Contract NO. PIC R-7519, Construction and upgrade of TAMA road (from T5 to flood channel) phase 2- Client:
Royal Commission-Yanbu, Consultant: Parson
Managed an infrastructure project and led a diverse team of professionals including Engineers, Designers, Quantity Surveyors, Vendors, and Contractors Acts as the Company representative to the client and interfaces frequently with both concerning progress issues
Provided the overall leadership for the execution of successful outcomes on projects assigned by the Company.
Regularly report out on progress and escalate issues as needed
Reviewed and approved Contractor Progress Payment applications
Supervised and mentored the whole team plus a range of subcontractor's.
Prepared the monthly report, cash flow and subcontractors’ payments. Led Weekly Progress Review Meetings and ensured construction stays on schedule and issues are addressed in a timely fashion.
I have worked as a Project Management Director, overseeing a variety of projects including construction of roads, buildings and maintenance, owned by various ministries which ranging from SR 20 million to SR 100 m.
Developed internal company visions for future project management practices that in line with the vision of the Kingdom 2030, and generate the strategies and resources required to achieve it.
Leading The company effort in create and developed a project management system that accommodates and benefits from modern information exchange systems by adopted and operated (ERP), for efficiency in time and cost by hire right professionals in the fields of scheduling, modeling and IT.
Created and developed project management office (PMO), to achieve process efficiency, hired staff, defining responsibilities, delegation of authority, policy development, procedures to guide engineers (project managers) and to support follow-up system.
Supervising the project control team to maintain high quality of gathering information from different projects to create reports that help upper management take right decision on time.
Leading the rehabilitation of sub-contractor’s process.
Projects:
General contractor with about 2, 000 employees engaged in roads and bridges projects.
Construction of Group # (21st). Client: Transport Ministry, Consultant: Saudi Tech Engineering & Geological Consultants
Managed roads and bridges project portfolio (DOT, 200M SAR) and led a diverse team of professionals including Engineers, Designers, Quantity Surveyors and Contractors
Reviewed the design, supervised planning and scheduling process. Motivated project teams to achieve project deliverables on time, and ensured it is complying with design, specifications and requirements.
Managed all aspect of project like, risk, scope, schedule, budget and communications
Oversaw all aspects of the day-to-day management, maintain quality, communicated with the Client’s representatives and consultant regarding Project Progress and areas of concerns.
Prepared the monthly report, cash flow and subcontractors’ payments.
Used P6 & Earned Value to control the execution time and cost in addition to the quality.
Information Technology & Management Company, worked with small and mid-size companies.
Collected requirements to help organization plan its strategy in project management for future growth.
Helped organizations adapted project management tools (software & ERP) for better business results.
Assisted clients identify project objectives, managed projects by determine the right tools to do so.
Sub-contractor (fit-out) of Harkins builders engaged in commercial and residential construction
Projects:
Planned, organized, control and oversaw site operations and construction activities for fit-out (Dry wall and painting)
for the following project:
1/ St Vincent’s Center.
2/ University Gardens.
3/ Bright view South River.
4/ Glassboro Student Housing.
Work Duties/Responsibilities
* Gathered key information from Project team to establish schedule and enforced the technical specifications.
* Planned, organized, control and oversaw site operations and construction activities for of the following project:
* Scheduling, project budgeting and preparing cash flow.
* Managed cost using earned value to monitor the progress.
Prepared schedules and managed resources
Reviewed Job Costs with Project Manager on a monthly basis
Reviewed Job Costs with Project Manager on a monthly basis and control the expenses.
Coordinated the project needs to be delivered on time to maintain maintenance schedule.
Planned the pre-construction activities in early stage of the project life cycle.
Coordinate internally within the company and externally with the client to kept project on track.
Developed time schedule and priority list for work to be accomplished.
Assigned duties to the project execution team and maintain productivity rate up to the expectation.
Led the planning, scheduling, budgeting the work.
Reviewed the design and make sure the drawings in compliance with DOT code and policies.
General Building Construction Company
Construction of French troops barracks & Rapcon tower in Prince Sultan Air base Al-kharj, Client: (DOD),
Main contractor: Northrop Grumman, consultant: Otishan Consulting Engineers.
Work Duties/Responsibilities
* Applied the American general contractor (Northrop Grumman) quality policy for each structure and set the
plan and the procedure to be followed to control the quality.
* Checked the quality plan for Accommodation Buildings, coordinated field test, inspections and documented
it in QC reports, for compliance with Northrop Grumman system and procedures.
* Observed on-site materials tests for compliance with standards, and coordinated special inspection and
testing performed by third parties.
* Initiated Non-Conformance reports (NCRs), and wrote inspection reports.
* Took care of QA/QC documents of the entire project including certificates, calibration, test results and
inspection requests.