Khurram Rehman Siddiqui, Project Manager MEP

Khurram Rehman Siddiqui

Project Manager MEP

OMAN National Engineering and Investment ompany (ONEIC)

Location
Oman
Education
Bachelor's degree, BE ELECRICAL ENGINEERING (POWER)
Experience
18 years, 5 Months

Share My Profile

Block User


Work Experience

Total years of experience :18 years, 5 Months

Project Manager MEP at OMAN National Engineering and Investment ompany (ONEIC)
  • Oman - Ibri
  • My current job since February 2023

Work Summary:
• Defining project scope, objectives, and deliverables, and obtaining necessary approvals.
• Planning, scheduling, and coordinating projects from initiation to completion, ensuring project objectives are met in line with quality standards and customer expectations.
• Monitoring project progress and performance, and making necessary adjustments to ensure project goals are achieved. Performing change management
• Producing reports for stakeholders and management.
• Communicating with stakeholders to identify and address project risks, issues.
• Building and leading project teams, assigning roles and responsibilities, and fostering a collaborative work environment.
• Developing and managing project budgets, timelines, and resources.
• Monitoring expenditures, and making necessary adjustments to stay within budget constraints.
• Conducting project evaluations and reviews, and using findings to inform future project planning and execution.

Project Manager at Majan Electricity Company (MJEC)
  • Oman - Sohar
  • November 2014 to July 2021

• Construction of 132/33kV Yanqul Grid Station.
• Upgrading Wadi Al Owainah and Wadi Al Jel Power Substations in North Batinah |2021
• Construction of Sohar Port PSS and Outdoor Substation | 2020
• Electrical upgrades totalling US$10.28M, including cable installation, grid station construction, feeder interlinks, and substation upgrades in multiple locations. | 2019
• Electrical grid infrastructure improvements consisting of feeder transfer, power substation construction, feeder/cable installation, and building construction, totalling US$11.3 million | 2018
• Electrical upgrades and construction projects, including substation upgrades, new substation construction, and feeder installation, costing US$10.2M | 2017
• New construction of four power substations and installation of interlink and cable feeders costing US$11.59M, with direct connection to Sohar Grid | 2016
• Power substation upgrades and construction, encompassing transformer upgrades, new feeders, and transformer refurbishment, totalling US$10.8M | 2015

Assistant Executive Engineer at Pakistan Steel Mill
  • Pakistan - Karachi
  • September 2006 to November 2014

 OPERATION & MAINTENANCE Head in Power Distribution Network Department in relevance with 132KV, 11.5KV &6.6 KV and to ensure the uninterrupted power supply for steel process.

 Operation & Maintenance of 24 distribution substations (11.5KV&6.6KV) located in various complexes of Pakistan Steel Mills.

 Switching for Emergency as well as schedule maintenance, Modification, Revamping and Installation work of High Tension Bus Bars (11.5/6.6KV), Circuit Breakers (2500A, 1250A & 630A) and Power Transformers (63MVA, 10MVA, 6.3 MVA, 1600kVA, 1250kVA, 1000kVA, 750kVA, 500kVA) during shut down of steel process units.

 Monitoring and maintaining the power supply (11.5/6.6kV) being generated at native Thermal Power Plant (TPP) possessing the capacity of 165MW.

 Supervision of cable tunnels, basements, galleries, trenches, transmission lines (132kV) and feeders (11.5/6.6kV) and lying of Cables up to 11kv supplying power to Pakistan Steel.
 Coordinating with K-Electric (Karachi Electric Supply Company) and TPP for load management scheme in case of short fall of electrical power or in event of any failure/break down of 132kV electrical system.
 Execution of cable joints (Heat Shrink) of 11.5/6.6kV power supply during cable faults in electrical system.
 Installation of Street Lighting System in the Industrial Premises.
 Leading and supervising the team of 120 Persons in order to achieve the required task.
 Record keeping and Reporting of all the technical documentation procedures regarding above said works such as technical work order, work permission, energy consumption report, tripping reports and filling of the log book regarding events, which occur in the assigned functional area.

Project Engineer at AS Consultants
  • Pakistan - Karachi
  • June 2004 to September 2006

 Load calculation and installation of switchgear, substations and lighting system of industrial and residential Areas.
 Selection of C.Ts, P.Ts and Cables and accordingly installation and lying of the same.
 Selection and Installation of power and distribution transformers.
 Preparation of tender documents.

Education

Bachelor's degree, BE ELECRICAL ENGINEERING (POWER)
  • at QUAID E AWAM UNIVERSITY OF ENGINEERING SCIENCES AND TECHNOLOGY
  • December 2004

Specialties & Skills

Issues Resolution
Management
Negotiation
Tender Process
ELECTRICITY
MANAGEMENT
CHANGE MANAGEMENT
PLANNING
TIMELINES
PROJECT PLANNING
SCHEDULING
CONTRACT MANAGEMENT
Operation & Maintenance of Electrical Network
Technical
ISO 9001-2008
Project Management
Negotiations
ISO 55001
Environment Management System

Languages

English
Expert
Urdu
Native Speaker
Arabic
Beginner
Hindi
Intermediate
Punjabi
Intermediate

Training and Certifications

ISO 14001-2008 (Training)
Training Institute:
Environment Management System
Date Attended:
February 2008
Duration:
18 hours

Hobbies

  • Cricket and Books