering and construction progress and performance analysis, review and reporting.
• Deliver change management proactively and on a contingency basis as required on project.
• Leading, planning, organising and controlling project management outcomes by means of using the motivation triangle principle.
• Ensuring continuous development of human capacity and formal mentorship of young project controls personnel in cost control/engineering/ motivational estimating.
• Interface with Project Planners and integrating the quantitative scope and value of works with the project schedule in setting up the performance measurement baseline for earned value and progress reporting.
• By implementing continuous improved project control optimization by means of internal mandate control we managed to decrease project man-hour cost.

Project Controls & Assurance Manager at PaCE Services
  • South Africa
  • October 2010 to March 2012

• Managing and control of project services and project deliverables on ZAR 9 Billion Coal mining project.
• Continuously developing the human capacity and formal mentorship of young PACE project controls personnel in cost control/engineering/estimating.
• Implementing and maintaining costing standards, roles and procedures for effective project implementation and execution.
• Interfacing with Project Planners and integrating the quantitative scope and value of works with the project schedule into Costrac to set-up performance measurement baseline for earned value reporting.
• Planning, leading, organisation and control on Pace resource management and labour planning.
• Managing costing commitments and expenditures following cash flow procedures and forecasts.
• Improving processes on costing, planning, scheduling and project assurance reporting for increased profitability.
• Assisting and leading on proposal development, risk analysis and project commencements.
• Deliver change management proactively and on a contingency basis as required on project.
• Overseeing quality, cost and data management inputs and reporting for project assurance and risk mitigation resulting in positive project outcomes.
• Reduced the EPCM project cost on Medupi Expansion Project by optimising the EPCM roles and responsibilities by means of team integration and collaboration.

Project Controls Manager at Murray & Roberts Engineering Solutions
  • South Africa
  • January 2006 to September 2010

• Spearheaded the estimating, risk assessment, controlling, reporting of foreign exchange influences, market indices, and contract price adjustments on major contracts and making recommendations.
• Organising and implementing the project scope to supervise costing life-cycle delivery within the project and reducing cost.
• Responsible for detailed estimating, performing economic analysis, cost analysis and control, life-cycle costing, provision of comparisons with market-related costs, contracts administration, measurement and activity scheduling of multi-disciplined engineering projects.
• Continuously developing of human capacity and formal mentor ship of young project controls personnel in cost control/engineering/estimating and quantity surveying.
• Actively setting- up and maintaining essential standards and procedures.
• Involvement and interface with Project Planners and integrating the quantitative scope and value of works and activities with the project schedule into PRISM for executive management reporting.
• Review of price escalation analysis and reporting including Forex analysis through to financial close
• Deliver the management summary, project-level and control level schedules by means of integrated reporting.
• Manage costing commitments and expenditures following cash flow procedures and forecasts.
• Assisting and leading on proposal development, risk analysis and project commencements.
• Spearheading engineering and construction progress and performance analysis, review and reporting.
• Oversee and ensure accurate costing review and reporting of invoicing, accounts payable and receivable by means of implementing assurance management principals.
• Actively delivering change management proactively and on a contingency basis as required on project.
• Planned and fully implemented PRISM Project manager cost system on Goedgevonden Project and managed to optimize project control and reporting through earned value methodology with great success.

Lead Cost Engineer at Fluor
  • South Africa
  • January 2004 to December 2005

• Projects controls and reporting on ZAR 14 Billion project turbo project in Secunda.
• Metric and trending reports on monthly man-hours on construction and engineering.
• Compensation events, change management and contract administration on NEC contract methodology.
• Roll-up to the total cost of the project in accordance with the work breakdown structure.
• Formalizing the project code structure and preparing the Work Breakdown/Network Activity.
• Structurige and issuing project code of accounts and providing regular updates of Master data.
• Preparing, issuing and maintaining project cost and work-hour reports. Analysing, evaluating and forecasting project costs and variance.
• Establishing budget and tracking, reports and analysing actual cost versus the budget.
• Managing value engineering techniques, earned value analysis, risk assesment and analysis, financial modelling, and compensation event assessments.
• Investigating causes of variances between estimated, committed and actual amounts and recommending solutions or recovery plans.
• Measuring progress and reviewing invoices of contractors to provide independent judgment for progress reporting and payment.
• Reviewing purchase order and subcontract commitments and expenditures in the Project.
• Performing cost sampling and analysing the results to validate or modify the cost forecast.
• Performing initial and on-going Risk and Contingency Management activities.
• Administering the incentive program and making recommendations for improved profitability.
• Coordinating and directing the estimating functions on projects to provide guidelines and reports for responding to client and project management requirements.
• By successfully implementing benchmarking, trending and metric reports on project turbo we managed to optimise project delivery resulting in cost savings.

