• Coordinated daily project activities between engineering, procurement, and construction
teams.
• Assist the Project Manager in preparing project schedules, work plans, and progress
reports.
• Extracted Material Take-off (MTO) quantities from piping isometic drawings for bulk
material procurement.
• Performed material reconciliation by comparing supplied materials against approved
MTO quantities.
• Maintained accurate material tracking record to ensure availability and prevent project
delays.
• Prepared and maintained the fabrication index by tracking drawing quantities, total
number of joints, diameter-inch (DI) calculations, and weld counts.
• Coordinated with fabrication and QA/QC teams to ensure accuracy of joint and weld
records.
• Monitored the project's progress and highlight risks, delays, or resource issues.
• Review drawings, technical documents, and specifications for coordination purposes.
• Ensure proper distribution and tracking of drawings, RFIs, submittals, and approvals.
• Support site teams with technical clarifications and documentation.
• Coordinated piping and structural support installation activities in accordance with
approved General Arrangement drawings and 3d model.
• Identified and proposed site-driven modifications when design conditions were
impractical, securing approval from Engineering and Operations prior to
implementation.
• Prepare weekly and monthly progress reports.
• Developed and implemented project reporting templates including DWR, Fit-up reports,
etc.
• Track milestones, deliverables, and action items.
• Maintain project logs (correspondence, RFIs, submittals, change orders).
• Coordinated daily teams meetings, conducted progress briefings to monitor work status,
resolve issues, and align construction activities with project schedule and follow up on
action items.
• Ensured timely flow of information among all project parties.
• Performed piping loop preparation based on P&ID and Isometric drawings in
accordance with design and temperature ratings.
• Developed and compiled Hydrotest Index and Test packs for Pressure testing activities.
• Coordinated with QA/QC and construction teams to ensure readiness for hydrotesting
activities.
• Prepared and tracked pre-commissioning action items, ensuring system readiness and
compliance with project requirements.