Lead Project Cost Engineer at Read Swatman and Voigt - Head Office
  • South Africa
  • January 1999 to December 2003

• Leading, organisation and controls of site cost engineers, planners and estimators on various platinum mining projects.
• Introduced metric and trending reports on monthly construction and engineering man-hours.
• Managing compensation events, change management and contract administration processes and procedures and making recommendations.
• Actively liaison with clients, on time and cost adherence and business analysis reporting.
• Formalizing the project code structure and preparing the Work Breakdown/Network Activity.
• Structuring and issuing project code of accounts and providing regular updates of Master data to project stakeholders.
• Preparing, issuing and maintaining project cost and work-hour reports. Analysing, evaluating and forecasting project costs and variance.
• Establishing budget and tracking, reports and analysing actual cost versus the budget.
• Investigating causes of variances between estimated, committed and actual amounts and recommending solutions or recovery plans.
• Reducing cost by measuring progress and reviewing invoices of contractors to provide independent judgment for progress reporting and payments.
• Reviewing purchase order and subcontract commitments and expenditures in the project and reporting against budget.
• Maintaining the project cost savings program.
• Performing initial and on-going Risk and Contingency Management activities.
• Producing monthly cost reports and controlling changes to the project budget.
• Set-up of weekly and monthly Project Reviews meetings.
• Coordinating and directing the estimating functions on projects to provide guidelines and reports for responding to client and project management requirements.
• Implemented benchmarking, trending and metric reports on monthly mining construction and underground development resulted in optimised mining production and cost savings.

Mining Superintendent at Lonmin
  • South Africa
  • January 1991 to December 1998

• Planning, leading and control of production and safety targets platinum mine and reporting to general manager.
• Responsible for management and control of operational and CAPEX budgets.
• Compilation of financial, profit and cost reports for scrutiny and profitability.
• Leading and control of all service departments in supporting logistical and services to production units.
• Leading the planning and scheduling of new mining activities and expansion projects.
• Overseeing the accurate cost estimation of new expansion mining projects.
• Overseeing expediting and procurement activities for all services departments.
• Organising monthly cost and budget reviews in controlling expenditure for all mining departments.
• Organising monthly reconciliation and cost analysis in relation with production to increase profitability of business units.
• Managing resources for the implementation of the planning, scheduling and costing for shafts and capital expansions.
• Successfully implemented the budget mass recorder.
• My core competence is vested in good management, computer, costing, budget and interpersonal skills for competitiveness, with great results.
• Received Supervisor of the Year Award for excellent production and safety targets achieved during 1995.

Education

Diploma, MDP Business Management / Project Management
  • at Univeristy of Stellenbosch
  • April 2014
Bachelor's degree, Business and Financial Management
  • at University of South Africa in Gauteng, South Africa
  • April 2012

Subjects • Accounting • Financial Management • Business Management • Commercial Law • Economics

Diploma, Primavera P5 - Project Planning and Scheduling
  • at Enterprise Project Solutions
  • November 2006
Diploma, PMP, Project Management Professional
  • at BRP Project Management
  • December 2005

Level PMP (Project Management Professional) Institution BRP Project management in Johannesburg, South Africa Subjects • AQF Level 5 Project Management • Project integrative processes • Scope Management • Time Management • Cost management • Quality Management • Human resources management • Communications management • Risk Management • Procurement Management

Diploma, Learner Official Mining Engineering
  • at Department of Minerals and Energy
  • December 1998

Mine overseer Cerificate of Competency - Mining (G.C.C) Subjects: • Loss Control • Mine management • Rock mechanics & Strata control • Geology • Mining Engineering • Mechanical & Electrical Engineering • Survey & Sampling

Specialties & Skills

Primavera
MS Project
Management
Cost Engineering
Project Management
CHANGE MANAGEMENT
COMPENSATION EVENTS
COST ANALYSIS
ESTIMATING
FORECASTING
PROGRESS
RISK ANALYSIS
PLANNING AND SCHEDULING
CONTRACT MANAGEMENT
EARNED VALUE

Languages

Afrikaans
Expert
English
Expert